Steel

Taking Off a Steel Package for Tender: the Tonnage and the Painted Area

A frame drawing gives you lengths, not weights, and never gives you area. How to close both columns on the afternoon before the return goes in.
  • 21 minReading time
  • 10Sections
  • 2Calculators inline
  • Last reviewed

Half past three, and the frame is still four PDFs

What came down with the enquiry is a general arrangement at 1:100, two elevations, one cross section, a sheet of general notes and a specification clause saying the protective treatment is to ISO 12944 for corrosivity category C3 at medium durability. There is no mark schedule. There is no bill. Fabrication drawings happen after award, which is the whole difficulty: the return is due at noon and it wants a fabricated tonnage and a quantity of shop primer, and both of them have to be produced from a drawing that was never drawn to be measured.

The reflex at this hour is to get the tonnage settled, because tonnage is what the rate hangs off, and then to reach for last job's paint allowance as so many litres per tonne. That second move is the one that quietly loses money, and it loses it in whichever direction the section mix has moved. Coating is bought by the square metre and steel is sold by the tonne, and the number connecting them is not a constant of steelwork — it is a property of this particular package, set by how heavy the average section in it happens to be. A frame of stocky columns and a frame of light bracing and rails can differ by a factor of three or four on painted area for the same weight, and nothing on the drawing announces which one you are looking at.

So there are two takeoffs to run before noon and only one of them is about weight. What follows is the order they go in: lengths off the arrangement, then the steel that is in the package and not on the plan, then the tally closed into a tonne, then the same member list turned sideways to measure its skin. How a per-metre mass is derived for a section whose designation does not carry one — an imported angle, a cold-formed rail, a cut-down beam — is a separate exercise with its own guide on this site, and this page assumes that column is already filled in.

One steel, two geometries

The reason the ratio moves is a piece of geometry rather than a piece of estimating. Mass per metre follows the cross-sectional area of the shape. Coating per metre follows the perimeter of the same outline. Grow a section and its area grows roughly as the square of the linear dimensions while its perimeter grows as the first power, so surface area per tonne falls as the steel gets heavier, and it falls steeply. That single relationship is behind every mismatch between a weight takeoff and a paint takeoff, and once it is in front of you the rest of the afternoon organises itself.

It bites hardest at the ends of the range, which is where real packages sit rather than in the comfortable middle: a shed frame is mostly light purlin, rail and bracing and its skin is enormous for its weight, while a short-span transfer structure is a few heavy columns and deep girders and its skin is small. Price both with one litres-per-tonne allowance and you are wrong twice, in opposite directions, by more than the margin on the paint line. The fix is not a better rate but a second quantity, measured from the member list the tonnage already needed.

Gridlines are not member lengths, and on a tender that is fine

Beams get measured grid to grid because that is what the drawing dimensions, and grid to grid is not the length that gets cut. A beam framing between two column centres is short by half the depth of the column at each end, and short again by the erection clearance the detailer leaves between the beam end and the column face. On a 6 m bay into 254 mm columns the two half-depths alone come to 254 mm, and a ten millimetre erection gap at each end takes it to 274 — better than four percent of the bay, measured and never fabricated. Take it anyway. A tender takeoff that runs a few percent over on member length is on the safe side of the only error that matters at this stage, and the alternative is deducting connection allowances from every beam on the plan with two hours left, for an accuracy nobody is going to check against a drawing that does not yet exist.

Columns are the ones to slow down on, because their length is the dimension the plan does not carry at all and the one people most often take from the wrong place. A column runs from the underside of its baseplate to the top of the section, which is neither floor to floor nor level to level: it starts at the top of the foundation or the top of the pocket, picks up the grout space beneath the plate, and finishes at whatever the roof or the next splice actually requires, which on a portal frame with a haunched eaves is well above the eaves level everyone quotes. Read those off the section and the elevations, not off the level schedule, and read every column rather than assuming the row is identical, because the one on the grid line where the ground falls away is longer than its neighbours and it is longer by more than you would guess.

Anything on a slope wants its true length rather than its plan projection, which sounds too obvious to write down until the third hour of a takeoff. A rafter across a 12 m span at a modest pitch is measurably longer than 12 m along its own line, and a diagonal in a braced bay is the hypotenuse of the bay rather than either dimension anybody quoted. Both get measured flat off a plan by tired people. Set the rule at the start of the sweep and hold to it, because it is not a judgement you want to be making member by member at five o'clock.

