Estimating

Pricing the Preliminaries: Building the Weekly Rate Off the Programme

The measured work is priced and the prelims column is empty. Resourcing supervision, plant and site services off the bar chart instead of guessing a percentage.
  • 25 minReading time
  • 10Sections
  • 5Calculators inline
  • Last reviewed

Two screens, one of them finished

The bill is done. Every measured item has a rate against it, the subcontract comparisons are levelled, the material enquiries came back and the discounts are in. On the other screen is the programme the planner issued on Friday: thirty-eight bars, a possession date, a completion date, and a critical path that runs through the frame and out through the roof. Between the two documents there is one page with almost nothing on it, and it is the page headed Preliminaries.

What usually happens next is that somebody writes a percentage. It is the percentage the last three jobs carried, adjusted by feel for how awkward this one looks, and it is defensible right up until anybody asks what is in it. The figure is not stupid — it is a compression of real experience — but it has thrown away the only two things that actually determine the number: how long the site is open, and what has to stand on it while it is. A percentage of the works cost knows neither.

The alternative takes a day and produces something a percentage never can: a weekly rate for running this site, built from named resources over named periods. That number does four jobs at once. It prices the tender, it tells the planner what a fortnight of float is worth in money, it is the figure a prolongation claim will eventually be argued from, and on the day somebody says the bid has to come down it is the only thing standing between a commercial decision and quietly deleting a site manager nobody misses until week nine.

A percentage of the works cost is measuring the wrong thing

Take two tenders of identical measured value. One is a new build on an open site: forty weeks, one entrance, room to lay down. The other is the same money spent inside a live building on a city street — eighteen months, a hoarding on a licensed footway, a hoist because there is no crane oversail, night access for anything noisy, and a full-time person managing nothing but the interface with a tenant who has not moved out. The two totals are driven by different quantities, which is why no single percentage can be right for both. Measured work is driven by how much there is of it; preliminaries are driven by how long you are there and what the site makes you do while you are, neither of which appears anywhere in a bill of quantities. A ratio between two things with unrelated drivers is not a rate, it is a coincidence you have seen hold a few times.

The measurement conventions know this, which is why every one of them gives preliminaries their own machinery. RICS New Rules of Measurement 1 keeps main contractor's preliminaries as a separate addition in the cost plan rather than folding them into elemental rates. NRM2 goes further and gives them a pricing schedule, with the contractor's own cost items set out under headings — management and staff, site establishment, temporary services, security, safety and environmental protection, mechanical plant, temporary works, cleaning, fees and charges, insurances and bonds — so each is priced rather than inferred. CESMM4 is the most explicit: its General Items class requires every method-related charge to be stated as fixed or time-related, which forces the estimator to declare item by item whether a delay costs more of it. North American practice collects the same money under Division 01 General Requirements and shows it in the schedule of values as general conditions, and NEC4 has no preliminaries bill at all, gathering the equivalent under People, Equipment and Charges in its Schedule of Cost Components.

Whichever convention you are working in, the useful move is the same one CESMM4 makes you do out loud: sort every line into fixed, time-related, or proportional to quantity. Fixed lines happen a set number of times regardless of duration. Time-related lines are multiplied by weeks. Quantity-related lines behave like measured work and belong in the same conversation as the rates. Once the page is sorted that way it stops being a lump sum and becomes a small model, and a model can answer questions a lump sum cannot.

Sorting the preliminaries page into the three behaviours, and what a month of slip does to each
LineBehaviourWhat actually drives itWhat one month of overrun does to it
Site establishment: hoarding, gates, signage, hardstanding, cabins craned in and connectedFixedThe number of times you set it up, and how awkward the setting-up isNothing at all, unless the delay forces a second establishment or a relocation
Cabin, container and welfare hire, consumables, servicing, waste from the welfare blockTime-relatedWeeks on site multiplied by the number of units the peak headcount requiredA full month, at the peak unit count rather than the average one
Site management, engineering, planning, commercial and safety staffTime-related, against a histogram rather than a flat lineWhich roles are on site in which weeks, at full cost of employmentA month of whatever the histogram holds at that point — usually not the peak, and never zero
ScaffoldFixed erect and dismantle, plus time-related hireErection is a measured job; the hire period is set by the last trade that needs to stand on itHire weeks only. The erection money is already spent and is not spent again
Tower crane, hoist, mast climbersFixed erect, test and dismantle, plus time-related hire, driver and attendanceFoundation and erection are one-off; everything after is a weekly charge with a person attachedA month of hire and of the operator, which is among the most expensive weeks on any site
Temporary electrical supply, water, telecomsFixed connection and disconnection, plus standing charge and consumptionUtility connection charges are one-off; the standing charge runs from energisation to disconnectionA month of standing charge and metered use, and possibly a generator that should have come off hire
Site clean, waste containers, muck away from general clearanceMixed: partly trade mix and quantity, partly durationHow many trades are working, how much packaging they bring, and how long the labour staysSome of it, in proportion to how much labour is still on site during the extra month
Contract works insurance, performance bond, parent company guarantee, collateral warrantiesFixed against the contract sum, but written for a periodThe sum insured and the period of insurance stated in the contractAn extension premium where the policy or bond period is exceeded, which is a real invoice
Setting out, testing, samples, benchmarks, as-built records, operation and maintenance manualsProportional to quantity and milestonesHow much there is to set out and test, not how long the job runsVery little. These follow the work, and the work has not grown
Sorting the preliminaries page into the three behaviours, and what a month of slip does to each

