Twenty-eight on the Monday, and the cabins land on the Thursday
Welfare is the one part of a site that has to be finished before the work starts, and it is ordered by somebody reading a programme that has not happened yet. The enabling gang turns up on the Monday, twenty-eight strong, and the welfare schedule was written against a peak of a hundred and eighty in month fourteen. Order for the twenty-eight and you spend the next year adding units in ones. Order for the hundred and eighty and you pay hire on eleven empty cabins through a winter.
Neither is the answer, and the reason people get it wrong is that welfare hire is bought as a count of cabins when almost every constraint on it is a rate: basins per minute at half past twelve, seats per sitting, litres per head per day into a tank somebody empties, kilowatts of latent heat out of a room full of wet coats overnight. Get the rates first and the cabin count writes itself — including the month at which the second block has to already be standing, which is a date and belongs on the programme rather than in a hire manager's inbox.
The headcount you size against is not the one on the resource curve
The resource curve gives average operatives per month, and averages are exactly the wrong shape for welfare. What sizes a toilet block is the number of bodies inside the fence at one instant, which is higher than the curve for three reasons that all land at once.
The first is trade overlap. A curve that says a hundred and twenty in month nine says nothing about the fortnight when the first-fix electricians, the ductwork gang and the ceiling grid are all in the same building, and the subcontractor's own labour returns arrive after the fact. The second is shift changeover: if a night gang hands over to a day gang, for forty minutes there are two workforces washing and changing in one block, and that overlap is the design case for basins and lockers even though it never appears as a headcount anywhere. The third is everyone who is not on the labour return at all — delivery drivers, the testing engineer, the client's monthly walk-round.
So build the number rather than read it, and keep the working out. When the hire company asks why you want six sanitary units rather than four, the answer that gets the order approved is the arithmetic, not the assertion.
- Take the peak month off the resource curve, not the average across the phase.
- Add the subcontractors who report their own labour separately and are missing from your return.
- Add the changeover overlap in full if two shifts are on site at the same moment, even briefly.
- Add a counted visitor and delivery-driver allowance rather than a percentage.
- Re-issue the number to the hire desk whenever the programme is re-baselined, not only when somebody complains.
The law hands you a duty and withholds the number
There is a persistent belief on British sites that a regulation somewhere states how many toilets a hundred people need. It does not. The Construction (Design and Management) Regulations 2015 put the obligation on the principal contractor and set out in Schedule 2 what has to exist — sanitary conveniences, washing facilities, drinking water, changing rooms and lockers, and rest facilities with the means to boil water and heat food — and describes all of it as suitable and sufficient. That is a duty, not a quantity, written that way because a tunnel headworks and a two-storey housing plot are not the same problem.
The table everybody actually uses comes from somewhere else: HSE's L24, the Approved Code of Practice and guidance to the Workplace (Health, Safety and Welfare) Regulations 1992, which scales water closets and washstations against the number of people at work. Construction sites sit outside most of those workplace regulations and are governed by CDM instead, so L24's table is a defensible benchmark rather than a rule you are being measured against. Using it is sensible; citing it as the legal minimum is wrong, and an inspector who hears that will ask what assessment you actually did.
The American position is the opposite way round: the number is written down and the washing duty is narrower than people assume. OSHA 29 CFR 1926.51 covers sanitation for construction, and its Table D-1 sets toilet provision directly against headcount — a single facility for twenty or fewer, then one toilet seat and one urinal per forty workers, and per fifty workers once the site passes two hundred. A footnote allows urinals to stand in for toilets where the facility will not be used by women, but it puts a floor under the toilet count rather than permitting a straight swap. The washing facilities paragraph in the same section, though, is tied to operations where contaminants may be harmful rather than expressed as a ratio per head.
