From this site

One project, every trade

Each calculator adds its lines to a single estimate — consolidated BOM, schedule and cash-flow included.

Open My Project

Lifting

Planning a Crane Lift

Capacity comes off a load chart written for a level test pad, and the ground under the outriggers has to be built to match it.

Published · Last reviewed

Two Documents That Have to Agree

A mobile crane arrives carrying a book of numbers the manufacturer established on a level, prepared test pad, then parks on a site that is none of those things. Planning a lift means forcing those two realities into agreement before the hook takes weight. Half the problem lives in the load chart — what the machine can hold, in one stated configuration, at one stated radius. The other half lives under the outrigger floats — what the ground will carry without settling, punching through or sliding. Real capacity is the smaller of the two, and confidence in one half buys nothing from the other.

Failures rarely involve both halves at once. Far more common is a faultless chart calculation set down on ground nobody proved: a float over a backfilled service trench, a mat bridging soft fill behind a new retaining wall, a pad that was firm on Tuesday and saturated by Thursday. The mirror image also happens — an immaculate engineered platform under a crane rigged in a configuration the chart page never covered, or slewing into a quadrant with less capacity than the one the lift was checked in.

Sequence follows from the split. Chart work comes first because it fixes the configuration, and configuration fixes the outrigger reactions the ground must then carry. Ground work either confirms those reactions are supportable or sends you back to the chart with a new constraint. Two or three passes around that loop is normal on a constrained site; one pass usually means somebody assumed something.

The Chart Is a Set of Conditions, Not a Number

Every capacity figure belongs to a page, and the page has an identity: machine model, boom length, boom mode or jib configuration, counterweight fitted, outrigger extension, and the quadrant of operation. Pull a number from the fully extended outrigger table while the crew sets up on intermediate extension because a kerb was in the way, and the lift is already wrong before anyone touches a lever. Counterweight is the same trap — the chart assumes a stack that has to physically be on the machine, in the arrangement drawn.

Notes pages carry the conditions the tabulated numbers depend on, and they are part of the chart rather than commentary on it. Typical conditions: the load hangs freely, the machine stands level within a stated tolerance, the supporting surface is firm and uniform, wind is below a stated limit, and the tabulated figures are gross with deductions still to come. Manufacturers word these differently, and the wording that governs is the one printed in the manual for that serial number, not the one remembered from the last machine.

Two different failure modes sit inside one table. Short radius with heavy loads is usually structurally limited — boom sections, slew ring, cylinders — and the warning before failure can be very short. Long radius is usually stability-limited, capacity set as a defined percentage of the tipping load, with the percentage depending on machine type and on the standard in force. Where the shaded or bracketed regions change from one governing mode to the other tells you what kind of margin remains, and how the machine will misbehave when it runs out.

Everything the Hook Carries Before It Carries the Load

Chart figures are gross. What the crane actually delivers to the load is what remains after everything else hanging below the boom head is subtracted: hook block or ball, the reeved rope below the head, an erected or even stowed jib, auxiliary sheaves, and then the entire rigging assembly — slings, shackles, spreader or lifting beam, chain blocks, tag lines. Anything mounted for this job and not present when the chart was written is a deduction, and the omitted spreader beam is the classic one.

Load weight deserves the same scepticism. A nameplate, a fabrication drawing and a supplier's estimate are three different qualities of evidence, and the last of those has been wrong by a wide margin often enough to justify weighing. Ask what the figure includes: retained water, ice, mud, entrained concrete, contents left in a vessel, attached platforms, insulation, packaging. Where uncertainty cannot be removed it has to be carried as declared margin rather than optimism, and that margin belongs somewhere the operator will see it.

Utilisation — net load over net capacity — becomes the number the whole site argues about, and reasonably so. Organisations set planning thresholds above which a lift moves into a higher category: more review, an engineered plan, a named supervisor, sometimes a physical trial. Track it early, because a figure that creeps upward as rigging is finalised is the normal way a routine pick turns into a complex one.

The chart page, the deductions and the load weight only mean something once they resolve into a single utilisation figure, which decides here and now whether this pick stays routine or changes category.

Chart utilisation

70.8 %

Check your inputs

Within capacity for the chart figure entered. This is arithmetic, not a lift plan.

Gross lifted load
12485 lb
Rated capacity
17635 lb
Margin remaining
5150 lb
Load alone as a share of capacity
56.25 %
Rigging, block and allowance
2565 lb
Gross load in tonnes
5.66 t

With the figures above, the chart utilisation comes to 70.8 %. Behind that figure, load alone as a share of capacity is the biggest single quantity at 56.3 %; start there if the total looks wrong. The method behind this is well established, though site conditions and material batches will move it somewhat. This is presented for United States. Building in another market? Change the selector above and the units and terminology follow.

