Earned Value Management (EVM) Calculator
CPI, SPI, variances and a forecast at completion from planned value, earned value and actual cost.
Computed in your browser — nothing you enter is uploaded. Figures are presented for United States against IRC 2024, and every formula is cited under regulatory standards below.
Last verified 2026-08-27 · v1.0.0
Estimate at completion
1166666.67 currency
Over budget and behind schedule on the figures given. TCPI shows the efficiency the remaining work would need to still land on budget.
- Cost performance index (CPI)
- 0.86
- Schedule performance index (SPI)
- 0.9
- Cost variance (CV)
- -60000 currency
- Schedule variance (SV)
- -40000 currency
- Variance at completion (VAC)
- -166666.67 currency
- Estimate to complete (ETC)
- 746666.67 currency
- To-complete performance index (TCPI)
- 1.1
- Percent complete
- 36 %
- Percent spent
- 42 %
For the dimensions entered, expect a estimate at completion of 1166667 currency. Of the working steps, estimate to complete (etc) dominates at 746667 currency. Note that budget at completion (bac) and planned value (pv) sit at the edge of the range this calculator was checked against, so treat the output as indicative rather than settled. Set for United States against IRC 2024. The market selector changes both the units and the code cited.
[Schema Verified] Computed in alignment with American Concrete Institute (ACI 318-19) formulas and International Residential Code (IRC 2024) spatial boundaries.
Regulatory standards & verification citations
- PMBOK earned value definitions: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV
- EAC = BAC ÷ CPI where current cost performance is expected to continue; the most commonly used of several sanctioned formulas