Tuesday afternoon, and the bifold is nine weeks out
The steels are in, the opening is formed, and the blockwork has reached the head. The client comes down the garden with her phone held out and a photograph of somebody else's kitchen on it: a fixed pane with a single side-hung door beside it, instead of the three-leaf bifold on the drawing she approved in March. Before you get too far, she says, could we? The builder says he will look into it, which is the correct answer, and it is the last correct thing that happens for four days.
Because the bifold is not something that will be bought. It is something that has been bought. A deposit went to the fabricator eleven days ago, a survey is booked, and somewhere in a factory a cutting list either has or has not been released. Whether her question costs the price of a phone call or the price of a doorset is decided entirely by which side of that release the call falls on, and nobody standing in the garden knows which side that is.
What follows is the sequence that turns could we into a signed line — one side of one page, ten fields — and does it before anybody telephones the fabricator. The order of operations is the whole of it: an instruction that is dated and properly authorised, a price built on a stated basis, an answer about time given in the same breath as the answer about money, and only then the amendment to the supply order. Reverse any two of those and somebody ends up paying for a door that nobody wants.
Nobody has instructed anything yet
A client wanting something is not an instruction. It is the reason an instruction might be issued. That sounds like pedantry while you are standing on a lawn, and it stops sounding like pedantry the first time two people remember the same conversation differently. What makes an instruction is that it identifies the change, carries a date, and comes from somebody with the authority to commit the money.
Authority is the part that gets skipped on domestic work, because there is usually only one person there. Check it anyway. Joint owners where only one is on site. A client drawing down a lender's staged advance against a valuation of a scheme the lender holds a drawing of. A landlord whose managing agent is the party actually named on the contract. A builder who takes his instruction from whoever is standing nearest the work is exposed exactly as far as that person's authority fails to run, and he finds out at the end.
The standard forms all solve this the same way, and the solution is worth borrowing on a job that uses none of them. Under the JCT Minor Works Building Contract and the Building Contract for a Home Owner/Occupier, a change arrives as an instruction from the person the contract names as able to give one, and the contractor's protection is that anything said aloud is confirmed in writing before it is acted upon. NEC4 goes further and makes the two things one thing: the Project Manager gives an instruction changing the Scope, and clause 60.1(1) makes that instruction a compensation event in itself, so the change to the work and the entitlement it creates are notified together rather than argued over separately six weeks later.
AIA A201 is the most useful of the three at domestic scale, because its Article 7 separates three instruments the trade habitually calls by one name. A Change Order under Section 7.2 is agreement: scope, money and time, signed by owner, architect and contractor, issued on AIA Document G701, and it is what everybody pictures when they say variation. A Construction Change Directive under Section 7.3, issued on G714, is what you reach for when the work genuinely cannot wait for a price — the owner and architect direct it, the contractor performs it, and the adjustment is settled afterwards by a method the article sets out, with the contractor keeping an itemised accounting in the meantime. A minor change under Section 7.4 is the architect alone, on the express footing that it affects neither the contract sum nor the contract time.
The door question is the first of those three. Nothing is stopping, no gang is standing in a trench, and the only reason to reach for either of the others is that somebody has already telephoned the fabricator.
- Date and hour the instruction was given, because the fabricator's release is also dated and the two have to be compared.
- What comes out, identified by its drawing reference and its line on the schedule rather than by description alone.
- What goes in, specified tightly enough for a supplier to quote from it: leaf configuration, opening direction, threshold, finish, glass specification, and the structural opening it now has to fit.
- Who gave it, in full — and on whose authority, where more than one person owns the building or a lender is funding it.
- Whether the contractor is authorised to hold, amend or cancel any existing order while the price is being obtained, and if so which order.
- That the price and the effect on the completion date are both to be returned before the change is confirmed, and that nothing is ordered until they are.
The deadline belongs to the fabricator
On a variation that is only labour, the price is what it costs to do the new thing instead of the old thing. On a variation that involves a bought item with a lead time, the price is what it costs to do the new thing, plus what it costs to stop the old one, plus whatever has already been built to the old one's dimensions. The second and third of those are invisible from the garden and are frequently the larger.
So the first call is not to the client with a price. It is to the supplier with a question, and the question is narrow: what is the state of this order today, and what does amending or cancelling it cost. An order passes through a set of states — quoted, placed with a deposit, surveyed, released to manufacture, made, delivered, installed — and the cost of the answer steps up at each boundary. Across one of those boundaries the difference is an administration charge. Across another it is the entire value of a made-to-size item that no second buyer exists for.
