Financial-Adjacent

Construction Preliminaries (General Conditions) Calculator

Add up preliminaries (general conditions) from your own weekly and one-off figures: fixed, time-related and value-related, and what a week of delay adds.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The contract period in weeks, from possession of the site to practical completion.

Take it from the programme, not from the optimistic version in the tender letter. Every time-related item below runs for this whole span, including the weeks at the end when the value being certified has slowed to a trickle and the site staff are still there chasing snags. Under-stating the duration is the commonest way prelims come out short, because it discounts every line at once.

People on site full-time whose cost is not in any trade rate.

The site manager, the assistant, the engineer setting out, the storeman, the gateman. Anyone whose time is already inside a measured rate — the bricklayer, the electrician — is NOT counted here, or their cost lands in the estimate twice. Part-timers go in as a fraction: a visiting contracts manager one day a week is 0.2.

All-in weekly cost of one member of site staff.

All-in means salary plus the employer's on-costs — national insurance or payroll tax, pension, holiday accrual, sick pay, training, and the vehicle and fuel if one comes with the job. That total is commonly 25 to 40% above the bare salary, and estimates that use the salary alone are short by exactly that margin on the biggest prelims item there is.

Weekly hire of offices, canteen, drying room, toilets and stores.

Welfare is not optional and is not negotiable down: the regulations set what has to be provided from day one, and an inspector who finds it missing can stop the job. Include the servicing — the toilets are emptied on a contract, and that contract runs weekly whether the job is busy or quiet.

Power, water, lighting, telecoms and skips, per week.

Temporary power on a construction site is metered at commercial rates through a supply that also has a standing charge, and the lighting runs longest in the months when the daylight does not. Skips belong here rather than in the trades: waste arrives from every trade at once and no single rate carries it.

Weekly hire of plant that stands on site rather than belonging to a trade.

The hoist, the tower crane, the telehandler, the site-wide access. What makes this a prelim rather than a trade cost is that it is hired for the duration and charged whether or not it turned a wheel that week — the crane is on hire through the fortnight the steel was late. Plant hired in for one operation and sent back belongs in that operation's rate instead.

Mobilisation: hoarding, gates, signage, hardstanding, first connections.

Everything paid once to turn a piece of ground into a site. Delivery and craning-in of the accommodation, the hoarding and gates, the temporary road or hardstanding, the incoming power and water connections, the site signage and first-aid provision. A delay does not repeat these, which is exactly why they are kept out of the weekly rate below.

Demobilisation: removing everything and making the ground good.

Collection of the accommodation and plant, taking down the hoarding, disconnecting the temporary services, the final clean, and reinstating whatever the compound stood on. Routinely left out on the grounds that it is somebody else's problem by then, and it is not — it is in the contract and it lands in the last month, when there is no value left to certify against it.

The contract value, used for the value-related items and the percentage check.

Enter the sum including the preliminaries themselves, since that is what insurance and bonds are priced against and what the resulting percentage is normally quoted as. If you are building the number up from scratch and do not have it yet, an approximate figure is enough — it moves the value-related line and the percentage, and nothing else.

Contract works insurance, liability cover and any bond, as a percent of the sum.

Contract works and public liability insurance are usually a fraction of a percent between them; a performance bond adds more, and a parent company guarantee instead of a bond adds nothing but is not always accepted. Collateral warranties and professional indemnity, where the contract asks for design, sit here too. These scale with the contract sum rather than with time, so a delay does not increase them — which is why they are held separate from the weekly rate.

Total preliminaries

Needs your rates

This page does not assume a price. Enter yours and the answer appears here.

Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope
  • Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value
  • The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay

Inputs used

Programme Duration
26
Full-Time Site Staff
2
Cost Per Person Per Week
Accommodation and Welfare Per Week
Temporary Services and Waste Per Week
Plant Standing Per Week
Setting Up (One-Off)
12000
Clearing Away (One-Off)
6000
Contract Sum
1000000
Insurance and Bonds
1.2
Final resultNaN

What this calculation does not cover

  • Every rate here is a quote, not a published figure — the site does not carry regional prices for site staff, accommodation hire or plant standing.
  • Head office overhead and profit are NOT included. These are the cost of running the site; the mark-up that carries the business sits on top and is a separate decision.
  • Assumes one continuous period of possession. A phased or sectional contract carries its setting-up more than once and needs a run for each section.
  • Attendances a main contractor provides to subcontractors — scaffold use, hoist time, task lighting, cleaning up after them — are often priced within the trades instead. Wherever they are, they must appear exactly once.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-02 · in the site-wide review of 2026-09-06 · v1.0.0

Regulatory standards & verification citations3
  1. Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope
  2. Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value
  3. The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for.

How to calculate construction preliminaries (general conditions) in 11 steps

  1. Programme DurationThe contract period in weeks, from possession of the site to practical completion.
  2. Full-Time Site StaffPeople on site full-time whose cost is not in any trade rate.
  3. Cost Per Person Per WeekAll-in weekly cost of one member of site staff.
  4. Accommodation and Welfare Per WeekWeekly hire of offices, canteen, drying room, toilets and stores.
  5. Temporary Services and Waste Per WeekPower, water, lighting, telecoms and skips, per week.
  6. Plant Standing Per WeekWeekly hire of plant that stands on site rather than belonging to a trade.
  7. Setting Up (One-Off)Mobilisation: hoarding, gates, signage, hardstanding, first connections.
  8. Clearing Away (One-Off)Demobilisation: removing everything and making the ground good.
  9. Contract SumThe contract value, used for the value-related items and the percentage check.
  10. Insurance and BondsContract works insurance, liability cover and any bond, as a percent of the sum.
  11. Total preliminariesThe tool computes the total preliminaries from those figures and shows the formula, its sources, and a confidence rating alongside it.

Frequently asked questions

What is the difference between preliminaries and overheads?
Preliminaries are the cost of running THIS site: the manager standing in this compound, these huts, this hoist. Head office overhead is the cost of running the business that sent them — the office, the estimators, the accounts department, the directors — and it is recovered as a percentage across every job. Mixing them is how a contractor ends up recovering the same cost twice on one job and not at all on the next. Price the site here, then add overhead and profit on top of the whole estimate.
Why separate the weekly rate from the fixed cost?
Because a delay repeats one and not the other. If a job overruns by six weeks you carry six more weeks of staff, huts, services and standing plant — but you do not set the site up a second time, and your insurance does not increase because the contract sum has not changed. The weekly time-related rate is therefore the number an extension of time is priced on, and a claim built on a proportion of the total would wrongly include mobilisation. It is also the number that tells you what accelerating is worth: if a week costs this much to stand still, that is your budget for avoiding it.
Should subcontractor attendances go in here?
Wherever you put them, exactly once. A main contractor commonly provides scaffold use, hoist time, task lighting, water, power and clearing away for its subcontractors, and there are two consistent ways to handle it: price those items here as prelims and take them out of the subcontract rates, or leave the subcontractors to price their own and keep them out of here. What loses money is doing neither — assuming the subcontractor carries it while they assume you do — and what loses just as much is doing both, and pricing yourself out.
My percentage came out much higher than 15%. Is the estimate wrong?
Not necessarily: on a small or short job it is usually right, and a four-week job can easily show 25% or more against the 8-15% common on a main building contract. Setting a site up costs roughly the same whether the contract is worth 40,000 or 400,000 — the same hoarding, the same welfare, the same connections — so the fixed element lands far heavier on the smaller one, and that 25% can be perfectly correct. What the high figure should prompt is a look at the programme: every week carries the full weekly rate whether or not anything is happening on site, so a duration padded for comfort is expensive in a way a padded material quantity is not.
Does this include the contractor's profit?
No. Everything here is cost — what leaves the bank to keep the site running. Overhead recovery and profit are applied to the estimate as a whole, after the measured work and these preliminaries are added together, and they are a commercial decision rather than a calculation. Treating prelims as a place to hide margin makes both numbers untrustworthy: the day a client asks for the prelims build-up, or a delay has to be priced from it, an inflated weekly rate is very hard to defend.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.