Keep the count as you go, in a column beside the lengths, because the piece count is a quantity in its own right and it is not recoverable from the tonnage afterwards. Fabrication hours, handling, painting setups, transport and the erection sequence are all driven by how many pieces there are rather than by what they weigh, and the tonnage divided by the count gives an average piece weight that tells you more about the character of the job than the tonnage does. A package at half a tonne a piece and a package at eighty kilograms a piece can carry the same total and are not the same contract.

  1. Print or open the general arrangement at a fixed scale and mark up in colour as you go, so a member that has been measured is visibly different from one that has not.
  2. Take beams grid to grid without deducting for column depth or connection clearance, and write on the sheet that you have done so, so the number is a decision rather than an oversight.
  3. Measure every column individually from underside of baseplate to top of steel, off the section and elevations, and never off the floor-to-floor levels.
  4. Take every sloping member — rafters, braces, valley and hip steel, stair strings — at true length from an elevation or by computing it, never by scaling the plan.
  5. Keep a piece count in its own column next to the length column; you will need it for handling, painting setups and loads out, and it cannot be recovered later.
  6. Group by mark or by section size rather than by grid line, so the per-metre mass column can be filled in once per group instead of once per member.
  7. Close the loop before you total anything: every column has to appear on two elevations and one plan, and every beam has to land on something at both ends.

The steel that is in the package and not on the plan

The framing plan shows the frame, and the frame is not the package. What is missing is rarely a beam anyone would notice missing; it is a category — a whole class of member that lives on a different drawing series, in an architect's detail, in the cladding subcontract, or nowhere at all until the fabricator asks about it. Those categories are where a tonnage goes wrong by a margin no amount of careful measuring on the visible steel can recover, because the error is not in the measurement, it is in the scope.

Work the categories deliberately rather than hoping to notice them. Read the general notes, then the specification's scope clause, then the drawing register itself, and ask of each line whether steel appears on it. A register with an S-series and an SK-series where you have only opened the S-series is the commonest way half a secondary package goes unmeasured. Where the answer is genuinely unresolvable in the time available, that is a qualification rather than a guess.

Categories of steelwork that a framing plan does not show, and where each of them is actually documented
What is missingWhere it lives insteadHow it goes unmeasured
Purlins, side rails, sag rods, eaves beams and their cleatsA separate secondary steel drawing series, or the metal building supplier's own layoutThe primary plan is complete and self-consistent, so nothing on it suggests a second series exists
Trimmers and framing around roof openings, risers and stair wellsArchitectural and services drawings, often dimensioned nowhere on the structural setThe opening is drawn as a void with no steel around it until the shop drawings are done
Kickers, ties, restraint angles and stub columnsTypical details on a section sheet, shown once and noted as applying throughoutA detail marked typical is one line on a drawing and can be forty members in the package
Stair strings, landings, handrail posts and access platformsAn architect's stair detail or a specialist subcontract packagePriced as metalwork by one party and as steelwork by the other, or by neither
Holding-down bolt assemblies, shear plates and levelling packsThe foundation drawings and the groundworks packageCast into somebody else's concrete, so it is ordered by whoever remembers first
Temporary bracing and erection steel that never becomes permanentNowhere in the tender set; it belongs to the erection methodIt is real material and real hours and appears on no drawing at all
Categories of steelwork that a framing plan does not show, and where each of them is actually documented

Closing the length tally into a tonne

Two columns close it: total length by group, and the per-metre mass for that group. The second column is a transcription where the designation carries its own mass and a calculation where it does not, and how that calculation is done — along with how the groups are then combined into one figure without describing a package that does not exist — belongs to the section-weights guide on this site rather than to this afternoon. What belongs here is keeping the groups separate long enough to be useful in the first place.

Run the total twice and keep both. Primary steel on its own is the number that carries the frame rate and the number a client will recognise. Primary plus secondary is what leaves the shop and what the transport and erection lines are built on. Reporting a single blended tonnage when the enquiry may yet split those scopes is how a return gets compared against a competitor who did split them, and loses on a line that was never the same line.