There is a consumer-law point here and it runs opposite to the direction people expect. The Consumer Contracts (Information, Cancellation and Additional Charges) Regulations 2013 give a client cancellation rights against a builder in the right circumstances, but regulation 28 lifts those rights off several kinds of contract, among them goods made to the consumer's specifications or clearly personalised. More to the point, the order for the doors is not the client's contract at all. It is the builder's, with a fabricator, business to business, and it is governed by that fabricator's own terms of sale — which are the terms that actually decide what cancelling the doors costs, and which nobody in this story has read.
Read them before answering, and read for three lines specifically: the point at which the order stops being cancellable, the charge for amendment as distinct from the charge for cancellation, and whether the deposit is applied or forfeited. Amendment is very often available where cancellation is not, and a fabricator willing to change a configuration on an unreleased order for a handling fee is offering a completely different answer from the one the client is bracing herself for. Get that answer in writing from the supplier before it is repeated to the client, because it will be repeated as a promise.
| State of the order | What can still be changed | What is already committed |
|---|---|---|
| Quoted, nothing placed | Everything — configuration, sizes, finish, hardware, supplier | An estimator's afternoon, and a lead time that now restarts from today |
| Placed and deposit paid, not yet surveyed | Usually the whole specification, by amendment rather than by cancellation | A handling charge under the supplier's terms, and the slot in the queue |
| Surveyed | The specification, but the survey has to be done again | The survey visit, and any structural opening already set out to the surveyed dimension |
| Released to manufacture | Nothing without a settlement; profiles are being cut to a list | Material for a made item, and a production slot somebody else wanted |
| Made, awaiting delivery | Nothing; the item exists and fits exactly one opening | The full value of a made-to-size unit with no resale |
| Delivered to site | Nothing; storage and damage risk have already transferred | The item, the delivery, and the crew who took it off the lorry |
| Installed | Nothing; the change has become a strip-out | The item, the installation, the perimeter seal, and making good either side of it |
Put the whole cost of the change into the work field, not the difference between two doors — the new doorset, the fitting, the resurvey, and whatever the fabricator charges to stop the old order. Then apply the rate the contract already fixes for varied work, and the flat handling charge if it carries one. That total is what the client is being asked to agree to, and it is the only figure worth putting in front of her.
Your direct material + labor cost for the added scope.
Markup applied to the additional work, same as your normal project markup.
A flat fee covering paperwork, re-scheduling, and coordination overhead.
Total change order cost
$2,400
- Markup amount
- $300
They open the calculator with your figures already in it
Change Order Cost Calculator: 2,400 $ (total change order cost) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
What this calculation does not cover
- Markup lands on the added work cost alone — the administrative fee is added after it and is never marked up, so a contract that allows markup on the processing charge will settle slightly above this figure.
- One percentage covers the whole variation, with no split between overhead and profit and no separate rate for subcontracted work; where a sub's price already carries its own uplift, no second tier is stacked on top of it here.
- Time is absent from the arithmetic. Nothing is priced for extra days on site, extended preliminaries, or the disruption to work already sequenced around the original scope, which on a mid-project change is often the larger number.
- The flat fee is counted once per run. Several small variations that each trigger their own charge, or one order bundling unrelated items, have to be worked through individually rather than as a single lump.
- Deductive changes have no route in: the added work cost cannot be taken below zero, so a credit for scope removed has to be handled as its own line away from this page.
- The added work cost is entered as one figure, so nothing distinguishes short-notice material pricing, restocking on cancelled orders, or remedial work to undo what was already built — those belong inside the number you type, or they are missing from the total.
The old opening was approved and the new one has not been
A door change is a change to the envelope, and the envelope was approved on the strength of the door being deleted. Building control was notified of a scheme. An energy calculation counted a glazed area. Somewhere in that elevation there may be an opening a bedroom is relying on. Confirming a price before those are checked is agreeing to pay for something that may not be permitted, and the second variation that corrects it will be argued about on much worse terms than the first.
