SettingsSettings for this calculationUS
How far past the completion date the job is expected to finish.
Use the forecast overrun, not the delay accrued so far — the decision to accelerate is made against where the programme is heading. If some of the overrun is already covered by an extension of time that has been granted, deduct those weeks and run only what remains, because they are a different case with a different answer.
Which of the three cases applies, because they cost completely different amounts.
A culpable week carries damages AND prolongation, both on the contractor. A neutral event — exceptional weather is the usual example — earns an extension that stops the damages, but nobody pays for the extra weeks, so the prolongation is still yours. An employer delay earns both an extension and loss and expense, so in principle it costs nothing. In principle: an entitlement that was never notified in the form and within the period the contract requires is routinely lost, and this page assumes notice was given properly.
The rate stated in the contract, not an estimate of the employer's loss.
Liquidated damages are pre-agreed precisely so nobody has to prove actual loss, so the figure comes off the contract particulars and nowhere else. A rate set so high that it is a penalty rather than a genuine pre-estimate of loss may be unenforceable in some jurisdictions — but that is an argument to have with a lawyer, not a reason to plan around a lower number.
The total damages cap in the contract. Enter 0 if there is no cap.
Commonly stated as a percentage of the contract sum — 5% and 10% are both ordinary — which on a 900,000 contract at 10% is 90,000. The cap matters more than it looks: once it is reached, further delay costs only the prolongation, so the value of catching up falls sharply at exactly the moment the job feels most urgent. Enter 0 only if the contract genuinely has no limit, which is unusual and worth checking rather than assuming.
What the site costs to keep open for a week: staff, accommodation, services, plant standing.
The Preliminaries calculator on this site produces exactly this figure and labels it as the cost of one week's delay. It must exclude the fixed charges — setting up and clearing away — because a delay does not repeat those, and a prolongation claim that includes them will be reduced by the amount as soon as anyone looks.
What overtime, extra crews or additional plant would cost to recover the time.
Price it honestly, including what acceleration does to productivity rather than only what it adds to the wage bill. Sustained overtime loses output per hour, a second crew on the same face gets in the way of the first, and both raise the defect rate — so the real cost of buying back four weeks is usually well above four weeks of extra labour. Enter zero if you only want the cost of the delay itself.
How much of the delay the spend above would actually claw back.
Be pessimistic. Acceleration plans routinely deliver about half what they promise, because the constraint is usually not labour hours — it is a sequence, an inspection, a lead time or a single trade that cannot be doubled up. Recovering fewer weeks than planned while paying the full cost is the normal outcome, and it is worth running this at half the optimistic figure to see whether the decision survives.
Cost of the delay
$47,100
Recovering 4 weeks saves 31400 against a spend of 30000, so accelerating is worth 1400 on these figures. Before committing, halve the weeks recovered and run it again — acceleration plans routinely deliver about half what they promise, because the constraint is usually a sequence or a lead time rather than labour hours, and a plan that only survives at the optimistic figure is not a plan.
- Liquidated damages
- $21,000
- Prolongation borne
- $26,100
- Saving from recovering 4 week(s)
- $31,400
- Cost of that acceleration
- $30,000
- Net of accelerating
- $1,400
- Most it is worth spending to recover those weeks
- $31,400
They open the calculator with your figures already in it
Delay Cost and Acceleration Break-Even Calculator: 47,100 currency — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Liquidated damages are a pre-agreed rate stated in the contract, recoverable without proof of actual loss, and in most standard forms subject to a stated maximum expressed as a percentage of the contract sum; once that maximum is reached no further damages accrue however long the delay continues
- Standard forms distinguish culpable delay (damages apply, prolongation borne by the contractor), excusable non-compensable delay such as exceptional weather (an extension of time stops damages but carries no money), and excusable compensable delay caused by the employer (an extension plus loss and expense, which recovers time-related costs)
- Loss and expense for prolongation is evaluated on the time-related preliminaries actually incurred over the extended period, not as a percentage of the contract sum, and requires notice and substantiation under every standard form
Inputs used
- Weeks of Delay
- 6
- Whose Delay Is It
- The contractor's — damages run, prolongation borne
- Liquidated Damages Per Week
- 3500
- Maximum Damages
- 90000
- Time-Related Preliminaries Per Week
- 4350
- Cost of Acceleration Being Considered
- 30000
- Weeks That Acceleration Would Recover
- 4
Intermediate steps
- Liquidated damages
- $21,000
- Prolongation borne
- $26,100
- Saving from recovering 4 week(s)
- $31,400
- Cost of that acceleration
- $30,000
- Net of accelerating
- $1,400
- Most it is worth spending to recover those weeks
- $31,400
Confidence note: Recovering 4 weeks saves 31400 against a spend of 30000, so accelerating is worth 1400 on these figures. Before committing, halve the weeks recovered and run it again — acceleration plans routinely deliver about half what they promise, because the constraint is usually a sequence or a lead time rather than labour hours, and a plan that only survives at the optimistic figure is not a plan.
What this calculation does not cover
- The contract governs. The damages rate, the cap, what counts as an excusable event and the notice a claim requires are all in it and none of them are here.
- Assumes any entitlement has been properly notified within the contractual period. Unnotified entitlement is routinely worth nothing whatever its merits.
- Damages are treated as running weekly. Some contracts state them per day or per calendar month, and a partial period then rounds differently.
- Acceleration is priced as a single figure you supply, not modelled. Lost productivity under sustained overtime and trade stacking are real and belong inside that figure.
- Consequential losses beyond the contract's damages — a lost tenancy, a missed season, a reputational cost — are outside a liquidated damages regime and outside this page.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-02 · in the site-wide review of 2026-09-06 · v1.0.0
Regulatory standards & verification citations3
- Liquidated damages are a pre-agreed rate stated in the contract, recoverable without proof of actual loss, and in most standard forms subject to a stated maximum expressed as a percentage of the contract sum; once that maximum is reached no further damages accrue however long the delay continues
- Standard forms distinguish culpable delay (damages apply, prolongation borne by the contractor), excusable non-compensable delay such as exceptional weather (an extension of time stops damages but carries no money), and excusable compensable delay caused by the employer (an extension plus loss and expense, which recovers time-related costs)
- Loss and expense for prolongation is evaluated on the time-related preliminaries actually incurred over the extended period, not as a percentage of the contract sum, and requires notice and substantiation under every standard form
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.