The number you multiply by is not the construction period

Every time-related line gets multiplied by weeks, so the weeks matter more than any individual rate on the page. The mistake that costs most is taking that figure off the contract period and stopping there. The contract period is a legal date pair, from possession to the date for completion, and it is the window liquidated damages run against. It is not how long the site is open.

The site is open earlier: somebody has to put the hoarding up, get the cabins in, apply for and take delivery of a temporary supply, form a crane base, and be standing there when the first subcontractor arrives with a lorry. That establishment sits in front of the first measured operation on the bar chart, and on a constrained site it is not a week. The site is open later too. Practical completion does not empty a compound — there is demobilisation, a final clean, security cover until the client takes the keys, commissioning attendance that runs past handover, and on many jobs a small presence through a defects period that somebody prices whether or not anybody has thought about it.

Inside those weeks the resources are not flat either, and that is what separates a real build-up from a longer version of the guess. A site manager may run from establishment to demobilisation, but the assistant covers the frame and the fit-out and not the twelve weeks of groundworks between them, the engineer is heavy at setting out and light afterwards, and the commercial staff arrive properly at the first valuation. Pricing every role across the full period is how a build-up comes out high and then gets cut by somebody who cannot see why. Pricing every role at its average is how a peak arrives unfunded.

Do it as an overlay on the programme rather than as a list and the arithmetic falls out. Total the time-related lines over their own windows, then divide by the contract period in weeks. That quotient is the weekly rate for running this site, and it is the number the whole exercise exists to produce.

  1. Write the contract period in weeks exactly as the contract states it, from possession or notice to proceed to the date for completion. That is the client's number and the damages clause hangs off it.
  2. Add the establishment period in front: hoarding, gates, compound platform, cabins delivered and connected, temporary supply energised, crane base cast and cured. On a constrained or licensed site that is weeks, not days.
  3. Add the tail behind: demobilisation, builder's clean, security until handover, commissioning attendance, and any presence committed through the defects period.
  4. For each staff role and each item of site-wide plant, write the week it arrives and the week it leaves. Where a role is part-time, write the fraction.
  5. Total every time-related line across its own window, then divide by the contract period. The total is what you are bidding; the quotient is the rate you will be arguing from for two years.
  6. Write the working assumptions beside the rate — days per week, shift length, weekend or night work, any shutdown. A client who later asks for a shorter working week is asking for weeks, and this line shows it.

The people on site who never install anything

Supervision is usually the largest single line on the page and the one most often priced as a job title rather than as a cost. A site manager, an assistant, a setting-out engineer, a planner attending fortnightly, a surveyor one day a week, a safety adviser monthly, a document controller shared with two other jobs. Each is a fraction of a person over a stated window, paid for at what employing that person actually costs — salary plus the employer's on-costs, the vehicle, the phone, the accommodation on a job nobody can commute to. That is the burden arithmetic the site's contractor-pricing guide works through in full, applied here to somebody who produces no measured output at all, so no rate anywhere in the bill can absorb it.

Some of these roles are not a management preference. The Construction (Design and Management) Regulations 2015 place duties on the principal contractor to plan, manage and monitor the construction phase and to secure cooperation between contractors, which is a job somebody holds rather than a document somebody files. OSHA 29 CFR 1926 Subpart C puts accident prevention responsibility on a competent person authorised to take corrective measures, and individual operations name competent persons of their own — Subpart P for excavations, Subpart L for scaffolds. BS 5975 sets out the procedural control of temporary works and the appointment of a temporary works coordinator, which on a job with much falsework, propping or facade retention is a genuine part-time role and not a box on a chart. NFPA 241 requires a fire prevention programme with somebody responsible for it. When the number gets challenged these are the easiest lines to defend, because they were never yours to remove.