In England and Wales the checks a door swap re-opens are few and quick. Approved Document L, Volume 1 sets limiting standards for windows and doors and allows compliance to be demonstrated on an area-weighted basis, so replacing a large glazed unit with a smaller one moves the sum in the direction that usually helps and occasionally does not, depending on what else in the extension was carrying it. Approved Document B is the one to verify rather than assume: if escape from a room depended on an opening in that wall, the replacement has to preserve it, and a fixed pane preserves nothing. Approved Document K governs glazing in critical locations, with impact performance classified to BS EN 12600, and the doorset's own weathertightness, operation and strength are classified to BS 6375. Approved Document Q applies to new dwellings rather than to an extension of an existing one, so security performance here is a contractual choice rather than a regulatory duty — which is worth writing down as a choice, so that nobody later mistakes it for a requirement somebody dropped.
The American equivalents sit in the same places and behave the same way. IRC Section R310 covers emergency escape and rescue openings, Section R308 covers safety glazing, installation is normally referred to ASTM E2112, and product performance to AAMA/WDMA/CSA 101/I.S.2/A440. Wherever the job is, the point is procedural rather than technical: the check takes ten minutes on the telephone to whoever is inspecting the job, and the answer belongs on the variation sheet as a line of its own — approvals checked, by whom, on what date — because it is the line that stops the price being agreed twice. Note the resurvey while you are there. BS 8213-4 is the code of practice standing behind the survey and installation of external doorsets, and a changed configuration means the survey the fabricator has already done no longer describes anything.
Which of four bases the number is built on
A price with no stated basis is a number somebody made up, and on the page it is indistinguishable from a number somebody worked out. The habit worth acquiring is to write the basis above the figure, in four or five words, before the figure exists. It costs nothing and it converts every later disagreement from an argument about trustworthiness into an argument about a rate, which is a much shorter argument.
The bases are not a matter of taste; the standard forms name them, and the naming is the useful part. JCT's Standard Building Contract collects them as valuation rules and puts them in a hierarchy. Where the changed work is of similar character to work already priced in the contract, carried out under similar conditions and without significant change in quantity, it is valued at the contract rates. Where the character is similar but the conditions or the quantities have moved, those rates are the starting point and are adjusted — a pro-rata valuation, with the adjustment written down rather than absorbed. Where nothing in the contract resembles it, it is a fair valuation. And where it cannot properly be measured at all, it goes on daywork, with the prime cost defined by the RICS Definition of Prime Cost of Daywork carried out under a Building Contract and the percentage additions taken from the contract rather than invented at the end of the job.
NEC4 does it differently and instructively. A compensation event is assessed on the forecast Defined Cost of the work not yet done, plus the Fee, and it is assessed on that forecast even where the actual turns out otherwise — which puts the risk of the forecast on whoever made it, and is the entire reason the quotation goes in before the work starts. Clauses 62 and 63 carry that machinery, and clause 61.3 puts an eight-week limit on a contractor notifying an event he has become aware of — a limit that does not bite where the event arose from the Project Manager's own instruction, which is the single best argument for having the instruction issued from the other side in writing. AIA A201's Article 7 offers the same menu more directly: mutual acceptance of a lump sum with supporting data, unit prices already stated in the contract, cost of the work plus a fee, or, failing agreement, the method the article provides with an itemised accounting kept as the work proceeds.
On the doors, three of those four bases are live and the fourth is not, and the price should be written as three lines rather than blended into one. The fitting is similar-character work already priced in the contract, so it starts at contract rates and is then adjusted pro rata for the fact that hanging one leaf is not hanging three — two of the bases, arriving on one line. The new doorset resembles nothing in the priced document, so it is a fair valuation, and the supplier's quotation is the evidence that makes it one rather than an assertion. The abortive element — the settlement with the fabricator, the resurvey, the wasted delivery slot — is a fair valuation as well, evidenced by third-party invoices rather than by any rate. Daywork is the basis that stays out of this one, because every part of it can be measured in advance. Blended into a single figure, the client is asked to accept an opaque number and will reasonably resist it. Split into three, each line can be disputed on its own terms, and two of them usually are not disputed at all.
| Basis | When it applies | What it stands on |
|---|---|---|
| Contract rates | Similar character, similar conditions, comparable quantity | The priced document already agreed — no new arithmetic and nothing to negotiate |
| Pro-rata rates | Similar character, but access, conditions or quantity have moved | The contract rate plus a stated, written adjustment for what actually changed |
| Fair valuation | Nothing in the contract resembles it: abortive work, a supplier settlement, a repeat survey | Third-party invoices, the supplier's terms of sale, and a build-up the other side can follow |
| Daywork | The work cannot properly be measured — opening up, chasing an unknown, standing time | Timesheets signed on the day, with percentage additions taken from the contract |
The credit is not the addition run backwards
The bifold coming out has a value, and the argument about that value outlasts every other argument on the sheet, because the two parties are working from different numbers without either of them realising it. The client is thinking of the price the bifold appeared at in the quotation, which carried the builder's overhead and profit inside it. The builder is thinking of what he can actually recover, which after a settlement with the fabricator may be very little, and which certainly does not include the overhead already spent placing, chasing and now unwinding the order.