Radius Refuses to Stay Still

Radius is measured from the centre of rotation to the centre of gravity of the load, and it changes twice in every pick — once at the lift point, once at the set point. Plan against the worse of the two, plus the path between them. Tape measures and site plans disagree with reality often enough that the radius should be confirmed on the machine, with the boom in the working configuration, rather than scaled off a drawing produced before the piling rig moved.

Under load the boom deflects, and deflection pushes the load outwards, so the operating radius on a loaded boom is longer than the unloaded one. Manufacturers state whether their tabulated radii already account for this, and that statement decides whether extra allowance is owed. Slewing adds the second variable — capacity commonly differs over the side and over the rear, and a lift checked in one quadrant is not automatically valid in the one it swings through.

Wind acts on the load's sail area rather than its weight, which is why light, large panels are the ones that hurt people. Manufacturers publish a maximum permissible wind speed for the configuration; gusts rather than the average are what break a lift, and the reading that counts comes from boom-tip height, not from ground level beside the site cabin. Add dynamics: snatching a load, freeing one that is stuck or frozen down, hoisting too quickly, or swinging hard all put forces through the machine that the static table never contemplated.

Underneath the Percentage: What the Outriggers Actually Push

Outrigger reactions are not the gross load divided by four. During slew the majority of weight transfers onto two floats, and the peak reaction at a single corner can approach — or exceed — the combined weight of the crane and its load. Reactions should come from the manufacturer's software or a documented calculation method for that machine, and they should be produced for the worst slew position, not the parked one.

On the other side of the interface, what the ground can accept is governed by the geotechnical standard in force, the site investigation and the temporary works regime the project runs under — not by a generic table of soil types remembered from somewhere. Made ground, uncontrolled fill, reinstated trenches and the zone behind retaining structures all behave differently from natural soil a few metres away. Buried services, culverts, basements, tanks, drainage runs and old foundations are each a reason a competent-looking surface fails under a float.

Evidence-gathering happens before the crane is ordered, not on the morning of the lift. Ask for the ground investigation report, the service drawings and the as-built records; where those do not resolve the question, trial pits, hand probes, dynamic cone penetrometer testing or plate loading fill the gap. Record what was found, because the crane pad counts as temporary works in most regimes and someone has to check and accept it against a design.

Building Ground That Matches the Chart

Mats and pads exist to convert a concentrated reaction into a pressure the ground will accept, and they do that only as well as their stiffness allows. A flexible timber mat under a heavily loaded float does not distribute across its whole plan area; pressure concentrates beneath the float and tails off, so the effective bearing area is smaller than the area you can see. Steel and engineered composite mats are stiffer and spread further, at the cost of weight, handling plant and lay-down space.

Below the mat, a proper working platform is its own design: granular material of specified type and thickness, compacted, sometimes with geosynthetic reinforcement, over a prepared and drained subgrade. Guidance for platform design is published by industry bodies and referenced in most temporary works regimes, and the resulting thickness is a design output rather than a habit carried from the last job. Rain changes the answer — a platform signed off in dry weather can lose capacity after a night of it, so re-checking after weather is a scheduled activity, not a favour.

Detail at the float decides whether any of it works. Full and even contact between float, packing and mat; no rocking; no bearing on a kerb edge or a protruding lump of rock; cribbing built square and interlocked where height is needed; and a stated minimum distance from the crest of any excavation or slope, measured rather than eyeballed. Set-up level is checked with the machine on outriggers before rigging and again afterwards, because floats settle into ground that looked firm.

With reactions known and mats chosen, one question remains at the interface between the two halves of the plan — whether the pressure arriving at the subgrade is smaller than what that subgrade will take — and it gets settled here before anything is craned.

4 ft4 ft
Schematic, drawn to the proportions you entered — not to scale on screen.

Applied ground bearing pressure

14.4 psi

Check your inputs

This calculator checks GROUND bearing pressure ONLY, using a reaction load YOU supply from your crane's own manufacturer-certified load chart and rigging plan — it does NOT calculate crane capacity, stability, ballast, or outrigger reaction loads, all of which must come from the crane manufacturer's certified data and a qualified rigger/operator per OSHA 29 CFR 1926 Subpart CC. Allowable ground bearing capacity must come from your own geotechnical data or a competent person's site assessment. A failing result means a larger mat, additional cribbing, or ground improvement is needed before the pick — always consult a qualified person for the final crane setup.