The trap in the other direction is the shared resource, a favourite of a tight bid: a surveyor covering three jobs, a manager splitting his week between two. Sharing is legitimate and common, and it becomes a fiction the moment the histogram assumes more of it than the jobs will permit — two sites do not obligingly peak in different months, and when they collide the cover is bought in at short notice at a price nobody tendered. Write the fraction on the build-up, and write what happens if the other job wants the same weeks.

One line hides behind all of them and is invariably missed: the attendance the trades need from you rather than from each other. Somebody unloads the delivery that arrives when the subcontractor is not there, holds the keys, runs the induction, chases the method statement, books the lift, moves the cabin and stands with the meter reader. On a small job that is the manager doing it between other things and it is already inside his week. On a large one it is a general foreman and two labourers — a resource priced by the week, appearing in no measured item anywhere.

Run it once per role rather than once for the site. Hours is the window that role is genuinely on site — weeks multiplied by the hours a week, for that role only, not for the contract period — and the rate is the full cost of employing that person, on-costs and vehicle included, rather than a salary divided by 2,080. Crew size is how many of that role. Then add the role totals up and divide the sum by the contract period in weeks: that is what supervision alone contributes to the weekly rate, and it is usually a bigger share of it than anyone expects.

Labor Cost Calculator

The total hours the job is expected to take, per worker.

The rate charged (or paid) per worker, per hour.

The number of workers billed at this hourly rate.

Total crew-hours

40 hours

Medium confidence

Figures that depend on a rate wait for yours — this page does not assume one.

What this calculation does not cover

  • One rate is multiplied across every hour and every worker, so there is no tier for overtime or holiday premiums, night and weekend differentials, or a crew that pairs a licensed lead with an apprentice — a mixed-rate job has to be totalled in separate runs and added by hand.
  • Crew size acts as a straight multiplier on the hours you entered, which assumes each additional worker stays productive for the full duration: the tasks that will not split across two pairs of hands, the time a crew loses coordinating, and the helper who is only on site for part of the week all leave the total untouched.
  • Nothing distinguishes a wage you pay from a rate you are charged, because the same multiplication runs on either. A figure built from raw wages carries no payroll taxes, workers' compensation, insurance or benefits on top of it, while a contractor's quoted rate may already have overhead and profit buried inside — the answer looks identical in both cases.
  • Only worked hours are priced. Travel and mobilization, setup and clean-up, tool or equipment hire, disposal, permits and materials all sit outside the figure, and no minimum charge is imposed either — an entry of half an hour returns half an hour of money on a job many trades would bill as a minimum visit.
  • The hours you type are taken exactly as they stand, with no contingency for rework, weather, waiting on an inspection or scope that grows once the walls are open, and the rate is held flat for the whole span — a long program approaching the 2,000-hour entry ceiling is still priced at today's number, with no escalation partway through.

Scaffold and plant run on a clock that somebody else is holding

Site-wide plant is where the fixed and time-related split earns its keep, because almost every item on this part of the page is both at once. A scaffold is an erection price, a weekly hire, adaptations as the job changes, and a dismantle. A tower crane is a foundation, an erection with a mobile crane and a road closure, statutory examination, then a weekly hire with an operator and a slinger attached, then a dismantle with the same road closure again. A hoist is the same shape. Price any of them as a single lump and the first thing the programme does is make the number wrong, because slip moves the hire weeks and leaves the erection cost exactly where it was.

The hire period is the part not in your gift, and it is the specific way scaffold overruns. You erect it for the bricklayer and it comes down when the last person who needs to stand on it has finished — the roofer, the window fitter, the renderer, the painter, whoever does the flashings nobody sequenced. The hire period is set by the tail of somebody else's programme rather than by the trade that asked for it, so an estimator pricing it against the masonry duration has priced perhaps half of it. Design and adaptation carry their own money: NASC TG20 covers good practice for tube and fitting scaffolding and the compliance sheet route for common configurations, BS EN 12811-1 sets performance requirements, OSHA 29 CFR 1926 Subpart L governs the North American equivalent, and anything outside the standard configurations is a designed scaffold with an engineer's drawing behind it — a fee and a lead time.