The contractual answer is written down and worth knowing before the conversation rather than during it. Article 7 of AIA A201 provides that where a single change carries both an addition and a related deletion, the allowance for overhead and profit is figured on the net increase if there is one — so the builder does not earn twice on a swap, and equally does not hand back margin on work he is still doing. The credit itself is the actual net cost of the deletion, not the price at which the item was sold. On a contract carrying no such wording the same outcome has to be negotiated, and the negotiation goes very much better when both build-ups have been put on the table side by side rather than exchanged as two bare totals.
There is a limit running the other way too, and it is not intuitive. A variation clause lets an employer change the work; it does not generally let an employer take work out of the contract in order to give it to somebody else. That principle is old and settled — the High Court of Australia decided it in Carr v J A Berriman Pty Ltd, where an owner omitted work and had it carried out by another contractor, and the omission was held to be a breach rather than a variation. It matters here in exactly one shape, and that shape is common: a client who has changed her mind about the doors and also intends to buy them herself from a showroom is not instructing a variation at all. She is removing scope and appointing a second supplier, and the builder's fitting price, his warranty position, his insurance and his programme all move with it. Say that out loud before the sheet is signed, rather than on the morning a pallet arrives that nobody was expecting.
Run it twice. Once for what goes in — the doorset from the supplier's quotation, the fitter's time, the repeat survey — at the rate the contract fixes for varied work. Then once for what comes out, at the cost the builder can genuinely recover rather than the price the item was sold at. The gap between the two totals is the net the sheet has to state, and having both build-ups visible is what keeps the conversation about arithmetic instead of about whose figure is bigger.
Your direct cost for materials on this job.
Your direct labor cost for this job (wages, not billed rate).
The percentage added on top of costs to cover overhead and profit.
Total price to charge
$9,600
- Cost subtotal
- $8,000
- Markup amount
- $1,600
- Gross margin on the price
- 16.67 %
They open the calculator with your figures already in it
Contractor Markup Calculator: 9,600 $ (total price to charge) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
What this calculation does not cover
- Only two cost lines feed the subtotal — materials and labor. Permits, equipment and tool rental, dumpster and disposal fees, subcontractor invoices, insurance, fuel and supervision are not inputs, so anything you have not already buried inside those two figures is neither marked up nor billed.
- Materials and labor are marked up at one identical rate, because the percentage is applied once to their combined subtotal. If you price material at one percentage and labor at another — a common split — price the two separately and add the results, since a single blended figure here will not reproduce that.
- The markup amount in the breakdown is gross, not profit: it is the one figure that has to carry overhead and profit together, and there is no overhead input to separate them. Office costs, vehicles, estimating time and idle days come out of that same amount before anything is left over.
- The gross margin row is the same money expressed against the price instead of against the cost, and it is always the smaller percentage of the two — a 20 per cent markup is a 16.7 per cent margin. It is shown because the two are routinely used interchangeably and are not equal; it is still gross, so overhead has not been taken out of it, and it is not a net profit figure.
- Nothing is added after the markup — the total is exactly the subtotal multiplied by one plus your percentage. Sales tax, VAT or GST, permit fees passed through to the client, and card or financing charges all sit outside it, so the number is a price to quote rather than a finished invoice.
- The costs you enter are treated as final and already known. There is no waste allowance and no contingency term, so if supplier prices move between quote and purchase or the hours run long, the overrun comes out of the markup instead of being added to the price.
- Each cost line accepts up to 500,000 and the markup up to 200 per cent, which caps how large a single job this will price without splitting it. The currency is a label only: the answer comes back in whatever currency you typed the costs in, with no conversion and no rounding to a tidy quotable figure.
Time is the second answer and it is due with the first
A price agreed without an answer about time is half an agreement, and it is the half that produces the row in week fourteen. These doors sit on the critical path: the opening cannot be closed, the plasterer cannot start on that elevation, the scaffold cannot come down and the client cannot have her kitchen back. A new order restarts a lead time, and it restarts from the day the amended order is confirmed rather than from the day she changed her mind.