For the appliance scales themselves, and for the floor a cubicle and its door swing genuinely need, BS 6465-1 and BS 6465-2 are the documents to have open when you are arguing with a cabin layout drawing. Whichever regime you are under, the count you can defend is the one where somebody wrote down the headcount, the ratio's source, and why a bigger or smaller number suited this site.
| Document | What it settles | What it leaves to you |
|---|---|---|
| CDM 2015, Schedule 2 | The list of facilities that must exist, and that they must be there for the whole construction phase | Every quantity — it says suitable and sufficient and stops there |
| HSE L24 (guidance to the Workplace Regulations 1992) | A published scale of water closets and washstations against people at work | Whether it transfers to a construction site at all, which is a judgement you make and record |
| OSHA 29 CFR 1926.51, Table D-1 | Toilet and urinal counts stepped against headcount bands | Basin numbers as a ratio, canteen seating, and anything about drying wet clothing |
| BS 6465-1 and BS 6465-2 | Appliance scales of provision, and the space each appliance and its door swing needs | The site-specific case: a compound where the walk from the work face is the binding constraint |
| The hire company's unit specification | Seats, basins, cubicles, water storage and connected load for the actual cabin arriving | Whether the number of those cabins matches your peak, which is the only question that matters |
Basins run out before cubicles do, and they run out at two known minutes
Toilet use spreads itself through a day. Hand washing does not: it happens in the four minutes before the break and the six minutes before the gate, and it happens to everybody at once. That asymmetry is why a block sized correctly on cubicles still produces a queue, and why the queue produces the thing you were trying to avoid, which is people going to lunch without washing.
Treat a basin as a throughput. A proper wash is twenty to thirty seconds at the tap, and with approach, drying and turnaround a basin serves roughly one person a minute in practice. A hundred and twenty people converging on a five-minute window need something close to twenty-four basin-minutes per minute of window — which is to say the number of basins that clears that crowd is two dozen, not the four you get in one sanitary unit. You will not hire two dozen, and you do not have to: the fix is usually to break the peak rather than to buy throughput, by staggering break times between blocks or by putting a satellite wash point at the far work face so that half the crowd never walks to the main compound. What you cannot do is decide the queue is a discipline problem.
Ninety kilograms of water, and nowhere for it to go
A drying room is the most under-specified thing in a welfare compound, because it looks like an empty cabin with a heater in it and is in fact a piece of process plant. A soaked jacket, trousers and a pair of boots carry on the order of a kilogram and a half of water. Sixty people coming in off a wet November afternoon bring in something near ninety kilograms of it, and by seven the next morning all of it has to be somewhere other than in the clothing.
Evaporating water costs about 0.63 kWh per kilogram — the latent heat of vaporisation, in units a hire schedule can use. Ninety kilograms is around fifty-seven kilowatt-hours, and across a fourteen-hour night that is a continuous four kilowatts doing nothing but turning water into vapour. Then the vapour has to leave, because a hot sealed cabin reaches equilibrium at high humidity and the clothes stop drying while the walls start streaming. Carrying ninety kilograms away on ventilation air means shifting on the order of a thousand cubic metres an hour through a cabin of thirty — dozens of air changes an hour, not the two or three a trickle vent gives you — and heating that incoming air from a winter night to room temperature is another five kilowatts. The psychrometrics behind those figures are in the ASHRAE Handbook — Fundamentals. The point of doing them is that a drying room for sixty people is a ten-kilowatt appliance running all night, and it is routinely hired as a cabin with a three-kilowatt fan heater in the corner.
That number is also the argument for the other approach. A heat-and-vent room throws its latent heat out of the vent; a recirculating room with a refrigerant dehumidifier condenses the water instead and gives the heat back to the air, which is why the better hire units are built that way. It changes what you specify: ninety litres a day is around a hundred and ninety US pints a day of dehumidification, which is several domestic-sized machines or one commercial unit, and a machine rated at a warm-basement duty will not hold that rate in a cold cabin. Hanging space is its own constraint on top of that — clothing packed shoulder to shoulder on one rail dries at the rate of the outside of the bundle, not at the rate the arithmetic promised.
Schedule 2's changing-room paragraph carries the drying requirement where clothing becomes wet, and OSHA's change-room provisions are triggered by protective clothing worn against contaminants rather than by rain. Neither gives a kilowatt. The mass balance does, and it is the only thing that tells you in September whether the unit you booked can cope in January.
Seats are a sittings problem, and the microwave is the real queue
Canteen seating is the one figure people size by eye, and eye-sizing gives a room that is fine at half past eleven and unusable at half past twelve. The controlling arithmetic is sittings: seats times the number of times the room turns over inside the break is the number of people who get to sit down. A hundred and twenty operatives on a thirty-minute break with a room seating forty is three sittings, which needs a ninety-minute window. Without it, forty people eat and eighty stand in the drying room — which is where they will go, and which undoes the drying you paid ten kilowatts for.