Outrigger reaction force
147152.94 N
Mat contact area
16 ft²
Allowable bearing capacity (user-supplied)
21.76 psi

For the dimensions entered, expect a applied ground bearing pressure of 14.4 psi. Of the working steps, allowable bearing capacity (user-supplied) dominates at 21.8 psi. Moderate confidence — sound arithmetic, but allow for the variation any real site introduces. Set for United States. The market selector changes the units and the trade terminology; any standard behind the formula is cited under sources.

Add the equipment this sizes

This result is a specification — 14.4 psi — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

When the Halves Will Not Meet

Disagreement between chart and ground is a normal outcome, not a crisis. The levers available: shorten the radius by repositioning the crane or the delivery, lengthen the boom to clear an obstruction without adding radius, add counterweight or a superlift where the chart supports it, upgrade to a larger machine, enlarge the mats, improve or rebuild the platform, split the load, or plan a tandem lift with two machines and a documented load-sharing arrangement.

Every lever pulled on one side moves the other. A larger crane resolves a utilisation problem and immediately worsens the ground problem, because it arrives heavier and pushes harder through bigger floats. Bigger mats reduce pressure and add crane time and handling. Repositioning to shorten the radius may put a float directly over the drainage run you were avoiding. Iterating is the work, and the plan is finished only when both halves close at the same time.

Authority to stop belongs to more than one person, and it has to be usable in practice. Late load-weight discoveries, ground that fails a check after rain, a wind reading over the limit, a mat that will not sit flat — each is a reason to hold, and holding is cheap set against a machine on its side, a closed road, an investigation and a fleet-wide stand-down. Write the hold points into the plan so that stopping is a listed step rather than an act of individual courage.

The Plan on Paper and the Brief on the Ground

Roles are defined by whichever standard governs the site, and titles differ — appointed person, lift director, lifting supervisor, competent person — but the structure is consistent: someone plans, someone supervises execution, someone operates, someone slings and signals. Most regimes also grade lifts by complexity, and the grade sets how much of the plan must be written, checked and independently accepted before anyone tracks a machine onto the pad.

A lift plan that stays in the site office has done nothing. What reaches the ground is the brief: the sequence, the exclusion zone and who keeps it clear, the single nominated signaller and the comms channel, the weather limits and who reads the anemometer, the tag line arrangement, and the parking or recovery position if the lift is aborted mid-pick. People who will never open the plan should leave that briefing able to say what they personally do and when they stop.

On the day the order is set-up, level check, mat and packing inspection, function tests, then a trial lift — take the load just clear, hold, and watch the machine, the floats and the ground before committing. Re-check level once the load is on; re-check the platform after rain, after another plant item has tracked across it, and at the start of every shift the crane stands there. Change control applies to all of it: a different load, radius, mat layout or quadrant means the plan is revisited, not adjusted verbally at the hook.

Before the crane is booked

Six things that have to exist on paper before a machine is ordered — three belonging to the chart, three to the ground.

  • The exact chart pageModel, boom length and mode, counterweight fitted, outrigger extension, quadrant. Print it and attach it to the plan.
  • A rigging deduction listBlock, ball, rope, jib, slings, shackles, spreader, tag lines. Weighed where possible, not carried forward from the last job.
  • Load weight with a stated sourceNameplate, drawing, weigh ticket or estimate — record which, and carry declared margin where it is an estimate.
  • Outrigger reactions for the worst slew positionFrom the manufacturer's software or a documented method for that machine, never from gross load divided by four.
  • Ground evidenceInvestigation report, service and as-built drawings, plus trial pits or probes where those leave a gap. Note anything buried under a proposed float.
  • Mat and platform scheduleMat type and size against effective bearing area, platform specification and thickness, and a named person to check and accept it.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • ASME B30.5, Mobile and Locomotive Cranes
  • ASME B30.9, Slings
  • ASME P30.1, Planning for Load Handling Activities
  • BS 7121-1, Code of practice for safe use of cranes — General
  • BS 7121-3, Code of practice for safe use of cranes — Mobile cranes
  • BS EN 13000, Cranes — Mobile cranes
  • AS 2550.1, Cranes, hoists and winches — Safe use — General requirements
  • AS 2550.5, Cranes, hoists and winches — Safe use — Mobile cranes
  • OSHA 29 CFR 1926 Subpart CC, Cranes and Derricks in Construction
  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER), United Kingdom
  • BS EN 1997-1, Eurocode 7: Geotechnical design — General rules
  • BRE BR 470, Working platforms for tracked plant

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.