Two distinct sums live in here and blending them is the commonest error on a small job. The first is the direct cost of the change: the doorset, the labour, the abortive work. The second is the cost of the job simply taking longer — further weeks of scaffold hire, welfare, fencing, insurance, plant standing idle, and supervision that continues whether or not anybody is working. NEC4's discipline is the one to copy here: the quotation for a compensation event covers changes to the Prices and to the Completion Date in one document, submitted before the instruction is confirmed. The Society of Construction Law's Delay and Disruption Protocol argues the same case from the opposite end, that an entitlement assessed while the facts are still visible is worth far more than one reconstructed out of invoices at the end of the job.
Do not assume the two move together, either. A change can cost money and no time at all. It can cost time and almost no money. And — the case that catches people — it can quietly consume float that some other item was relying on, so the doors themselves land on programme and the decorator does not. Whichever of the three it is, record the outcome as a revised completion date rather than as a number of weeks. A number of weeks has to be added to something, and nobody afterwards agrees what it was added to.
- The date the amended order is confirmed, which is where the new lead time actually begins.
- The revised delivery week, in writing from the fabricator, rather than the one offered on the telephone.
- Which trades were booked against the old delivery, and what it costs to move each of them.
- The time-related items that run whether or not work is happening: scaffold, welfare, fencing, plant, insurance, supervision.
- The revised completion date as a date, and whether any payment stage moves with it.
The register, and what it does to the money still unspent
One variation is a sheet of paper. Six are a register, and the difference between them is a running total. Number, date, who instructed it, the basis of valuation, the addition, the omission, the net, the effect on time, the revised contract sum and the revised completion date: ten columns, one line each, both parties initialling as they go. Kept from the first change it costs two minutes a fortnight. Started at the sixth it is an evening of forensic work against a message thread, done at the point in the job when neither party has an evening to spare.
The register earns its keep at a moment nobody plans for, which is when the accumulated net additions have moved the contract sum far enough that the original figure is no longer the number anybody is managing. Every job has that threshold. Past it, the sensible thing is to re-baseline the remaining work rather than keep tracking deviations from a document that has stopped describing the project. Naming the threshold in advance, as a figure written into the contract, is a five-minute decision at the start and an impossible one in the middle.
Which is where the buffer needs reading again. The contingency set at the outset was sized against the whole job and against the unknowns the whole job carried. Half way through, most of the work with unknowns in it — the ground, the drainage, the structure, the opening up — has been done and the money for it is largely spent. What matters from here is the buffer standing against the work that has not happened yet, and a confirmed variation moves that quantity in both directions at once: it consumes cash, and it introduces new work carrying its own risk. The stage-payments guide on this site draws the other line, between a change that is a discovery and a change that is a preference and where the money for each properly comes from; what belongs here is narrower and mechanical, which is that the buffer is recomputed after every confirmed variation against what is left rather than against what was originally signed.
Enter the value of the work still to come — the contract sum less what has already been certified, adjusted by the net of every variation confirmed so far — rather than the figure signed in March. The headline figure it returns is that remaining work with the buffer added back onto it; the buffer itself — the money standing between this job and its next surprise — is the contingency amount in the breakdown underneath, and that is the number to read. On a half-built extension with the ground and the structure already behind it, a smaller percentage against a smaller base is often the more honest answer than the one set before anybody had dug anything.
Your planned budget before adding a buffer for the unexpected.
The extra buffer to add for unexpected issues.
Total budget with contingency
$23,000
Contingency is a planning buffer, not a guarantee — projects that uncover major surprises (structural damage, code-required upgrades) can still exceed even a generous contingency.
- Contingency amount
- $3,000
They open the calculator with your figures already in it
Project Contingency Calculator: 23,000 $ (total recommended budget) — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
What this calculation does not cover
- The percentage is applied to the base budget as one flat multiplier, so every dollar of the job is treated as carrying identical risk. A $20,000 kitchen made up of $14,000 of fixed-price cabinetry already on order and $6,000 of demolition into an unknown wall gets the same $3,000 buffer at 15% as one that is speculative end to end. Where the risk sits in a single part of the scope, size a buffer against that part and add it to the rest rather than smearing one rate across the total.