The rent-or-own question turns up in the middle of this. The bare break-even is trivial — purchase price divided by daily hire rate gives the number of hire days at which buying is level — and it ignores everything ownership drags along: maintenance, statutory examination, transport between sites, storage, an operator you employ rather than hire, the money tied up, the residual at the end. Hire is quoted off a rate card whose weekly and monthly rates sit well below seven or thirty times the daily, so the honest comparison uses the structure you would be quoted rather than a daily rate multiplied out. Do the break-even anyway: it frames the decision in the only unit that matters here, days on this site. Then remember that whichever way it goes the cost lands in the preliminaries as weeks. A machine you own is not free while it stands there, only a cost you have stopped being invoiced for, and the surest way to lose money on owned plant is to let a job carry it for months with nothing to do.

Put in the purchase price of the item and the daily rate you would actually be quoted, and read the break-even in days. Now compare that number against the window on your histogram rather than against the whole programme — a telehandler needed for eleven weeks of a forty-week job is an eleven-week decision. Then run it again with the daily rate replaced by a weekly rate divided by seven, which is closer to what a long hire really costs per day, and watch the break-even move a long way out. That gap between the two answers is roughly the size of the mistake in any rent-or-buy argument settled on a daily rate.

The cost to buy the equipment outright.

The cost to rent the same equipment for one day.

The hire firm's week rate, if they quote one. Zero means day rate only.

How many days the equipment is actually needed for.

What you expect to sell it for afterwards, if you will.

Break-even rental days

Needs your rates

This page does not assume a price. Enter yours and the answer appears here.

What this calculation does not cover

  • The daily rate is the sticker, not the invoice. Yards add a damage waiver, environmental and fuel charges, and delivery and pickup on anything you cannot carry in a truck, and many bill an eight-hour meter day — run a machine ten hours and it counts as more than one day. Each of those raises the real cost of renting, which moves the true break-even below the day count shown here.
  • It assumes the rented machine and the bought machine are the same machine, and at the same price they usually are not. Rental fleets are contractor-grade and built for daily abuse, while the tool a comparable purchase price buys is often a lighter homeowner model with less capacity and a shorter life. Matching the rented machine's specification costs more to buy and pushes break-even further out.

Welfare and temporary power have a floor underneath them

Two lines on the page are not commercial decisions at all, and it is worth knowing which before anybody starts cutting. Welfare is a legal minimum: the Construction (Design and Management) Regulations 2015 require suitable and sufficient welfare facilities, with Schedule 2 setting out what that means — sanitary conveniences, washing facilities, drinking water, changing and rest facilities — and OSHA 29 CFR 1926.51 does the equivalent job for potable water, toilets and washing. Specification, supplier and layout are yours to choose. Less than the floor is not, and a tender carrying one cabin fewer than the peak headcount requires has deferred an order rather than saved money.

Temporary electrics carry a comparable floor and an easily-missed shape. NFPA 70 Article 590 governs temporary installations, BS 7671 Section 704 covers construction and demolition site installations, and HSE HSG141 sets out electrical safety on construction sites. The pricing consequence is that the supply is fixed at each end — the connection application and the utility's charge going in, the disconnection coming out — with a standing charge running from energisation to disconnection, a period the utility's dates govern rather than your programme. Sites routinely run on a generator for the months in between, and that is fuel and servicing by the week. The compound layout, what the cabins draw and how far the supply can sit from the cabin door are all worked out on this site's compound guide; what matters here is only the figure you multiply by weeks.

Reading the exclusions until the gaps show

Every subcontract quotation on the comparison sheet has a list at the bottom of things it does not include, and that list is where preliminaries are silently created and silently duplicated. Removal of rubbish from the work area to a container provided by others. Task lighting by others. Unloading and distribution by others. Scaffold by others. Power and water free of charge at each floor. Attendance for testing. Protection of the finished work. Every one of those clauses is a cost that has to be somewhere, and there are exactly two ways to get it wrong.

The gap is the expensive one: nobody prices it, because each party assumes the other did, and it surfaces on site as an argument you lose while the work stands still. The double count is quieter and loses you the job rather than the money — the prelims carry a general clean, every trade has also priced clearing their own, and you have bought the same broom twice for a reason nobody will ever tell you. Both are found the same way, by reading the exclusions across every package at once and marking who does each thing. It is an afternoon, and the highest-yield afternoon in the tender.

