The Take-Off Nobody Enjoys
Ask an estimator which part of a job is most often guessed and many will say the services. Walls and roofs are big and obvious; the outlets, switches, light points, fixtures and the runs of cable and pipe between them are small, numerous and spread over every room. They are usually counted with a coloured pen on a printout, a tally in the margin and a length scaled off with a ruler, and a missed room shows up only when the electrician asks for more cable.
The Construction Canvas treats services as two kinds of thing. A point is anything you count: an outlet, a switch, a light, the panel, a fixture, a drain, a radiator, a register. A route is anything you measure: a cable, a pipe or a duct, drawn as a line from point to point the way it would be fixed. The list counts the points by kind and works the routes into lengths to buy, bends, supports and stock lengths or coils.
The worked example is the flat-services template: a one-bedroom flat about 8 by 6 metres (26 by 19 feet 6 inches) inside, rewired and replumbed over its existing walls.
Walls That Hold the Plan, and Nothing Else
A rewire or a replumb works inside walls that are staying. The canvas needs the walls to show where the rooms are, but it should not count studs for them. Draw them without a type: an untyped wall is drawn and measured on the plan but brings no rows to the list. If you have a PDF of the flat, put it under the drawing and calibrate it first, then trace the walls quickly over it; the points and routes are what matter.
If the job also adds walls, a new partition for a bathroom say, draw those with a type and they will be counted as normal while the existing ones stay silent.
Points First, Room by Room
Go round the plan one room at a time and drop every point with the services tool, choosing its kind as you place it. Outlets come as general, protected, weatherproof or dedicated to an appliance; lights as ceiling, recessed, wall, outdoor or a fan; switches for one place, two places or a dimmer; fixtures as a WC, a basin, a sink, a shower, a bath, a washer or dishwasher connection, a water heater or an outside tap. The list counts each kind separately, which is how the trades and the merchant want them.
Place the panel and the water heater first, because every route starts at one of them. Then the kitchen, which has the densest set of points, then the bathroom, then the other rooms. Ask each room for the minimum number of outlets the spacing rule gives for its wall length and compare it with what you drew; the rule is a floor, not a design, and most kitchens want more.
- Trace the walls without a type, or put the plan under the drawing and trace over it.
- Place the panel and the water heater.
- Drop the points room by room, each with its kind.
- Compare each room's drawn outlets with the spacing rule's minimum.
Then the Runs, the Way They Would Be Fixed
Draw each route as an open line from its source to its last point, clicking at every change of direction. Follow the path the cable or pipe would really take, along a wall, through a ceiling void, up to a fixture, rather than a straight line across the room; the length to buy is the drawn length plus the rises and drops you type and a tail at each end, so a route drawn as the crow flies under-counts every time.
Give each route a type. For cable, the product decides how often it must be supported: the canvas cites the electrical code's spacing for NM cable at 4 1/2 ft (1.37 m), MC cable at 6 ft (1.83 m) and EMT conduit at 10 ft (3.05 m), and asks you for the spacing of products whose table it could not read at source. For pipe it cites the plumbing code's hanger table, with PEX at 32 in (0.81 m) level and copper and plastic further apart. Every corner is counted as a bend, every support at that spacing, and the length is rounded up to the coils or stock lengths the product comes in.
Ducts work the same way with a duct type: a rectangular or round duct listed as sheet metal by its surface area, with its mastic round every joint and its hangers along the run, and its sections and elbows counted. The laundry-room template's vented dryer shows a short round duct drawn this way.
Reading What the List Gives You
The list now has three kinds of line. In the electrical and plumbing sections, one row per route type gives the length to buy from the service run page, with its working. Underneath, the counts give every point by kind, then for each route type its bends, its supports and its coils or lengths. That is a material schedule an electrician or a plumber can check line by line against their own experience of the job.
Try a change to see what it moves. Switch the supply from PEX to copper and the length stays the same while far fewer supports are counted. Run the circuits in EMT conduit instead of NM cable and the supports drop again. Move the water heater to the other side of the kitchen and the supply run's length changes with it. These comparisons are where drawing beats counting: each takes a click, and each answers a question that would otherwise go to site.
Checking the Count Before It Goes to the Trades
A services take-off is easy to get almost right and hard to get exactly right, because one missed bedroom or one bathroom drawn twice is lost among dozens of small points. Before the list leaves your desk, walk it against the plan in three passes. First the rooms: every room on the plan should have at least one light and one switch beside its door, and every habitable room its outlets; a room with none usually means the points were dropped on the wrong level. Second the wet areas: each fixture that takes water should sit at the end of a supply run, and each one that drains at the start of a waste run; a basin with no pipe to it is a run you forgot to draw. Third the routes: each cable run should begin at the panel or at a point already fed, never in the middle of a wall.
Then compare the totals with the job's own scale. A one-bedroom flat with a few hundred metres (several hundred feet) of cable has a route drawn back and forth over itself; one with a handful of metres has circuits missing. The supports count is a useful cross-check here: it rises with length at a fixed rate for each product, so a supports figure far out of step with the length points straight at a route given the wrong type.
Finally, read the counts as the people who will install them do. An electrician wants outlets, switches and lights by kind and by room, and the cable by type and reel; a plumber wants fixtures, pipe by material and stock length, and fittings. The canvas groups its counts the same way, so a sentence in your message to each trade can point at a section of the list rather than restating it.
A House, Not a Flat
The same method scales to a whole house: a level per storey, the points on each, and routes that climb between levels with their rises typed in. Draw the main runs first, the feed from the panel to each floor and the supply riser, and fill in the branches after. Keep cable and pipe on their own layers if the plan gets busy, so you can hide one while drawing the other; hidden layers are not snap targets, so a pipe will not jump to a cable's corner.
The Design Is the Trade's
The canvas counts what you draw and never sizes it. How many circuits the home needs, the cable and breaker sizes, the protection devices, the pipe diameters, the waste falls and vents, and whether a run may pass through a fire-rated wall are the electrician's and the plumber's designs under the electrical and plumbing codes, and most places require licensed installers and an inspection. Use the list to plan, compare and order; let the trades confirm the design before anything is fixed.
Try the calculation
Check a run and a room
These are the pages behind the services rows. Check one route's length and one room's outlets against them.
- A route's length to buy — The service run page for a run's length, rises, tails and stock.
- Outlets the rule asks for — The outlet spacing page for a room's wall length.
- Duct hangers — Hangers along a duct run at the spacing its table allows.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.