The queue is rarely at the seats, though. It is at the microwave, and that one is arithmetic anybody can do on the back of a delivery ticket. Two and a half minutes of heating plus the shuffle in and out is about three minutes per person per machine, so one microwave serves ten people in a thirty-minute break. If seventy per cent of a hundred and twenty-strong workforce heats food, that is eighty-four heatings and something like eight microwaves. Nobody hires eight microwaves. They hire two, and the last man in the queue eats at ten past one, which is either lost production or a cold lunch, and both of them turn up later as a canteen that people have stopped using.
The same counting applies to the boiling water Schedule 2 asks for: a twenty-litre wall boiler holds perhaps sixty mugs and then has to reheat, so its recovery rate rather than its capacity decides whether the second half of the break gets tea. Every one of these appliances is also a nameplate on a receptacle circuit, and they all go on at the same moment, which is where the next section starts.
The block's electrical load is a spike at half past twelve
An office cabin draws a broadly steady load through a working day. A welfare block does not: it has two spikes, and the bigger one is lunchtime, when the microwaves, the boiler and the canteen heating are all on while the water heater recovers from the wash-up rush and the drying room is still running. Sizing the supply off an average, or off a per-cabin figure the hire desk quotes, produces a head that trips at exactly the moment two hundred people notice.
Add it up as three groups. Lighting across the canteen, drying room and sanitary units is small — call it 900 VA. Heating and drying is the largest single line: nine kilovolt-amps for the drying room and four for the canteen and toilet block gives 13,000 VA. The receptacle group is the one that surprises people, because it is where the eight microwaves live: eight at roughly 1,400 VA of input each is 11,200 VA before the water boiler and the water heater, and 17,200 VA is a fair total. That is 31,100 VA connected, and at 240 V it is a shade under 130 amps.
One hundred and thirty amps is not the supply, though — it is the input to two corrections. The continuous-load rule in NFPA 70, the National Electrical Code, requires overcurrent devices to be rated at not less than 125 per cent of a continuous load, and heaters and water heaters are exactly that, so 130 A becomes about 162 A and the honest order is a 200 A service, not the 100 A one that was assumed. Temporary construction power itself is governed by Article 590 of the Code, Temporary Installations, and in Britain by Section 704 of BS 7671, Construction and demolition site installations — those documents, not this arithmetic, decide conductor size, protective devices and disconnection.
Two things the division cannot see. A British site is on a 400 V three-phase supply, where the same 31.1 kVA is about 45 A a phase; the voltage field below stops at 240 V because it models the North American split-phase case, so on three phase take the volt-amp total and do the division yourself. And a total says nothing about balance — a block whose drying room, boiler and water heater all landed on one leg draws far more on that leg than the sum implies, which is the fault that presents as a trip nobody can reproduce.
Enter the welfare block's lunchtime case rather than a day average: nameplate lighting, everything thermal in the heating group, and every microwave, boiler and water heater in the receptacle group.
Required service amperage
29.2 A
- Total connected load
- 7,000 VA
This is a simple connected-load sum with no demand factor applied — NEC Article 590 (Temporary Installations) governs the actual code requirements for temporary construction power, including conductor sizing, GFCI protection, and disconnect requirements, which this calculator does not address. Round up to the next standard breaker/service size and consult a licensed electrician for the actual installation.
The set that carries all of it until the supply lands
Metered temporary supplies are applied for in weeks and delivered in months, and welfare is a day-one duty, so the first phase runs on hire generation. Size it off the same connected-load exercise rather than off the number of cabins, then deal with the part a connected load misses: the starting surge of the largest motor on the block, which on a welfare cabin is usually an air-conditioning compressor or the macerator pump on the effluent line, and which asks for several times its running current for a second or two.
Work the first-phase case rather than the peak one. Twenty-five people in a single welfare unit is roughly 400 W of lighting, a three-kilowatt water heater, six kilowatts of heating, two microwaves at 2,800 W and a three-kilowatt boiler — a little over fifteen kilowatts running. Give the largest motor 2,400 W of surge beyond its own running watts, take twenty per cent of headroom, and you land near twenty-one kilowatts: a thirty kVA set, not the twenty kVA one that sounded about right. Sets are sold in kVA and this arithmetic is in watts — at a typical 0.8 power factor a 30 kVA set is 24 kW, and forgetting that conversion is how a set arrives already too small.