Waste is worth doing carefully, being the clearest case of a cost that is neither purely time-related nor purely quantity-related. The volume is driven by the trades — packaging, offcuts, plasterboard, strip-out arisings — and the number of exchanges by how long those trades are there and how much they were allowed to leave for you. A container also carries two charges that behave differently: a delivery and collection charge per exchange, and a rental accruing while it stands. A skip sitting half-full for three weeks because nobody booked the exchange is paying rental on air, which makes this one of the few preliminaries lines that responds to management rather than to money. Segregation and compound layout belong to the waste-compound page; the tender question is narrower — how many exchanges over how many weeks, and which of them the trades should have been paying for.

  1. Pull the exclusions off every package quotation into one column, in the subcontractor's own words, and do not summarise them.
  2. Against each, write who does it: the trade, your preliminaries, or another package. Anything without a name in that column is a gap, and it costs more later than it costs now.
  3. Circle anything named twice. That is money in your bid no competitor is carrying, and it is nearly always cleaning, unloading, task lighting or scaffold adaptation.
  4. Convert the ones landing on your preliminaries into resources with windows: labourers by the week, a forklift by the month, a container with a stated exchange frequency.
  5. Feed that frequency back into the histogram, because it is not constant — strip-out and first fix produce nothing like the volume of second fix, and one average hides both ends.

Price the container the way it is actually billed rather than as a lump. The daily rate and the days on site give you the rental that accrues while it stands there; the haul fee is the delivery and collection that happens once per exchange. Run it for one exchange, then multiply by the exchanges your trade mix demands over the weeks the trades are on site. Now run the single exchange again with the days halved and the exchange count left alone — the volume is set by the trades, not by you — and the rental halves while the haul fee does not move. That difference is what the skip was earning the hauler for standing still, and it is the part of this line that responds to booking the exchange on time. The opposite move is worth pricing before anybody promises it: halving the days by doubling the exchanges leaves the rental total exactly where it started and buys a second haul fee every time.

The hauler's quoted daily rate for the rental period.

How many days the container will be on-site.

The flat fee to deliver and later pick up the container.

Total rental cost

Needs your rates

This page does not assume a price. Enter yours and the answer appears here.

What this calculation does not cover

  • This prices one container, delivered once and pulled once. A job that fills the box twice pays the haul fee again on every swap, and most haulers restart the rental clock or bill the swap at a different rate from the original drop — so two 20-yard pulls is not the same money as one 40-yard rental even when the volume matches exactly. Ask for the swap rate before choosing the size.
  • Some materials are billed outside the daily rate entirely. Mattresses, tires, appliances holding refrigerant, treated lumber and anything containing asbestos each carry a flat surcharge or are refused at the gate, and a load turned away at the scale comes back to site with the trip billed both ways. Pull those out of the box before it is hauled, not after.
  • A container in the street is a permit, not just a rental. Where the box sits on a public road or sidewalk most municipalities require a right-of-way permit with its own fee, its own duration limit and often reflectors or lights, and an unpermitted container gets ticketed daily and can be removed at the owner's expense. On private ground none of that applies — which is why the identical rental costs two different amounts on the same street.

The weekly rate is the number you will be paid at

There is a reason to do all of this that has nothing to do with winning the tender. Sooner or later something happens that is the client's risk and not yours — late information, an instruction that stops a work face, access promised and not given — and you apply for an extension of time. Time is not money, though, and the two travel under separate clauses: an extension protects you from damages, while the cost of having been there longer comes from somewhere else. In JCT that is the loss and expense provisions and the Relevant Matters triggering them; in NEC4 a compensation event assessed on Defined Cost plus Fee; under AIA A201 the extension of time in Section 8.3 sits apart from the claim for what the delay cost, and FIDIC's Red Book separates the two for the same reason.

What every one of those routes eventually asks for is the same thing: what did it actually cost you to keep this site standing for the extra period. That is the preliminaries build-up, week by week, with dates against each resource. A contractor who priced a percentage has nothing to hand over. A contractor with a resourced histogram has a contemporaneous document showing exactly which staff and which plant were committed in which weeks — which is not proof of what was spent, but it is the baseline everything else gets measured against, and it was written before anybody had a reason to be self-serving about it.

Two refinements are worth having straight before the argument rather than during it. The first is which weeks get valued: the Society of Construction Law's Delay and Disruption Protocol is clear that compensation for prolongation is assessed by reference to the period in which the effect of the employer risk event was felt, not the extended period tacked on at the end — different weeks, with different resources standing on the site, which is why the histogram matters more than the average. The second is that prolongation and disruption are not the same claim: prolongation is the site being open longer, disruption is the same work costing more per unit because of how it had to be done, and no multiple of weeks recovers it. Head office overhead during a delay is a third question, argued through named formulae — Eichleay in United States federal contracting, Hudson and Emden in the British literature the Protocol discusses — and it is contested ground rather than arithmetic.

