Crane Lift Utilisation Calculator

Total lifted load against the rated capacity from your load chart, as a utilisation percentage with the rigging and block included.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
Read from YOUR crane's chart, at this radius and configuration.

Capacity is specific to the machine, the boom length, the radius, the counterweight, the outrigger extension and whether it is on tyres or fully set up. This calculator will not generate it — the chart for the actual machine is the only valid source, and a figure taken from a different configuration is a wrong number that looks right.

Mass of the item being lifted.

Verify it. A drawing weight, a delivery note and the actual item disagree more often than anyone expects, and water in a vessel or trapped in a section is a classic overload.

Slings, shackles, spreader beam, lifting frame.

A spreader beam is frequently several hundred kilograms on its own and is the item most often left out of the sum.

The block reeved on the machine.

Deducted from capacity on most charts. Include the auxiliary head or jib too, whether or not it is in use — it is on the boom either way.

Allowance for wind and dynamic effects.

Wind on a large flat load can be very large, and it acts on the surface area, not the mass — a light panel can be the harder lift. Above the manufacturer's stated wind speed the lift stops, and no percentage allowance substitutes for that limit.

Chart utilisation

70.8 %

ComparisonA comparison, not a check — no result here is an approval.

Within capacity for the chart figure entered. This is arithmetic, not a lift plan.

Gross lifted load
12,485 lb
Rated capacity
17,635 lb
Margin remaining
5,150 lb
Load alone as a share of capacity
56.25 %
Rigging, block and allowance
2,565 lb
Gross load in tonnes
5.66 t
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Rated capacity is read from the crane's own load chart for the specific configuration, radius and boom length — it is not derived here
  • ASME B30.5 and common practice: gross load includes the load, all rigging, the hook block, and any jib or auxiliary head, whether in use or not

Inputs used

Rated capacity from the load chart
17635 lb
Load mass
9920 lb
Rigging mass
550 lb
Hook block and ball
880 lb
Dynamic and wind allowance (%)
10

Intermediate steps

Gross lifted load
12,485 lb
Rated capacity
17,635 lb
Margin remaining
5,150 lb
Load alone as a share of capacity
56.25 %
Rigging, block and allowance
2,565 lb
Gross load in tonnes
5.66 t
Final result70.8 %

Confidence note: Within capacity for the chart figure entered. This is arithmetic, not a lift plan.

What this calculation does not cover

  • This is arithmetic on figures you supply, not a lift plan and not an engineering approval. A lift plan covers ground bearing, proximity hazards, exclusion zones, wind limits, the rigging arrangement and the sequence — none of which is here.
  • Rated capacity must come from the chart for the actual machine in the actual configuration. Radius, boom length, counterweight and outrigger extension each change it, sometimes dramatically.
  • Wind is not modelled. It acts on the load's surface area rather than its mass, and a large light panel can be a harder lift than a small heavy one. The manufacturer's wind limit is a stop, not a factor.
  • Ground bearing pressure under outriggers or tracks is a separate and frequently governing check.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-08-27 · in the site-wide review of 2026-09-06 · v1.1.0

Regulatory standards & verification citations2
  1. Rated capacity is read from the crane's own load chart for the specific configuration, radius and boom length — it is not derived here
  2. ASME B30.5 and common practice: gross load includes the load, all rigging, the hook block, and any jib or auxiliary head, whether in use or not
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

Still deciding? Sling Angle vs Crane Capacity — the factors that actually differ, with no invented prices.

How to calculate crane lift utilisation in 6 steps

  1. Rated capacity from the load chartRead from YOUR crane's chart, at this radius and configuration.
  2. Load massMass of the item being lifted.
  3. Rigging massSlings, shackles, spreader beam, lifting frame.
  4. Hook block and ballThe block reeved on the machine.
  5. Dynamic and wind allowance (%)Allowance for wind and dynamic effects.
  6. Chart utilisationThe tool computes the chart utilisation from those figures and shows the formula, its sources, and a confidence rating alongside it.

Chart utilisation by rated capacity from the load chart

Page defaults, not your figures above.

Rated capacity from the load chartChart utilisation (%)
10,000 lb125
15,000 lb83.3
20,000 lb62.4
25,000 lb50
30,000 lb41.6
35,000 lb35.7

Frequently asked questions

Why does this not calculate the crane's capacity?
Because capacity comes from the machine's own load chart and nothing else. It changes with radius, boom length, counterweight, outrigger extension, whether the machine is on outriggers or on tyres, and the specific model. There is no formula that produces it, and a site that generated one would be inventing the single number the entire lift depends on. Read it from the chart for the machine you actually have.
What gets forgotten in the gross load?
The spreader beam, most often — several hundred kilograms of lifting frame that nobody counted. Then the hook block, which most charts deduct rather than include. Then a jib or auxiliary head that is stowed but still hanging on the boom. And water: rain collected in a vessel, or trapped in a hollow section, has overloaded more than one lift that was calculated correctly on the dry weight.
Is 75% a rule?
It is a common threshold in lift planning schemes above which a documented plan and an appointed person are required, and it is a sensible point to stop and verify the load mass independently rather than trusting a drawing. It is not a universal legal limit — check the scheme that applies to your site. What is universal is that above 100% the lift does not happen.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.