Two cautions. The running-watts field below stops at 20 kW, which is a fair statement of where a rule of thumb stops being the right tool — a full block for a hundred and twenty is a hire company's load study and a set specified against ISO 8528-1, which defines the rating classes and is the reason a prime-rated set and a standby-rated one are not interchangeable on a compound running continuously. The second is the opposite problem: the same set at three in the morning carries frost protection and a security light, perhaps seven per cent of its rating, and a diesel run lightly loaded for long periods wet-stacks and fouls. That argues for a smaller out-of-hours set or a battery hybrid, and it is cheaper to decide before the hire starts than to read in a service report.
Run the first-phase welfare block through it — running watts for everything that is on at lunchtime, plus the extra surge of the single largest motor — then convert the answer to kVA before you ring the hire desk.
Recommended generator size
6,600 W (recommended generator rating)
- Total running watts
- 3,500 W
- Peak (with largest surge)
- 5,500 W
This is a rule-of-thumb estimate. For whole-home standby systems, an electrician performs a full load calculation accounting for which circuits can run simultaneously.
Where the effluent goes when there is no sewer
Plenty of compounds sit on a plot with no sewer connection for the first six months, and the welfare block's drainage becomes a tank and a tanker rotation. The number that matters is not the tank volume: it is the interval between pump-outs, and it falls out of the volume divided by the daily flow.
Get the flow from something real. A hire company will have pump-out records for its own units, and the US EPA's Onsite Wastewater Treatment Systems Manual, EPA/625/R-00/008, carries tables of typical wastewater flows by establishment type. This site will not publish a per-head figure as though it were a standard, because welfare flow swings enormously on whether there are showers and whether the canteen washes up on site. Work it with your own number: if your records say thirty litres a head a day for WCs, basins and a canteen sink with no showers, a hundred and twenty people is 3,600 litres a day.
Now read the tank calculator below honestly. It is a domestic tool: it maps a bedroom count onto the minimum tank volumes state and local health codes commonly require, and its smallest band is a thousand US gallons — about 3,785 litres, which is one single day of the flow just worked out. That comparison is the most useful thing it can tell you here. A weekly tanker on that duty would need something near twenty-five thousand litres, and the real answer on most compounds is a large holding tank on a twice-weekly rotation. Use it as a floor and a sanity check, and expect it to under-read, because a canteen and a wash-up sink are load a bedroom count never accounted for.
The rest is permission and access rather than arithmetic. A septic tank discharging to ground is a permitted or rule-bound activity — in England under the Environment Agency's general binding rules for small sewage discharges, elsewhere under the local health authority — and a temporary compound rarely has the percolation area or the consent, which is why sealed holding tanks are the norm. Where a tank and field genuinely are the answer, BS 6297 governs drainage field design in Britain and BS EN 12566-1 covers prefabricated septic tanks for populations up to fifty.
- Fix the daily flow from pump-out records or a published flow table, and write down which one you used.
- Divide the tank volume by that flow, then test the interval against the peak month rather than the month you order in.
- Confirm the discharge is permitted before assuming a tank and field rather than a sealed holding tank.
- Prove the tanker route and standing position on the compound layout, before the cabins are craned into it.
A bedroom-count proxy, so use it as a floor: it returns the minimum volume a domestic system is allowed, which is the yardstick that shows how quickly a welfare block would fill one.
Use the Septic Tank Sizing calculatorThe bin point pays rent on a rectangle you cannot see
A canteen makes waste every day, and the container it goes in cannot stand against the side of a cabin. A skip fire overnight next to a stack of occupied units is one of the arrangements that fire precautions on construction sites exist to prevent — NFPA 241, Standard for Safeguarding Construction, Alteration, and Demolition Operations, and Chapter 33 of the International Fire Code both address fire safety during construction, and the separation distance itself is set by your local fire code, the site fire plan or the insurer rather than by a national figure anybody can quote at you.
What the arithmetic does show is how expensive that clearance is in compound area, which is the thing layouts get wrong. A six-cubic-yard skip occupies roughly 3.6 m by 1.8 m, which is 6.5 square metres of steel. Ring it with a three-metre clearance on every side and the rectangle it consumes is 9.6 m by 7.8 m, close to 75 square metres — eleven times the skip. Do that for the canteen skip and a second one for recycling and you have committed a fifth of a small welfare compound to two containers, which is a decision worth making on the layout drawing rather than discovering when the units arrive and there is nowhere left to put them.