For tender day the consequence is short. The weekly rate you build now is the rate you will be quoting back at somebody in eighteen months, so build it as though it will be read by a quantity surveyor who is not on your side. Keep the workings, date them, note the assumptions about working hours and shared staff, and keep the one-off costs separate from the weekly ones exactly as you did here — because standing a site down and starting it up again costs the same whether the stoppage was two weeks or six.

Use it to price a prolongation rather than a variation. The additional work cost is the weeks of delay multiplied by your own time-related weekly total — not the tender preliminaries divided by the contract period if the resources in those particular weeks were heavier or lighter than average. The markup is the percentage addition the contract actually allows on a change, which is frequently not the one in your tender build-up. The administrative fee is the one-off: standing down, securing the site, re-mobilising, re-inducting. Now halve the weeks and run it again — the weekly part halves, the standing-down part does not move, and that is why a short stoppage costs disproportionately more per week than a long one.

Your direct material + labor cost for the added scope.

Markup applied to the additional work, same as your normal project markup.

A flat fee covering paperwork, re-scheduling, and coordination overhead.

Total change order cost

$2,400

High confidence
Markup amount
$300

What this calculation does not cover

  • Markup lands on the added work cost alone — the administrative fee is added after it and is never marked up, so a contract that allows markup on the processing charge will settle slightly above this figure.
  • One percentage covers the whole variation, with no split between overhead and profit and no separate rate for subcontracted work; where a sub's price already carries its own uplift, no second tier is stacked on top of it here.
  • Time is absent from the arithmetic. Nothing is priced for extra days on site, extended preliminaries, or the disruption to work already sequenced around the original scope, which on a mid-project change is often the larger number.
  • The flat fee is counted once per run. Several small variations that each trigger their own charge, or one order bundling unrelated items, have to be worked through individually rather than as a single lump.
  • Deductive changes have no route in: the added work cost cannot be taken below zero, so a credit for scope removed has to be handled as its own line away from this page.
  • The added work cost is entered as one figure, so nothing distinguishes short-notice material pricing, restocking on cancelled orders, or remedial work to undo what was already built — those belong inside the number you type, or they are missing from the total.

Risk on this page is counted in weeks before it is counted in money

Contingency on a tender usually arrives as a percentage on the total, which has the same defect as a percentage for the preliminaries themselves: it is not connected to anything. On the preliminaries page there is a better exchange rate available, and you have just built it. Every risk that threatens the programme converts into money at exactly one number — the weekly rate — so the honest question is not what percentage to add but how many weeks of exposure this particular job carries.

That makes the risk register something you can price rather than something you file. Weather is the clearest case, and whether it is your risk or the client's is a contract question with a real answer: JCT lists exceptionally adverse weather conditions among the Relevant Events, which buys time and not money, while NEC4 provides a weather compensation event measured against data recorded at a stated weather measurement place over a stated return period. Where neither applies, a winter start on a job with twelve weeks of groundworks is carrying weeks that belong to you. The same treatment works for a ground risk in the soil report, a condition with a discharge period, a diversion in a utility's hands, or a package with one credible supplier. AACE International Recommended Practice 40R-08 is the reference for doing it as contingency estimating rather than as padding, and it keeps contingency separate from management reserve, which was never the estimator's to hold.

Two disciplines make the result honest. Size the buffer against the time-related total rather than against the whole preliminaries figure, because a delay does not re-erect a scaffold or re-cast a crane base; the fixed lines are already spent. And write the weeks down alongside the money, because weeks survive an adjudication meeting in a way that a percentage never does — nobody argues a contractor out of a percentage they cannot see, but a room full of people can look at three weeks of assessed weather exposure and decide, on the record, to carry two.

Make the percentage a derived number instead of a chosen one. Put your time-related preliminaries total in as the base, then set the contingency percentage to your assessed weeks of programme risk divided by the contract period in weeks, multiplied by a hundred — four weeks of exposure on a forty-week job is ten per cent, and that figure came off a risk register rather than out of the air. Read the contingency amount rather than the headline total, because the headline adds the buffer back onto the preliminaries you were already carrying: that contingency line on its own is what those weeks cost you in site establishment, before any of the measured work is considered, and it is usually the moment the risk register stops being a formality.

Your planned budget before adding a buffer for the unexpected.

The extra buffer to add for unexpected issues.

Total budget with contingency

$23,000

Medium confidence

Contingency is a planning buffer, not a guarantee — projects that uncover major surprises (structural damage, code-required upgrades) can still exceed even a generous contingency.

