The volume of crushed limestone in cubic yards.
About 1.35 short tons per cubic yard for dense-graded crushed limestone; dust content and gradation shift this either way.
Approximate weight
13.5 short tons
About 1.35 short tons per cubic yard for dense-graded crushed limestone; dust content and gradation shift this either way. A planning figure, not a specification. Confirm the actual density with your supplier before ordering by weight.
- Conversion factor applied
- 1.35 short tons per yd³
They open the calculator with your figures already in it
Crushed Limestone Cubic Yards to Tons Calculator: 13.5 short tons — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Typical bulk density used here: approximately 1.35 short tons per cubic yard
- Density varies with moisture, compaction and composition — the supplier's ticket weight governs
Inputs used
- Crushed Limestone volume (yd³)
- 10
Intermediate steps
- Conversion factor applied
- 1.35 short tons per yd³
Confidence note: About 1.35 short tons per cubic yard for dense-graded crushed limestone; dust content and gradation shift this either way. A planning figure, not a specification. Confirm the actual density with your supplier before ordering by weight.
What this calculation does not cover
- A heap judged by eye carries more error than the density ever will, and angular limestone with damp fines stands steeper than rounded gravel — steep enough to hold a cut face. Measure the shape that is there: base and height describe an intact cone, not a pile a loader has been into.
- Loads of stone are limited by weight, not by the capacity of the body: a tipper or a skip reaches its rated payload long before it is filled level. The yardage you started from will not tell you how many loads turn up — this tonnage will.
- This tonnage is a load as well as a purchase quantity, since a cubic yard of crushed limestone runs to well over a ton. Stockpiled on a suspended slab, over a basement, or beside an open excavation, it is a surcharge that has to have been allowed for.
Estimated cost — your price
This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-08-26 · in the site-wide review of 2026-09-06 · v1.0.0
Regulatory standards & verification citations2
- Typical bulk density used here: approximately 1.35 short tons per cubic yard
- Density varies with moisture, compaction and composition — the supplier's ticket weight governs
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.
Crushed limestone is the workhorse sub-base material across much of North America, specified as a compacted thickness and sold by the ton. The conversion has to account for the fact that dense-graded material is designed to compact hard: the loose yardage that arrives is meaningfully more than the yardage that ends up in place, because the fines migrate into the voids under a roller. Ordering against the compacted requirement without allowing for that loss leaves the sub-base under specification, which shows up years later as settlement rather than immediately as a shortfall.