Then check the answer by a route that shares nothing with the first one. The mark-by-mark tally is bottom-up and it fails silently: a missing category produces a total that looks entirely reasonable, because nothing about it is visibly incomplete. A top-down ratio — kilograms per square metre of framed floor, or tonnes per bay — has different failure modes, so it will never agree exactly and it will disagree loudly when something whole is absent. Build that ratio from your own recent jobs of the same structural form rather than from a published figure, because frame benchmarks swing with span, loading, storey height and bracing strategy far more than any general number admits.

Total length is the column the drawing gave you and the per-metre figure is the column the section tables gave you. Run the primary steel first, note the answer, then run it again with the secondary added — the difference between the two is a line you will be asked about.

The combined linear length of all steel members being tallied.

The average weight per unit length across the members being tallied.

Total steel tonnage

24.8 tons

High confidence
Total mass
49,591.31 lb

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

1640 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • The tonnage is a takeoff, not a purchase. Sections are bought in mill or stock lengths — commonly 12 m or 40 ft — and cut to suit, so what arrives is the sum of the sticks required rather than the sum of the member lengths, and the offcut is paid for either way. On a package with many short members that gap runs to several percent before a single hole is drilled.
  • A single total weight is the wrong basis for a price. Fabricated steel is quoted by weight, but the rate is set by how much work each unit of weight carries: light beams with heavy connections, copes, stiffeners and site bolts cost far more per unit of weight than the same weight in plain heavy columns. One average rate multiplied by this number misprices a light, connection-dense frame badly.

The perimeter the drawing never dimensions

Painted area is the same member list read sideways: perimeter of the cross-section, multiplied by length, multiplied by count. The perimeter is the one term nobody has handed you. Some section tables publish it directly — the SCI publication P363, the Blue Book, carries surface area per metre and surface area per tonne alongside the section properties for the UK series — and where the table you are using does not, the outline can be assembled from three dimensions you already have.

For an I section, an H section or a channel, the painted perimeter comes out as four times the flange width, plus twice the overall depth, less twice the web thickness. It is worth walking the outline once to see why, because the result is more useful than it looks: the two flange outer faces contribute two widths, the two flange inner faces contribute two more widths less the web that interrupts them, and the four flange edge thicknesses cancel exactly against the two flange thicknesses each of the two web faces loses at its top and bottom. Flange thickness drops out of the answer altogether. Two sections of the same serial size, one nearly twice the weight of the other, have very nearly the same skin.

Put two real sections through it and the spread stops being theoretical. Take a light beam of the 305 by 102 serial size at about 25 kg/m: with a depth near 305 mm, a flange near 102 mm and a web near 6 mm, the outline gives roughly 1.005 m of perimeter per metre run. A tonne of it is 40 m of steel, so a tonne of it carries about 40 square metres of skin. Now take a heavy column of the 305 by 305 serial size at about 198 kg/m: depth near 340 mm, flange near 315 mm, web near 19 mm, and the outline gives about 1.90 m per metre run. A tonne of that is a little over five metres of steel and carries under 10 square metres. Same family, same rolling mill, four times the paint per tonne.

The outline arithmetic ignores root fillets and toe radii, and it errs generously rather than meanly: a concave fillet is a shorter path than the square corner it replaces, so the true wetted perimeter runs a percent or two below the outline figure. On a tender that is the right direction to be wrong in. Two further distinctions are worth holding onto. Section factor tables written for fire protection quote a boxed perimeter as well as a profile one, and only the profile figure describes what a spray gun has to cover — take the box value into a paint quantity and you underbuy on every open section in the package. And connection material moves the two takeoffs in opposite directions: a gusset or a cleat is two broad faces of area for very little weight, so plate inflates painted area proportionally more than it inflates tonnage.