Contingency amount
$3,000

What this calculation does not cover

  • The percentage is applied to the base budget as one flat multiplier, so every dollar of the job is treated as carrying identical risk. A $20,000 kitchen made up of $14,000 of fixed-price cabinetry already on order and $6,000 of demolition into an unknown wall gets the same $3,000 buffer at 15% as one that is speculative end to end. Where the risk sits in a single part of the scope, size a buffer against that part and add it to the rest rather than smearing one rate across the total.
  • Nothing in the arithmetic is a fixed amount: the buffer is purely proportional, so it shrinks with the budget while many of the surprises it is meant to absorb do not. A failed inspection, half a day of extra excavation or an emergency call-out costs roughly the same on a $3,000 job as on a $300,000 one, yet 15% sets aside $450 on the first and $45,000 on the second. Small jobs are the ones a percentage rule quietly under-buffers.
  • Whatever is missing from the base figure stays missing from the answer. The base budget is read as a single opaque number, so if permits, disposal, delivery charges or temporary accommodation were never counted in it, a 15% buffer on that total does not fund them — it scales an incomplete estimate rather than completing it.
  • The output is a lump sum with no timing in it. No term asks when the money is drawn or how long ago the base was priced, so a buffer taken on a year-old estimate is a percentage of a stale number. Re-running the figure part-way through a job would need the remaining scope and the buffer already consumed, and neither is tracked here.
  • The percent field accepts whole numbers from 5 to 50 and the base accepts $100 to $2,000,000; those are input bounds, not guidance about where your job belongs. The commonly cited 10-20% range is a general renovation figure, and nothing in the calculation weighs building age, how much structural work is involved, or how firm your quotes are to place you within it.

The last meeting, and where the money comes off

The bid gets adjudicated. Somebody senior looks at the total, forms a view about what it will take to win, and the number has to come down. There are three places it can come from and they are not equivalent. Off the measured rates, which you built and can defend line by line. Off the margin, which is a decision about how much of this job's profit to give away and belongs to whoever owns the business — the site's contractor-pricing guide works through what that costs across a year. Or off the preliminaries, which is where it usually comes from, for the simple reason that they look soft: nobody outside can measure them, and no bill document contradicts a smaller figure.

That instinct is not always wrong. A build-up done honestly for the first time often does hold slack — a role priced across the whole period that needs half of it, a scaffold priced for the full duration when it can be struck in three phases, a manager who genuinely can cover this and one other. What separates a commercial decision from a self-inflicted wound is whether the reduction names something. Delete a role and shorten a period, and write both down; take a percentage off the bottom of the page and you have bid a site you cannot resource, which surfaces around week nine and comes back out of the margin anyway with a delay attached.

Keep the deleted version, because it is worth more later than it is now: if the site turns out to need what was cut, the gap between the two build-ups is the clearest record there is of a decision taken with open eyes, and it stops week nine becoming an argument about competence. And once the job runs, remember what this line does to a progress measurement — it earns by the calendar rather than by the work, which earned value practice calls a level-of-effort activity, so it flatters the numbers early and punishes them late. Measuring a live job without that distortion is a different exercise on a different day, handled properly on the job-tracking guide.

What has to exist before the preliminaries page gets a total

Five documents and one number. None of them is a price, all of them come from the programme and the tender documents rather than from a price book, and every one of them is still useful in two years when somebody asks why the site cost what it cost.

  • The priced period, which is longer than the contract period — Possession to completion as the contract states it, plus the establishment weeks in front and the demobilisation, clean, security and commissioning tail behind. Every time-related line is multiplied by a slice of this, so an error here multiplies through the whole page.
  • A staff histogram, not a staff list — Each role with the week it arrives, the week it leaves, and the fraction of a week it is present. Roles imposed by regulation — the principal contractor's duties under CDM 2015, the competent persons under OSHA Subpart C, a temporary works coordinator under BS 5975 — marked as such, because those are the lines that survive an adjudication meeting.
  • Every line sorted into fixed, time-related or quantity-related — The sort CESMM4 forces by requiring method-related charges to be stated as fixed or time-related. It is what lets you answer the only question anybody will ask afterwards: what does a month of delay cost, and what does it not cost.
  • The exclusions sheet, with a name against every line — Every package quotation's exclusions in one column and who does each one in the next. Anything unnamed is a gap that lands on you at settlement; anything named twice is money in your bid that nobody else is carrying.
  • The weekly rate, written down and dated — Time-related total divided by the contract period. It prices float for the planner, prices a prolongation for the surveyor two years from now, and turns a risk register from a filing exercise into a number.
  • The risk weeks, separately from the risk money — Weather exposure, ground risk, a condition with a discharge period, a package with one credible supplier — each assessed in weeks and then converted at the weekly rate, so the contingency percentage is derived rather than chosen.
Open this as a workspace →

Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.

