SettingsSettings for this calculationUS
The weekday of the first day on site.
If it is not a working day, the count begins on the next working day and the calendar days before it still count toward the total.
Which days of the week the site works.
A six-day week recovers time on long jobs and costs overtime or a second crew; seven days is usually shift work on a tight programme.
The duration in working days, from the programme or a duration calculator.
Whole working days. A part day counts as a day, because a finish is a date.
Public holidays and shutdown days inside the period that would otherwise have been worked.
Count only those that land on a day of the working week. A holiday on a Saturday does not delay a Monday-to-Friday job.
Calendar days from start to finish
29 days
Starting on a Monday, 20 working days and 1 holiday finish on a Monday, the 29th calendar day counting the start day as the first.
- Working days, holidays included
- 21 days
- Days not worked in between — weekends, rest days and holidays
- 9 days
- Calendar weeks
- 4.14 weeks
They open the calculator with your figures already in it
Working Days to Finish Calculator: 29 days — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Calendar counting as programmes use it: each calendar day from the start is counted, a day counts as worked only if it falls in the working week, and the finish is the day on which the required working days — plus any holidays that fall on working days — have been worked
Inputs used
- Day the Work Starts
- Monday
- Working Week
- Monday to Friday
- Working Days Needed
- 20
- Holidays Falling on Working Days
- 1
Intermediate steps
- Working days, holidays included
- 21 days
- Days not worked in between — weekends, rest days and holidays
- 9 days
- Calendar weeks
- 4.14 weeks
Confidence note: Starting on a Monday, 20 working days and 1 holiday finish on a Monday, the 29th calendar day counting the start day as the first.
What this calculation does not cover
- It counts weekdays, not dates, so it cannot know which holidays fall inside the period — you tell it how many.
- Weather days, which an honest programme allows for on outdoor work, are not included; add them as holidays if you want them in the count.
- The start day counts as day one whether or not it is worked.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-22 · v1.0.0
Regulatory standards & verification citations1
- Calendar counting as programmes use it: each calendar day from the start is counted, a day counts as worked only if it falls in the working week, and the finish is the day on which the required working days — plus any holidays that fall on working days — have been worked