Painted perimeter by section family, assembled from dimensions the section table already carries
Section familyPainted perimeter of the outlineWhat it does to area per tonne
I, H and channel sectionsFour flange widths, plus twice the depth, less twice the web thickness — flange thickness cancels outFalls sharply with weight within a serial size, because the skin barely changes while the mass nearly doubles
Equal and unequal angleTwice the sum of the two leg lengths; the thickness cancels exactlyThe highest of the hot-rolled families — a thin angle is almost entirely surface, and a thick one of the same legs is painted identically
Rectangular and square hollow sectionTwice the sum of the two outside dimensions, less a small allowance for the corner radiiLow, because the bore is sealed and never coated — a closed section buys area cheaply
Circular hollow sectionPi times the outside diameterLow for the same reason; the perimeter is exactly independent of wall thickness, unlike the rectangle whose corner radii grow with it, so a change of wall moves the mass and nothing else
Flat plate and flat barTwice the width plus twice the thickness, or simply two square metres of coating per square metre of plateAbout 25 square metres per tonne at 10 mm, about 10 at 25 mm — thin plate is expensive to coat
Cold-formed purlin and railWeb, two flanges and two lips, counted on both facesThe highest in the package by a distance, and usually galvanised rather than painted, which takes it out of the paint quantity entirely
Painted perimeter by section family, assembled from dimensions the section table already carries

Read the coating clause before you price a litre

The specification decides the quantity long before any calculator does, and the clause is usually four facts in one sentence. ISO 12944-2 classifies the environment — C1 through C5 for atmospheric exposure, CX for extreme, Im1 to Im4 where the steel is immersed or buried — and ISO 12944-1 sets the durability bands the specifier then chooses from, low up to seven years, medium from seven to fifteen, high from fifteen to twenty-five and very high beyond that. Those two together point at a paint system in the ISO 12944-5 tables, and it is the system, not the environment, that tells you how many coats and what total dry film thickness the steel is going to receive. Reading C3 and stopping there leaves the most important half of the clause unread.

Surface preparation is the next line and it is a cost line, not a quality line, because it decides both the shop hours and how thirsty the steel will be. ISO 8501-1 defines the visual preparation grades — Sa 2.5 is the one most systems ask for — and the American equivalents are SSPC-SP 6 with NACE No. 3 for commercial blast and SSPC-SP 10 with NACE No. 2 for near-white. ISO 8501-3 covers the preparation of welds, edges and surface imperfections, which sounds like a detail and is not: it is the reason the specification also asks for stripe coats. A blast profile to ISO 8503 also consumes paint that never shows up as film thickness, because the first material applied fills the anchor pattern between the peaks before any measurable thickness accumulates over them.

Then subtract what is not being painted, because on most packages that is a real area rather than a rounding. Faying surfaces in slip-critical connections are either left bare or given a coating qualified for a slip class under the RCSC Specification for Structural Joints Using High-Strength Bolts, and either way they are masked in the shop. Steel to be encased in concrete is not coated. Steel receiving applied fire protection takes a compatible primer and nothing else from the paint scope, which is a separate quantity belonging to the fireproofing line. Site weld zones are held back and made good afterwards. AISC 303 on one side of the Atlantic, and BS EN 1090-2 with the BCSA National Structural Steelwork Specification on the other, are where those exclusions are conventionally written down; what matters this afternoon is that painted area is measured area less masked area, and on a heavily connected frame the difference is not small.

Square metres into litres, and litres into what you buy

The conversion is one identity and it is worth committing to memory rather than looking up. Theoretical spreading rate in square metres per litre equals ten times the volume solids percentage, divided by the specified dry film thickness in microns. A primer at 60 percent volume solids specified at 75 microns gives 600 over 75, or 8 square metres per litre. In imperial the same relationship reads as 1604 times the volume solids fraction divided by the film thickness in mils, giving square feet per gallon. Both numbers come off the product's technical data sheet, and the volume solids figure is the one to check, because two primers that look interchangeable on the shelf can differ by fifteen points of solids and therefore by a quarter of the material.

Theoretical is not what you buy. Between the tin and the film sits a list of losses that are individually modest and collectively decisive: overspray and transfer efficiency, which on airless spray applied to open sections with a lot of edge and very little face is the largest of them; the profile dead volume already mentioned; the film left in the pump, the hose and the pot; the stripe coats applied by brush to edges, welds and bolt heads, which are real litres against no measured area at all; the material lost to touching up handling damage after the coat has cured; and over-application, which is not sloppiness but arithmetic. SSPC-PA 2 sets out how measured dry film thickness is judged against a specified value, and its acceptance bands are the reason a competent applicator aims above nominal rather than at it — nobody targets the number they are allowed to fall below.

