Precast Kerb Calculator — Kerb Units, Bed and Haunch Concrete

Count precast concrete kerb units for a run, at the unit length your merchant sells, and the concrete for the bed and haunch you specify.

Kerb units to order: 24 kerbs for Length of the Kerb Run 66 ft, Length of One Kerb Unit 36 in and Joint Between Units 0.2 in, the page's opening figures; on the metric page, 20 m, 915 mm and 5 mm give 24 kerbs. Source: Marshalls, half battered kerb HB2 (NBS Source).

  • Answers as you type
  • 4 sources cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
Who is doing the work?

Waste is set to 5% by hand. Pick a tier above to replace it, or keep your own figure.

The straight length of kerb to lay, along its face.

Measure along the line of the kerb face. Leave out bends that need radius kerbs and the length of any dropped crossing, which take their own units.

Tools needed: Tape measure

The unit's length as sold, from your merchant's listing.

Standard UK precast kerbs are 915 mm long; half-length units (457 mm) and block kerbs (often 200 mm) are sold too. Read the length from your merchant's listing.

The mortar joint your specification gives between units.

Kerbs are laid with mortar joints, never butted tight. Take the width from your specification; 5 mm is an example to replace.

Extra units for cuts at the ends and breakages.

A cut unit at each end of a run and the odd broken one in delivery. Raise it for many short runs.

The width of the concrete bed under the kerb, from your specification.

Your designer's or highway authority's detail gives it. 300 mm is an example to replace, never a recommendation.

The depth of the concrete bed, from your specification.

150 mm is an example to replace with your detail's figure.

How far up the back of the kerb the haunch rises, from your specification.

The haunch is the concrete wedge behind the kerb that holds it in line. 100 mm is an example to replace.

How far the haunch spreads behind the kerb along the bed, from your specification.

Taken as a triangle from this width at the bed to nothing at the haunch's top. 100 mm is an example to replace.

Extra concrete for an uneven dig and spillage.

A trench is never dug exactly to the line; 10% covers ordinary over-dig. Raise it on rough ground.

Kerb units to order

24 kerbs

High confidence
Kerb units laid, before the allowance
22 kerbs
Kerb face laid, units and joints
66.37 ft · 66 ft 4 3/8 in
Concrete in the bed
1.2 yd³
Concrete in the haunch
0.14 yd³
Concrete per metre of kerb
0.02 yd³/ft
Concrete to order, with the allowance
1.47 yd³
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • Marshalls, half battered kerb HB2 (NBS Source): a straight precast unit 915 mm long, 125 mm wide and 255 mm high, hydraulically pressed, made to BS EN 1340
  • MKM Building Supplies, concrete half battered kerb straight HB2, 915 mm × 125 × 255 mm (a UK merchant's listing, read 2026-10-31)
  • Marshalls, Demarcation Kerb Installation Guidelines: wide joints fully filled with 1:4 cement:sand mortar; units are never butt-jointed; movement joints run through the concrete race and haunching
  • Suffolk County Council, standard detail DM 1100 02, kerbs laid on full construction: the kerb on a concrete bed with a concrete haunch, all concrete mix ST1 (an example of a highway authority's own detail)

Inputs used

Length of the Kerb Run
66 ft
Length of One Kerb Unit
36 in
Joint Between Units
0.2 in
Waste Allowance (%)
5
Concrete Bed Width
11.75 in
Concrete Bed Depth
6 in
Haunch Height Behind the Kerb
4 in
Haunch Width at the Bed
4 in
Concrete Allowance (%)
10

Intermediate steps

Kerb units laid, before the allowance
22 kerbs
Kerb face laid, units and joints
66.37 ft
Concrete in the bed
1.2 yd³
Concrete in the haunch
0.14 yd³
Concrete per metre of kerb
0.02 yd³/ft
Concrete to order, with the allowance
1.47 yd³
Safety / waste buffer appliedwaste allowance (+5%)
Final result24 kerbs

What this calculation does not cover

  • Straight units only: a bend tighter than the units can follow needs radius kerbs, and a dropped crossing needs droppers and transition units, which are counted separately from the maker's list. Enter only the straight run here.
  • The bed and haunch are your specification's figures, never sized here. Highway authorities publish their own kerb details, and a kerb that restrains a driveway or a road takes the detail the designer gives it.
  • The haunch is taken as a triangle behind the kerb; a square-shouldered haunch holds twice that concrete. Nothing is added for a haunch on the road side or for over-digging, which the concrete waste allowance has to cover.
  • Joints are counted at the width you enter between every pair of units; movement joints, where the specification calls for them, take compressible filler rather than mortar and are not counted.

Estimated cost — your price

This site holds no price list for this material — local prices vary too much to publish honestly. Enter your supplier's price and the result is costed with it.

66 ft0.2 in6 in
Schematic, drawn to the proportions you entered — not to scale on screen.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-10-31 · 2 test vectors · v1.0.0

Regulatory standards & verification citations4
  1. Marshalls, half battered kerb HB2 (NBS Source): a straight precast unit 915 mm long, 125 mm wide and 255 mm high, hydraulically pressed, made to BS EN 1340
  2. MKM Building Supplies, concrete half battered kerb straight HB2, 915 mm × 125 × 255 mm (a UK merchant's listing, read 2026-10-31)
  3. Marshalls, Demarcation Kerb Installation Guidelines: wide joints fully filled with 1:4 cement:sand mortar; units are never butt-jointed; movement joints run through the concrete race and haunching
  4. Suffolk County Council, standard detail DM 1100 02, kerbs laid on full construction: the kerb on a concrete bed with a concrete haunch, all concrete mix ST1 (an example of a highway authority's own detail)

Which documents these citations point at

Standards referenced: BS EN 1340 (European Committee for Standardization, as published in the UK by BSI, European (EN)).

Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for.

How to calculate precast kerb — kerb units, bed and haunch concrete in 10 steps

  1. Length of the Kerb RunThe straight length of kerb to lay, along its face.
  2. Length of One Kerb UnitThe unit's length as sold, from your merchant's listing.
  3. Joint Between UnitsThe mortar joint your specification gives between units.
  4. Waste Allowance (%)Extra units for cuts at the ends and breakages.
  5. Concrete Bed WidthThe width of the concrete bed under the kerb, from your specification.
  6. Concrete Bed DepthThe depth of the concrete bed, from your specification.
  7. Haunch Height Behind the KerbHow far up the back of the kerb the haunch rises, from your specification.
  8. Haunch Width at the BedHow far the haunch spreads behind the kerb along the bed, from your specification.
  9. Concrete Allowance (%)Extra concrete for an uneven dig and spillage.
  10. Kerb units to orderThe tool computes the kerb units to order from those figures and shows the formula, its sources, and a confidence rating alongside it.

Kerb units to order by length of the kerb run

Page defaults, not your figures above.

Length of the Kerb RunKerb units to order (kerbs)
40 ft15
60 ft21
80 ft29
100 ft36
120 ft42

Frequently asked questions

How many kerbs in a metre?
With 915 mm units and 5 mm joints, one metre takes 1000 / 920 = 1.09 units, so about 11 units for every 10 metres before the allowance for end cuts and breakages.
How deep should the concrete bed be?
That is your specification's or the highway authority's figure, not this page's: it depends on what the kerb restrains and the ground. The page opens on an example and counts the concrete for the figures you enter.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.