Drawn from

  • RICS New Rules of Measurement 1, Order of cost estimating and cost planning for capital building works — main contractor's preliminaries and main contractor's overheads and profit as separate additions to the works cost estimate, and the treatment of risk allowances
  • RICS New Rules of Measurement 2, Detailed measurement for building works — work section 1, Preliminaries, and the pricing schedule of contractor's cost items covering management and staff, site establishment, temporary services, security, safety and environmental protection, mechanical plant, temporary works, cleaning, fees and charges, and insurances, bonds, guarantees and warranties
  • CESMM4, Civil Engineering Standard Method of Measurement, Fourth Edition — the General Items class, and the requirement that each method-related charge be stated as fixed or time-related
  • Chartered Institute of Building, Code of Estimating Practice
  • Chartered Institute of Building, Guide to Good Practice in the Management of Time in Major Projects: Dynamic Time Modelling
  • CSI MasterFormat, Division 01, General Requirements — including the temporary facilities and controls section under which site establishment is specified in North American practice
  • AACE International Recommended Practice No. 10S-90, Cost Engineering Terminology — direct cost, indirect cost and field indirect cost as distinct terms
  • AACE International Recommended Practice No. 40R-08, Contingency Estimating — General Principles
  • Society of Construction Law, Delay and Disruption Protocol, 2nd edition — compensation for prolongation assessed by reference to the period in which the effect of the employer risk event was felt, rather than the extended period at the end of the contract; and its treatment of unabsorbed head office overhead, including the Hudson, Emden and Eichleay approaches
  • Eichleay Corp., ASBCA No. 5183 (1960) — the formula for unabsorbed home office overhead in United States federal contracting
  • JCT Standard Building Contract — the loss and expense provisions and the Relevant Matters that trigger them; the Relevant Events, including exceptionally adverse weather conditions; and Insurance Options A, B and C
  • NEC4 Engineering and Construction Contract — compensation events assessed on Defined Cost plus Fee; the Schedule of Cost Components, with People, Equipment and Charges; and the weather compensation event measured against data recorded at the weather measurement place
  • AIA Document A201, General Conditions of the Contract for Construction — Section 8.3, delays and extensions of time, and Article 7, changes in the work
  • FIDIC Conditions of Contract for Construction (Red Book) — extension of time for completion and the contractor's claims for cost, dealt with under separate provisions
  • The Construction (Design and Management) Regulations 2015 — regulation 13 (duties of a principal contractor in relation to health and safety at the construction phase, including regulation 13(4)(c), facilities complying with Schedule 2 provided throughout the construction phase), regulation 15 (duties of contractors, whose paragraph (11) carries the same Schedule 2 obligation) and Schedule 2 (minimum welfare facilities required for construction sites)
  • OSHA 29 CFR 1926 Subpart C, General Safety and Health Provisions — accident prevention responsibility and the competent person
  • OSHA 29 CFR 1926 Subpart L, Scaffolds
  • OSHA 29 CFR 1926 Subpart P, Excavations — the competent person for excavation work
  • OSHA 29 CFR 1926.51, Sanitation — potable water, toilet and washing facilities on a construction site
  • BS 5975, Code of practice for temporary works procedures and the permissible stress design of falsework — procedural control and the temporary works coordinator
  • NASC TG20, Guide to Good Practice for Tube and Fitting Scaffolding, and the TG20 compliance sheet route
  • BS EN 12811-1, Temporary works equipment — Scaffolds. Performance requirements and general design
  • NFPA 70, National Electrical Code — Article 590, Temporary Installations
  • BS 7671, Requirements for Electrical Installations (IET Wiring Regulations) — Section 704, Construction and demolition site installations
  • HSE HSG141, Electrical safety on construction sites
  • NFPA 241, Standard for Safeguarding Construction, Alteration, and Demolition Operations — the fire prevention programme and the person responsible for it
  • Highways Act 1980 — licences for hoardings, scaffolding and containers placed on or over the highway
  • Project Management Institute, Practice Standard for Earned Value Management — level of effort as an earned value technique

Guidance, not a specification. Local codes, the engineer of record and the product manufacturer’s instructions govern where they differ from anything written here.