So the figure to put into a quantity is a practical spreading rate, and the honest way to produce it is to take the theoretical rate from the data sheet and divide it by your own loss factor from your own shop records rather than by a number found in a book. The same 8 square metres per litre becomes something nearer 5.6 at a thirty percent loss, and the difference across a package of a thousand square metres is the whole paint line. Run the same calculation once per coat, because a system is rarely one coat and the primer, the intermediate and the finish have different solids, different specified thicknesses and different losses. Adding the coats together at the end is not the same as running the total dry film thickness through once.

Perimeter, length and count are the three you already built for the tonnage, so this is the same list read sideways. Put in your practical spreading rate rather than the theoretical figure off the data sheet, and run it once for each coat in the specified system.

The full outside perimeter of the member's cross-section.

The length of each individual member.

How many identical members are being coated.

The coating's rated spreading rate, from its technical data sheet.

Primer/paint needed

1.42 gal

Medium confidence

Coverage rate varies significantly by product (primer vs. topcoat, surface profile) — confirm your specific coating's rated coverage from its technical data sheet.

Total surface area
568.75 ft²

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

19.5 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

What this calculation does not cover

  • A coverage rate is quoted at a stated dry film thickness, and the specification usually sets a different one. Coverage scales inversely with DFT: a product rated at 50 microns (2 mils) delivers two fifths as much area at 125 microns (5 mils), so entering the data sheet's headline figure against a thicker specified film understates the paint by the ratio between them. Take the rate and its DFT together, and check whether it is the theoretical figure or one already discounted for loss.
  • Nothing comes off for what never reaches the steel. Spraying open framework is inefficient in a way painting a wall is not — a large part of the fan passes between the flanges and the web and lands on the floor — and more stays in the pot, the hose and the tin. Blast-cleaned steel takes its share as well: a 50 to 75 micron surface profile has to be filled before any film builds over it, and the first coat pays for that.
  • Perimeter × length × count describes plain, straight, identical members. The gussets, cleats, end plates, stiffeners and base plates welded to them are extra area carrying far more edge per square metre than the members do, while the areas deliberately left bare — faying surfaces in slip-critical joints, weld preparations, and anything to receive sprayed fire protection — come back off. On a connection-heavy frame those two corrections do not cancel.

Two hours left: measure this, allow for that

Not everything on the drawing deserves the same care, and deciding that consciously is the difference between a takeoff that finishes and one that stops halfway with the columns done beautifully and the roof untouched. Columns and primary beams are most of the weight and are individually few, so measure them one at a time. Repetitive secondary is many pieces of small weight, so measure one bay properly and multiply, then check the multiplier against the bay count on the plan. Fittings, cleats, stiffeners and connection plate are neither measurable at this stage nor negligible, so they take a stated allowance — and the word stated is doing the work.

An allowance is only defensible when it is visible. A percentage buried in a rate is a guess that has been hidden; the same percentage written on the return as an allowance for connection material, with the basis named, is a commercial position that can be tested and adjusted at award. That distinction survives into the contract, because a client who accepts a stated allowance has accepted the assumption behind it, and a client who was never told is entitled to think the rate covered everything.

  1. Sort the package by weight share before measuring anything, and give the columns and primary beams the time; they are the smallest count and the largest tonnage.
  2. Measure one typical bay of secondary steel in full, then multiply by the bay count from the plan and verify the count independently off the grid.
  3. Give fittings, cleats and connection plate an explicit stated allowance rather than a percentage folded into the rate.
  4. Cross-check the total against a kilograms-per-square-metre ratio built from your own recent jobs of the same structural form, and treat a large disagreement as a missing category rather than a measuring error.
  5. Take the painted area from the same member groups, deduct the masked and encased surfaces, and add the plate area separately because it is disproportionate to its weight.
  6. Convert to litres per coat at a practical spreading rate, then round up to whole containers in the pack sizes the product actually ships in — a part tin is bought whole.
  7. Write the qualifications page while the numbers are still fresh, not after the covering letter.

The assumptions go in the file, not in your head

By the time the return goes out you have made two dozen decisions nobody else can see: which drawing series you measured and which you never opened, whether beams were taken grid to grid, what the connection allowance rested on, which surfaces you assumed were masked, what loss factor turned the theoretical spreading rate into the practical one, and what you did about the stair steel that might be someone else's. Every one of them is defensible on the day it is made and indefensible six weeks later when you cannot remember making it.