Put the container footprint in and the clearance your fire plan requires around it, and the answer is the area the bin point actually takes out of the welfare compound.
Required staging area footprint
2,090 sq ft194 m²
The required setback distance is jurisdiction- and material-specific (fire code requirements for combustible debris storage, property line setbacks, or your site's own safety plan) — this calculator applies whatever setback value you supply, it does not determine the code-required distance for your location.
Fencing the welfare island off from what moves
The welfare compound normally sits inside the site perimeter, and the fence that matters is the inner one: the line keeping people who are walking to the canteen out of the path of everything with wheels. HSE guidance HSG144, The safe use of vehicles on construction sites, is built around separating pedestrians from plant, and the welfare walk is the most predictable pedestrian flow on any site — the same two hundred people, twice a day, at times printed on a noticeboard. It is the easiest movement to design for and the one most often left to chance.
Counting the panels is straightforward once the line is walked rather than scaled. A welfare island of 30 m by 20 m has a hundred metres of perimeter; take out a six-metre vehicle opening for the tanker and the cabin deliveries and a 1.2 m pedestrian gate, and 92.8 m of line remains for panels. At the 3.5 m width most hire fleets carry that rounds up to twenty-seven, and the rounding is real, because a partial panel is still a whole panel off the wagon. Confirm the width with your own supplier, since it varies by manufacturer, and count gate units separately rather than hoping the panel count absorbs them.
Two things belong in the line rather than bolted on afterwards. The pedestrian gate should open onto the walking route and not onto the haul road, and if the walk is long or a lifting zone is live overhead it wants covering. And the line has to leave the tanker its standing position and hose reach, because a welfare island fenced tight to its cabins and then reopened every week for a wagon is a fence that will be propped open by the second month.
Feed it the walked length of the inner line at your supplier's actual panel width, and count gates as separate units — the rounding up is the honest part of the answer.
Fence panels needed
33 panels
Week six, when the second gang lands and nothing has been re-counted
Welfare provision degrades without anybody deciding it should. The headcount steps up when a subcontractor mobilises early, a cubicle goes out of service and is not reported because there is another one, the drying room fills with stored gear until air cannot move through it, and the tanker interval that suited a hundred people is quietly serving a hundred and fifty. None of it shows up in a hire schedule, because the hire schedule has not changed — which is the point.
So book the re-count against the programme rather than against a complaint. Compare this week's labour with the number the block was hired against, and stand in the canteen at half past twelve rather than at four. Check what the tanker pumped last visit against what the tank holds, because a load that comes back consistently full means the interval has moved. Test the drying room by touching the clothes at seven in the morning, which is the only test of it that means anything. Where a number has moved, the fix is another unit and a date on the programme — considerably cheaper than the version where an inspector finds it first.
Have these settled before the hire schedule is issued
Six figures that turn a programme into a welfare order, each of which is far cheaper to establish now than to correct with a second mobilisation once the compound is occupied.
- Built peak headcount, with the month it occurs — Peak month from the resource curve, plus separately-reported subcontract labour, plus the shift overlap in full, plus a counted visitor allowance. The date matters as much as the number.
- Sanitary and washing counts, and the scale they came from — The count against your headcount, plus a written note of whether it came from L24, from OSHA Table D-1 or from BS 6465-1, and why that scale suits this site.
- Canteen seats against the number of sittings the break allows — Seats times sittings must clear the peak. Then count microwaves and boiler recovery separately, because the queue is there rather than at the tables.
- Drying load in kilograms of water per night — People times the water a wet set of clothing carries, converted at 0.63 kWh per kilogram of latent heat, then the ventilation or dehumidification rate that removes it.
- Lunchtime connected load, grouped as lighting, thermal and receptacle — Nameplates for every heater, water heater, boiler and microwave that is live at the same moment, before the continuous-load multiplier is applied to the total.
- Daily effluent flow and the pump-out interval it produces — Flow from pump-out records or a published flow table, divided into the tank volume, then tested against the peak month and against when a tanker can actually attend.
Opens the calculators above on one screen with the dimensions from this article already filled in. Quantities only — this site publishes no price list, because local prices vary too much to publish honestly.