Measurements & Conversions

Cubic Yard Calculator

Work out the cubic yards in a rectangular area from its length, width and depth — the unit bulk material is ordered in.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
Who is doing the work?

The standard allowance most suppliers and estimating guides assume for ordinary work.

The longest dimension of the area.

Measure the excavation or the finished area, whichever you are filling. For an irregular shape, break it into rectangles and add the results — that is more accurate than averaging a length and a width across a shape that is not rectangular.

The shorter dimension of the area.

Which of the two horizontal dimensions you call the width makes no difference here — the product is the same either way. The DEPTH is the field that matters, and it is the one most often entered in the wrong unit, because depths are quoted in small units while plan dimensions are quoted in large ones. Measure the plan size at the level you are filling to as well: a battered excavation is wider at the top than at the bottom.

How deep the material goes.

Depth is where most errors happen, because it is usually the smallest number and the one people convert wrong. Four inches is 0.333 ft, not 0.4 — using 0.4 over-orders by a fifth.

Allowance for spillage, compaction and uneven subgrade.

Ten percent is the usual allowance for bulk fill on a prepared base. Go higher on an uneven excavation, where the low spots take more than the average depth suggests.

Volume to order (cubic yards)

3.443 yd³

High confidence

Geometry only. The conversion is exact; the accuracy is entirely in your measurements.

Geometric volume
3.13 yd³
Cubic metres
2.63 m³
Cubic feet
92.95 ft³
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • 1 cubic yard = 0.764554857984 m³ exactly, from the international yard of 0.9144 m (1959)
  • Ready-mix concrete, aggregate and topsoil are sold by the cubic yard across North America

Inputs used

Length
19.5 ft
Width
13 ft
Depth
4 in
Waste / over-order (%)
10

Intermediate steps

Geometric volume
3.13 yd³
Cubic metres
2.63 m³
Cubic feet
92.95 ft³
Safety / waste buffer appliedWaste allowance (+10%)
Final result3.44 yd³

Confidence note: Geometry only. The conversion is exact; the accuracy is entirely in your measurements.

What this calculation does not cover

  • The waste box applies a single flat percentage to the whole volume, and that one number is doing the work of spillage, compaction and an uneven subgrade together — there is no separate swell factor, so material that loses depth once it is rolled needs the percentage raised rather than a second allowance.
  • Depth enters the sum once and is then spread evenly over the entire footprint, so a base that falls away to one corner, a dished excavation, or a trench with battered sides will swallow more than length times width times depth predicts.
  • Clearing the waste field is read as zero rather than as the ten percent it opens on: the answer reverts to the bare geometric volume and the waste-allowance note beneath it disappears with it.
  • Weight never enters the calculation — the answer and its breakdown are volume only, in cubic yards, cubic metres and cubic feet, with no density behind them, so a load that fits inside a truck or skip by volume can still sit over its weight limit.
  • Length and width are capped at 300 m (roughly 980 ft) and depth at 10 m, so a longer strip or a deep bulk excavation has to be split into sections and the cubic yards added up.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

19.5 ft5.94 m13 ft3.96 m4 in101.6 mm10 ft2 m

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-05 · in the site-wide review of 2026-09-06 · v1.0.1

Regulatory standards & verification citations2
  1. 1 cubic yard = 0.764554857984 m³ exactly, from the international yard of 0.9144 m (1959)
  2. Ready-mix concrete, aggregate and topsoil are sold by the cubic yard across North America
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

  • Three suppliers quoting per load, per tonne and per cubic yard, reduced to one rate you can actually compare — and how much to order once the allowance is honest.

How to calculate cubic yard in 5 steps

  1. LengthThe longest dimension of the area.
  2. WidthThe shorter dimension of the area.
  3. DepthHow deep the material goes.
  4. Waste / over-order (%)Allowance for spillage, compaction and uneven subgrade.
  5. Volume to order (cubic yards)The tool computes the volume to order (cubic yards) from those figures and shows the formula, its sources, and a confidence rating alongside it.

Volume to order (cubic yards) by length

Page defaults, not your figures above.

LengthVolume to order (cubic yards) (yd³)
10 ft1.75
15 ft2.63
20 ft3.51
25 ft4.39
30 ft5.26
35 ft6.14

Frequently asked questions

How many cubic feet in a cubic yard?
Twenty-seven. A yard is three feet, and three cubed is twenty-seven. That is the conversion people get wrong most often — dividing by three instead of by twenty-seven under-orders by a factor of nine.
How do I enter a depth in inches?
Switch the unit toggle to imperial and enter inches directly. If you are converting by hand, divide by twelve: 4 in is 0.333 ft, 6 in is 0.5 ft. Rounding 4 in to 0.4 ft over-orders by 20%, which on a large pour is a wasted delivery.
Should I order the exact figure?
No. Bulk material is delivered in whole units and subgrade is never perfectly level, so the low spots absorb more than the average depth predicts. The waste allowance here covers that; on a rough excavation raise it rather than ordering twice.
Does this work for a circular or irregular area?
Not directly — this is length by width. For a circle, work out the area separately (π × radius²) and treat that as one side against a depth. For an irregular shape, split it into rectangles and add the results.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.