Raised Access Floor Rolling Load Check Calculator

Check the heaviest wheel that will cross a raised floor against the panel's rolling load rating, at the pass count the route it takes will actually see.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The gross weight of the heaviest single item that will be moved across this floor.

Weigh the item as it will actually travel — a rack loaded for shipping, a UPS with its batteries in, a crate with its pallet. The empty weight on the data sheet is not the weight that crosses the floor.

How many wheels the item rolls on when it is travelling in a straight line.

Count the wheels actually in contact. A pallet truck has two load rollers and a steer wheel; a rack on four castors has four, until it is tipped to get over a threshold.

How few wheels carry the item at the worst moment of a turn or a threshold crossing.

This is where raised floors get damaged. Pivoting a four-castor rack round a corner puts most of its weight on two wheels, and lifting one corner over a ramp lip can put it on one. Two is the usual honest answer; one is the answer if the item gets tipped.

The panel's published rolling load for a small number of passes, from its test certificate.

In the CISCA procedure this is the ten-pass figure — what the panel survives on a one-off delivery route without permanent set beyond the allowed limit. It is always the larger of the two ratings.

The panel's published rolling load for repeated traffic, from the same certificate.

The ten-thousand-pass figure, and the one that governs any aisle a trolley uses regularly. It is markedly lower than the low-pass rating because the failure mode is accumulated damage rather than a single overload.

Whether this route sees a single delivery or repeated trolley traffic.

Choose by the route, not by the item. The same rack crossing the same floor once during fit-out and every week thereafter is two different checks, and the second one is against a much lower rating.

Governing wheel load

550 lb

ComparisonA comparison, not a check — no result here is an approval.

The governing wheel load is under the panel rating shown with it. Being under the rating on this one comparison is not clearance to move the load: the understructure, the panel condition and the route are all outside it.

Wheel load with the load shared evenly
275 lb
Wheel load on a pivot turn
550 lb
Panel rating applied
705 lb
Spare capacity against that rating
155 lb
Utilisation of the panel rating
78.01 %
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • CISCA Recommended Test Procedures for Access Floors — rolling load is rated by passing a defined wheel over the panel a set number of times, at both a low pass count and a high one, and a panel carries a different rating for each
  • BS EN 12825, Raised access floors — the European counterpart, which classifies panels by load capacity and states the rolling load separately from the concentrated and uniformly distributed cases
  • The governing wheel load is the delivered weight divided by the number of wheels genuinely sharing it. On a pivot turn that is fewer wheels than the equipment has, which is the case this check exists for

Inputs used

Delivered Equipment Weight
1100 lb
Number of Wheels or Castors
4
Wheels Sharing the Load on a Pivot Turn
2
Panel Rolling Load Rating, Low Pass Count
990 lb
Panel Rolling Load Rating, High Pass Count
705 lb
Traffic on This Route
Repeated traffic route (high pass count)

Intermediate steps

Wheel load with the load shared evenly
275 lb
Wheel load on a pivot turn
550 lb
Panel rating applied
705 lb
Spare capacity against that rating
155 lb
Utilisation of the panel rating
78.01 %
Final result550 lb

Confidence note: The governing wheel load is under the panel rating shown with it. Being under the rating on this one comparison is not clearance to move the load: the understructure, the panel condition and the route are all outside it.

What this calculation does not cover

  • Checks the panel, not the understructure. A pedestal that has lost its adhesive bond or a stringer left out during a cable pull will fail long before the panel does.
  • Wheel diameter and tyre hardness change the answer and are not inputs here. A small hard castor concentrates its load into a far smaller contact patch than the test wheel the rating was measured with.
  • Cut panels at borders and panels with cutouts carry less than a full panel. Neither is covered by the published rating.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-06 · in the site-wide review of 2026-09-06 · v1.0.1

Regulatory standards & verification citations3
  1. CISCA Recommended Test Procedures for Access Floors — rolling load is rated by passing a defined wheel over the panel a set number of times, at both a low pass count and a high one, and a panel carries a different rating for each
  2. BS EN 12825, Raised access floors — the European counterpart, which classifies panels by load capacity and states the rolling load separately from the concentrated and uniformly distributed cases
  3. The governing wheel load is the delivered weight divided by the number of wheels genuinely sharing it. On a pivot turn that is fewer wheels than the equipment has, which is the case this check exists for

Which documents these citations point at

Standards referenced: BS EN 12825 (European Committee for Standardization, as published in the UK by BSI, European (EN)).

Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

How to calculate raised access floor rolling load check in 7 steps

  1. Delivered Equipment WeightThe gross weight of the heaviest single item that will be moved across this floor.
  2. Number of Wheels or CastorsHow many wheels the item rolls on when it is travelling in a straight line.
  3. Wheels Sharing the Load on a Pivot TurnHow few wheels carry the item at the worst moment of a turn or a threshold crossing.
  4. Panel Rolling Load Rating, Low Pass CountThe panel's published rolling load for a small number of passes, from its test certificate.
  5. Panel Rolling Load Rating, High Pass CountThe panel's published rolling load for repeated traffic, from the same certificate.
  6. Traffic on This RouteWhether this route sees a single delivery or repeated trolley traffic.
  7. Governing wheel loadThe tool computes the governing wheel load from those figures and shows the formula, its sources, and a confidence rating alongside it.

Governing wheel load by delivered equipment weight

Page defaults, not your figures above.

Delivered Equipment WeightGoverning wheel load (lb)
500 lb250
1,000 lb500
1,500 lb750
2,000 lb1,000

Frequently asked questions

Why does the pass count change the rating so much?
Because the two tests measure different failure modes. A small number of passes asks whether the panel survives a single heavy crossing; ten thousand asks whether it survives fatigue and accumulated permanent set. A panel comfortably inside its low-pass rating can still dish under an aisle that sees a trolley twice a day.
Is a pivot turn really the worst case?
Usually, yes. Rolling straight, a four-castor load is shared four ways; swinging it round a corner puts nearly all of it on the two wheels on the inside of the turn, and the load moves slowly across a very small contact patch, which is the condition rolling load ratings exist to describe. Tipping the item over a threshold is worse still.
What do I do if the check fails?
Spread the load rather than argue with it. Track boards or ply sheets across the route move the wheel load into several panels at once and cost almost nothing. Larger-diameter wheels help too. Upgrading panels along a delivery route is the expensive answer and is worth it only where the traffic will keep coming.
Do published ratings apply to panels that have been lifted before?
Not strictly. Ratings are measured on new panels seated on an undamaged, correctly torqued grid. Every lift and relay risks a bent stringer, a loosened pedestal head or a chipped corner, and none of that is in the certificate. On an existing floor, treat the rating as an upper bound.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.