SettingsSettings for this calculationUS
The contract period in weeks, from possession of the site to practical completion.
Take it from the programme, not from the optimistic version in the tender letter. Every time-related item below runs for this whole span, including the weeks at the end when the value being certified has slowed to a trickle and the site staff are still there chasing snags. Under-stating the duration is the commonest way prelims come out short, because it discounts every line at once.
People on site full-time whose cost is not in any trade rate.
The site manager, the assistant, the engineer setting out, the storeman, the gateman. Anyone whose time is already inside a measured rate — the bricklayer, the electrician — is NOT counted here, or their cost lands in the estimate twice. Part-timers go in as a fraction: a visiting contracts manager one day a week is 0.2.
All-in weekly cost of one member of site staff.
All-in means salary plus the employer's on-costs — national insurance or payroll tax, pension, holiday accrual, sick pay, training, and the vehicle and fuel if one comes with the job. That total is commonly 25 to 40% above the bare salary, and estimates that use the salary alone are short by exactly that margin on the biggest prelims item there is.
Weekly hire of offices, canteen, drying room, toilets and stores.
Welfare is not optional and is not negotiable down: the regulations set what has to be provided from day one, and an inspector who finds it missing can stop the job. Include the servicing — the toilets are emptied on a contract, and that contract runs weekly whether the job is busy or quiet.
Power, water, lighting, telecoms and skips, per week.
Temporary power on a construction site is metered at commercial rates through a supply that also has a standing charge, and the lighting runs longest in the months when the daylight does not. Skips belong here rather than in the trades: waste arrives from every trade at once and no single rate carries it.
Weekly hire of plant that stands on site rather than belonging to a trade.
The hoist, the tower crane, the telehandler, the site-wide access. What makes this a prelim rather than a trade cost is that it is hired for the duration and charged whether or not it turned a wheel that week — the crane is on hire through the fortnight the steel was late. Plant hired in for one operation and sent back belongs in that operation's rate instead.
Mobilisation: hoarding, gates, signage, hardstanding, first connections.
Everything paid once to turn a piece of ground into a site. Delivery and craning-in of the accommodation, the hoarding and gates, the temporary road or hardstanding, the incoming power and water connections, the site signage and first-aid provision. A delay does not repeat these, which is exactly why they are kept out of the weekly rate below.
Demobilisation: removing everything and making the ground good.
Collection of the accommodation and plant, taking down the hoarding, disconnecting the temporary services, the final clean, and reinstating whatever the compound stood on. Routinely left out on the grounds that it is somebody else's problem by then, and it is not — it is in the contract and it lands in the last month, when there is no value left to certify against it.
The contract value, used for the value-related items and the percentage check.
Enter the sum including the preliminaries themselves, since that is what insurance and bonds are priced against and what the resulting percentage is normally quoted as. If you are building the number up from scratch and do not have it yet, an approximate figure is enough — it moves the value-related line and the percentage, and nothing else.
Contract works insurance, liability cover and any bond, as a percent of the sum.
Contract works and public liability insurance are usually a fraction of a percent between them; a performance bond adds more, and a parent company guarantee instead of a bond adds nothing but is not always accepted. Collateral warranties and professional indemnity, where the contract asks for design, sit here too. These scale with the contract sum rather than with time, so a delay does not increase them — which is why they are held separate from the weekly rate.
Total preliminaries
Needs your rates
This page does not assume a price. Enter yours and the answer appears here.
They open the calculator with your figures already in it
Construction Preliminaries (General Conditions) Calculator — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope
- Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value
- The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay
Inputs used
- Programme Duration
- 26
- Full-Time Site Staff
- 2
- Cost Per Person Per Week
- Accommodation and Welfare Per Week
- Temporary Services and Waste Per Week
- Plant Standing Per Week
- Setting Up (One-Off)
- 12000
- Clearing Away (One-Off)
- 6000
- Contract Sum
- 1000000
- Insurance and Bonds
- 1.2
What this calculation does not cover
- Every rate here is a quote, not a published figure — the site does not carry regional prices for site staff, accommodation hire or plant standing.
- Head office overhead and profit are NOT included. These are the cost of running the site; the mark-up that carries the business sits on top and is a separate decision.
- Assumes one continuous period of possession. A phased or sectional contract carries its setting-up more than once and needs a run for each section.
- Attendances a main contractor provides to subcontractors — scaffold use, hoist time, task lighting, cleaning up after them — are often priced within the trades instead. Wherever they are, they must appear exactly once.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-02 · in the site-wide review of 2026-09-06 · v1.0.0
Regulatory standards & verification citations3
- Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope
- Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value
- The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.