SettingsSettings for this calculationUS
The original contract sum, before variations.
The retention cap is a percentage of THIS figure, which is why it is asked for even though the valuation is built from measured work. Whether agreed variations enlarge the sum the cap is taken on depends on the contract — most standard forms base it on the original sum, so that is what this uses.
Cumulative value of measured work completed, not this month's slice.
CUMULATIVE, not the increment — that is what makes the whole method self-correcting. If last month over-measured a floor slab, entering the true cumulative figure this month simply reduces what is due now, with no credit note and no argument. 'Properly executed' is doing real work in that phrase: defective work is not valued, and neither is work that has been done out of sequence in a way the contract does not accept.
Cumulative value of variations agreed and executed. Omissions go in negative.
Only what has been AGREED and DONE. A variation instructed but not yet valued has no place in a certificate — it goes in the application as a notified sum and gets argued separately, and putting an optimistic figure here is the fastest way to have the whole certificate held up. An omission is a negative number, and omissions are routinely forgotten because nobody chases a credit.
Unfixed materials delivered and stored on site.
Payable in most standard forms where they are on site at the right time, properly protected and reasonably brought there. Title passes ON payment rather than before it — that is the direction, and getting it backwards costs money: a supplier's retention-of-title clause does NOT disqualify materials from an on-site valuation, and a contractor who drops the line because the supplier is unpaid has given away a certificate they were entitled to. Keep the line separate month to month: as each batch is built in it moves into the measured work, and a batch counted in both places is paid for twice. Materials stored OFF site are a different and far stricter test, usually excluded without a vesting agreement and a bond.
Percent withheld from the cumulative gross valuation.
5% is the common rate on a main contract, often halving to 2.5% at practical completion and releasing entirely at the end of the defects liability period. It is applied to the CUMULATIVE gross figure, not to each month's increment — the two agree only while nothing is ever revalued downward.
Maximum retention held, as a percent of the contract sum. Enter 0 for no limit.
The rate and the limit are two different numbers and both are in the contract: 5% withheld up to a total of 3% of the contract sum is the ordinary pairing. Once the limit is reached, no further retention comes off — which happens at 60% complete on those figures, and from there every certificate is larger than a naive 5% calculation says. Missing this under-values every application through the back half of a job, which is exactly when cash is tightest.
Sum of all previous certificates, net of retention, before this one.
The NET figure — what was actually certified after retention — not the gross valuations those certificates were built from. Mixing the two is a common slip and it shows up as a certificate that looks roughly right but is out by the retention on every previous month at once.
Anything the contract lets the payer deduct from this certificate.
Liquidated damages where a completion date has passed, the cost of work the employer has had done by others after a notice, plant or attendance supplied and rechargeable, insurance excesses. Most standard forms require notice before a deduction is valid, and a deduction made without one is usually recoverable — so enter what has been properly notified rather than what somebody intends to withhold.
Net due on this certificate
$100,900
Retention is still accruing at 5% and will stop at 27000, which on these figures is a cumulative gross of about 540000. Keep the materials-on-site line separate month to month: as each batch is built in it moves into the measured work, and a batch left in both places is paid for twice.
- Gross valuation to date
- $422,000
- Retention held
- $21,100
- Valuation less retention
- $400,900
- Less previously certified
- $300,000
- Less deductions
- $0
- Progress against the adjusted sum
- 45.67 %
- Net due, unrounded
- $100,900
They open the calculator with your figures already in it
Interim Payment Valuation Calculator (Certificate Due): 100,900 currency — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Standard forms of building contract (JCT, NEC, FIDIC and the AIA payment application) all value interim payments on the CUMULATIVE value of work properly executed to the valuation date, deduct retention from that cumulative figure, and then deduct the total previously certified — so an over- or under-measure in an earlier month self-corrects rather than compounding
- Retention is commonly deducted at 5% of the cumulative gross valuation, LIMITED to a total of 3% of the contract sum; once that limit is reached no further retention is withheld, however much work follows
- Materials and goods on site but not yet incorporated are payable in most standard forms where they are on site at the right time, adequately protected and reasonably brought there; title then passes TO the employer once the amount has been included in a certificate and paid. Materials stored OFF site are treated far more strictly and are commonly excluded entirely without a vesting agreement and a bond
Inputs used
- Contract Sum
- 900000
- Work Properly Executed To Date
- 380000
- Agreed Variations To Date
- 24000
- Materials On Site, Not Yet Built In
- 18000
- Retention Rate
- 5
- Retention Limit
- 3
- Total Previously Certified
- 300000
- Deductions and Contra Charges
- 0
Intermediate steps
- Gross valuation to date
- $422,000
- Retention held
- $21,100
- Valuation less retention
- $400,900
- Less previously certified
- $300,000
- Less deductions
- $0
- Progress against the adjusted sum
- 45.67 %
- Net due, unrounded
- $100,900
Confidence note: Retention is still accruing at 5% and will stop at 27000, which on these figures is a cumulative gross of about 540000. Keep the materials-on-site line separate month to month: as each batch is built in it moves into the measured work, and a batch left in both places is paid for twice.
What this calculation does not cover
- The contract governs, not this page: the rate, the limit, what counts as properly executed and whether a deduction has been validly notified are all things it decides.
- Sales tax is excluded on every line. It is added to the certified amount at the end, on whatever basis the contract and the jurisdiction set.
- Assumes retention at one rate. Where a contract halves the rate at practical completion, run the two periods separately.
- Off-site materials are not distinguished here; most standard forms exclude them without a vesting certificate and a bond, so they usually do not belong in the materials line at all.
- No interest, financing charge or late-payment entitlement is calculated.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-06 · in the site-wide review of 2026-09-06 · v1.0.1
Regulatory standards & verification citations3
- Standard forms of building contract (JCT, NEC, FIDIC and the AIA payment application) all value interim payments on the CUMULATIVE value of work properly executed to the valuation date, deduct retention from that cumulative figure, and then deduct the total previously certified — so an over- or under-measure in an earlier month self-corrects rather than compounding
- Retention is commonly deducted at 5% of the cumulative gross valuation, LIMITED to a total of 3% of the contract sum; once that limit is reached no further retention is withheld, however much work follows
- Materials and goods on site but not yet incorporated are payable in most standard forms where they are on site at the right time, adequately protected and reasonably brought there; title then passes TO the employer once the amount has been included in a certificate and paid. Materials stored OFF site are treated far more strictly and are commonly excluded entirely without a vesting agreement and a bond
Which documents these citations point at
- National Electrical Code (NFPA 70) (United States)Electrical installations — conductor sizing and protection, load calculation, wiring methods, grounding and working clearances.
A code or standard has force only where a jurisdiction has adopted it, usually with local amendments. This site holds no adoption data for any authority, so check what is in force with the authority where you build. Any section cited above without an edition should be checked against the edition in force where you build. What it would take to know.
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.