- Nothing in the arithmetic is a fixed amount: the buffer is purely proportional, so it shrinks with the budget while many of the surprises it is meant to absorb do not. A failed inspection, half a day of extra excavation or an emergency call-out costs roughly the same on a $3,000 job as on a $300,000 one, yet 15% sets aside $450 on the first and $45,000 on the second. Small jobs are the ones a percentage rule quietly under-buffers.
- Whatever is missing from the base figure stays missing from the answer. The base budget is read as a single opaque number, so if permits, disposal, delivery charges or temporary accommodation were never counted in it, a 15% buffer on that total does not fund them — it scales an incomplete estimate rather than completing it.
- The output is a lump sum with no timing in it. No term asks when the money is drawn or how long ago the base was priced, so a buffer taken on a year-old estimate is a percentage of a stale number. Re-running the figure part-way through a job would need the remaining scope and the buffer already consumed, and neither is tracked here.
- The percent field accepts whole numbers from 5 to 50 and the base accepts $100 to $2,000,000; those are input bounds, not guidance about where your job belongs. The commonly cited 10-20% range is a general renovation figure, and nothing in the calculation weighs building age, how much structural work is involved, or how firm your quotes are to place you within it.
When none of it was written down
The failure case is worth rehearsing, because it is common and because it is not symmetrical. The builder takes the client's word in the garden on Tuesday, telephones the fabricator on Wednesday, pays a settlement, orders a different doorset and produces the bill in week nine. The client remembers asking a question and receiving no price. Neither of them is lying, and both of them are certain.
What is left at that point is thin. Where work has been done at a client's request and no price was agreed, section 51 of the Consumer Rights Act 2015 supplies a reasonable price — but at the client's request is precisely the fact in dispute, and it is the builder who has to prove it. A supplier's invoice proves money was spent; it proves nothing about who authorised the spending. The party who spent it without a signature carries that gap, and on domestic work that is nearly always the builder, because the client's exposure is limited to declining to pay while the builder's is cash that has already left. Nor is there a quick forum: the commercial payment and adjudication machinery does not reach a contract with a residential occupier, as the stage-payments guide sets out, so the route is the county court and getting there costs more than most door changes are worth.
The defence is cheap and it is not a contract clause. It is a dated note of the conversation, sent the same day, in something that carries a timestamp, saying what was asked for, roughly what it looks like it will cost, what it will do to the completion date, and that nothing will be ordered or cancelled until there is a reply. A client who does not reply has not agreed to anything. A client who replies has created the record. Either outcome is better than Wednesday's telephone call, and the note takes four minutes to write in a van.
Two initials, then the order is amended
The finished object is one side of one page: the register's ten columns filled in for a single change, with the deleted item identified by drawing reference and the replacement specified tightly enough for a fabricator to quote from. At the foot, two signatures and the same date written twice.
The order those fields are filled in is the only thing this page has really been about. The supplier is asked what the change costs before the client is told what it costs. The approvals are checked before the price is fixed. The time answer is given alongside the money answer rather than a fortnight behind it. And the amendment to the fabricator's order goes in after the signatures, never before — a rule that feels absurdly formal for a house extension right up until the first time somebody changes their mind twice.
Settle these before the fabricator is telephoned
Six things that turn a question asked in a garden into a variation that can be priced, dated and defended — all of them done while the original order can still be amended.
- Who is entitled to give the instruction, in writing — Joint owners, a lender funding against a drawing it holds, a managing agent named on the contract: a builder acting on the word of whoever is nearest the work is exposed exactly as far as that person's authority does not reach.
- The state of the existing order, from the supplier, today — Placed, surveyed, released to manufacture or made — the boundary the change falls on decides whether it costs a handling fee or the whole value of a unit that fits one opening and no other.
- The supplier's terms on amendment as against cancellation — Read for three lines: when the order stops being cancellable, what amendment costs compared with cancellation, and whether the deposit is applied or forfeited. Amendment is frequently available where cancellation is not.
- The approvals the deleted item was satisfying — Escape from the room, the area-weighted glazing sum, safety glazing in a critical location, and the survey that no longer describes the opening — checked and initialled before the price is agreed rather than after.
- A stated valuation basis for every line of the price — Contract rates adjusted pro rata for the fitting, a fair valuation on the supplier's quotation for the doorset, a fair valuation on invoices for the abortive work: three lines that can each be argued separately, rather than one number that can only be accepted or refused.
- A revised completion date, given with the price and not after it — The new lead time starts the day the amended order is confirmed. Record the outcome as a date, because a number of weeks has to be added to something and nobody afterwards agrees what.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.
