SettingsSettings for this calculationUS
Total authorised budget for the work.
The baseline, including approved changes. Comparing performance against a baseline that has quietly moved is the most common way EVM is made to look better than reality.
Budgeted cost of work scheduled to date.
What the baseline says should have been achieved by now, measured in budget currency.
Budgeted cost of work actually completed.
Physical progress valued at baseline rates. This is the hard input: it requires an honest measure of what is genuinely complete, and optimistic percent-complete reporting corrupts every figure downstream of it.
What has actually been spent on that work.
Must cover the same scope and the same period as EV. Accruals matter — invoices not yet received are still cost incurred, and omitting them makes CPI look healthy for a month.
Estimate at completion
$1,166,667
Over budget and behind schedule on the figures given. TCPI shows the efficiency the remaining work would need to still land on budget.
- Cost performance index (CPI)
- 0.86
- Schedule performance index (SPI)
- 0.9
- Cost variance (CV)
- $-60,000
- Schedule variance (SV)
- $-40,000
- Variance at completion (VAC)
- $-166,667
- Estimate to complete (ETC)
- $746,667
- To-complete performance index (TCPI)
- 1.1
- Percent complete
- 36 %
- Percent spent
- 42 %
They open the calculator with your figures already in it
Earned Value Management (EVM) Calculator: 1,166,667 currency — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- PMBOK earned value definitions: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV
- EAC = BAC ÷ CPI where current cost performance is expected to continue; the most commonly used of several sanctioned formulas
Inputs used
- Budget at completion (BAC)
- 1000000
- Planned value (PV)
- 400000
- Earned value (EV)
- 360000
- Actual cost (AC)
- 420000
Intermediate steps
- Cost performance index (CPI)
- 0.86
- Schedule performance index (SPI)
- 0.9
- Cost variance (CV)
- $-60,000
- Schedule variance (SV)
- $-40,000
- Variance at completion (VAC)
- $-166,667
- Estimate to complete (ETC)
- $746,667
- To-complete performance index (TCPI)
- 1.1
- Percent complete
- 36 %
- Percent spent
- 42 %
Confidence note: Over budget and behind schedule on the figures given. TCPI shows the efficiency the remaining work would need to still land on budget.
What this calculation does not cover
- Every figure is only as good as the earned value input. Optimistic percent-complete reporting produces a healthy CPI on a failing project, and it is the standard failure mode of EVM in practice.
- SPI is measured in currency, not time, and it converges to 1.0 as a project finishes regardless of how late it is — a project delivered a year late still ends with SPI = 1. Use the schedule network for time performance, not this index.
- EAC here assumes current cost performance continues. Other sanctioned formulas assume the remainder runs to plan, or weight cost and schedule together; they give materially different answers on a troubled project.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-06 · in the site-wide review of 2026-09-06 · v1.0.1
Regulatory standards & verification citations2
- PMBOK earned value definitions: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV
- EAC = BAC ÷ CPI where current cost performance is expected to continue; the most commonly used of several sanctioned formulas
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.