Which of them belong on the return and which belong only in your own file is a commercial judgement, but the split is worth making deliberately. Anything that changes the scope goes on the return as a qualification, in plain language, because it protects the price. Anything that is a method rather than a scope — the grid-to-grid convention, the loss factor, the sample bay you extrapolated from — stays in the file, because it is how you rebuild the number when the addendum lands on Monday morning and moves three gridlines. How steelwork is measured for payment is set by the contract rather than by anybody's habit: RICS New Rules of Measurement 2 sets out the British measured-work convention for structural metalwork, and AISC 303 is the customary reference for scope and shop paint in American practice. Establishing which one the enquiry is written against, before the return leaves, decides whether your tonnage and the tonnage on the other side of the table are describing the same steel.

The seven decisions behind a steel tender return

Each of these changes the tonnage or the painted area, none of them is visible on the general arrangement, and all of them need an answer before the return goes out.

  • Whether every drawing series has been opened — A complete, self-consistent primary framing plan gives no hint that a secondary series exists. Read the drawing register itself, not just the drawings you were sent.
  • Where each column actually starts and stops — Underside of baseplate to top of steel, taken off the section and elevations. It is neither floor to floor nor level to level, and the column where the ground falls away is longer than its row.
  • Whether beams were measured grid to grid — They usually are, which over-measures by the column depth and the erection clearance at each end. Record it as a convention so the next person knows the tally runs generous.
  • The average piece weight — Tonnage divided by piece count. It drives fabrication setups, painting handling, loads out and erection hours, and it cannot be recovered from the tonnage afterwards.
  • Square metres per tonne for this mix — Perimeter over mass per metre, group by group. A package of light angle and rail can carry four times the skin per tonne of one built from heavy columns.
  • Which surfaces are not being painted — Slip-critical faying surfaces, concrete encasement, areas under applied fire protection and site weld zones are all masked or held back, and on a heavily connected frame that is real area.
  • The loss factor between theoretical and practical spreading rate — Overspray, blast profile dead volume, stripe coats, pot and hose residue, and deliberate over-application against the SSPC-PA 2 acceptance bands. Use your own shop records.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ISO 12944-1, Paints and varnishes — Corrosion protection of steel structures by protective paint systems — General introduction, which defines the durability ranges a specification selects from
  • ISO 12944-2, Classification of environments — the C1 to C5 and CX atmospheric categories and the Im immersion categories
  • ISO 12944-3, Design considerations — accessibility and detailing for coating
  • ISO 12944-5, Protective paint systems — the system tables that set coat count and nominal dry film thickness
  • ISO 12944-7, Execution and supervision of paint work
  • ISO 8501-1, Preparation of steel substrates before application of paints and related products — Visual assessment of surface cleanliness — rust grades and preparation grades
  • ISO 8501-3, Preparation grades of welds, edges and other areas with surface imperfections
  • ISO 8503, Surface roughness characteristics of blast-cleaned steel substrates
  • SSPC-SP 6/NACE No. 3, Commercial Blast Cleaning
  • SSPC-SP 10/NACE No. 2, Near-White Blast Cleaning
  • SSPC-PA 1, Shop, Field, and Maintenance Coating of Metals
  • SSPC-PA 2, Procedure for Determining Conformance to Dry Coating Thickness Requirements
  • AISC 303, Code of Standard Practice for Steel Buildings and Bridges — scope of work and shop painting provisions
  • AISC Steel Construction Manual, dimensions and properties tables for the US rolled series
  • RCSC, Specification for Structural Joints Using High-Strength Bolts — faying surface coating classes for slip-critical connections
  • BS EN 1090-2, Execution of steel structures and aluminium structures — Technical requirements for steel structures
  • BS EN 10365, Hot rolled steel channels, I and H sections — Dimensions and masses
  • BCSA, National Structural Steelwork Specification for Building Construction
  • SCI P363, Steel Building Design: Design Data (the Blue Book) — section property tables including surface area per metre and per tonne
  • RICS New Rules of Measurement 2: Detailed measurement for building works — the measured-work convention for structural metalwork
  • ISO 1461, Hot dip galvanized coatings on fabricated iron and steel articles, and ISO 14713-1 for selecting zinc coatings, where secondary steel leaves the paint scope

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.