Sustainability & Compliance

Embodied Carbon in Concrete Calculator

Cradle-to-gate (A1-A3) carbon for a concrete element, and what replacing cement with GGBS or fly ash actually saves.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
Placed volume of the element.

Design volume, not delivered. Over-ordering and waste carry their own carbon, but they belong in a separate line rather than inflating the element's declared figure.

Replacement level is the biggest lever available.

Ground granulated blast-furnace slag and fly ash substitute for clinker, which is where nearly all of concrete's carbon sits. High replacement levels slow early strength gain, which matters for striking times and for winter pours — it is a programme decision as much as a carbon one.

Used only when the mix above is set to Custom.

Take the A1-A3 GWP figure from your supplier's EPD for the specific mix and plant. This field wants the figure PER CUBIC METRE even when the volume above is showing yd³. A US EPD or mix submittal normally declares it per yd³, and 1 m³ is 1.30795 yd³, so the per-yd³ number is 23.5% smaller for the same concrete — the 215 kgCO₂e/m³ in this field's example is 164.4 kgCO₂e/yd³. Multiply a per-yd³ figure by 1.30795 before entering it. If your source quotes lbCO₂e/yd³ then the top of the unit converts as well as the bottom and the multiplier is 0.59328, not 1.30795: 362 lbCO₂e/yd³ is that same 215 kgCO₂e/m³. Neither mistake is refused — 164.4 and 362 both sit inside this field's 0-2000 range, so the wrong figure is accepted in silence and graded as though it were right. On this page's own defaults (50 m³, with the two reinforcement fields left as they are) entering 164.4 in place of 215 puts the total about 17% low and reports a saving against 100% Portland cement of 6,781 kgCO₂e where the truth is 4,250 — a claimed reduction about 60% larger than the real one.

Steel content by volume of concrete.

Around 80-120 kg/m³ for a typical suspended slab, 150-250 for a heavily loaded transfer structure, 40-60 for a ground slab. Reinforcement is frequently a fifth or more of a reinforced element's total carbon and is left out of concrete-only figures.

Depends heavily on how the steel was made.

Recycled electric-arc-furnace rebar sits far below primary blast-furnace steel — the difference is several-fold, and it is the single largest choice in the reinforcement line. Use the mill's EPD where you have it.

Embodied carbon (A1-A3)

19,000 kgCO₂e

Low confidence

Emission factors here are typical published ranges for orientation, not product data. A reportable assessment uses the supplier's own Environmental Product Declaration — the spread between two suppliers of the same nominal product routinely exceeds 30%.

Tonnes CO₂e
18.83 tCO₂e
Concrete
15,023.5 kgCO₂e
Reinforcement
3,805.95 kgCO₂e
Reinforcement share
20.21 %
Per unit volume of element
287.47 kgCO₂e/yd³
Saving against 100% Portland
0 kgCO₂e
Reinforcement mass
11,040.38 lb
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • EN 15804 modules A1-A3 define cradle-to-gate: raw material supply, transport to the plant, and manufacturing
  • Typical GWP ranges for structural concrete are drawn from published EPDs and the ICE database; product-specific EPDs vary widely around them
  • Cement clinker is the dominant contributor — roughly 90% of a plain concrete's A1-A3 figure comes from the Portland cement fraction

Inputs used

Concrete volume
65.5 yd³
Mix and cement replacement
C30/37, 100% Portland cement (~300 kgCO₂e/m³)
Custom factor (kgCO₂e/m³)
0
Reinforcement
168.56 lb/yd³
Reinforcement factor (kgCO₂e/kg)
0.76

Intermediate steps

Tonnes CO₂e
18.83 tCO₂e
Concrete
15,023.5 kgCO₂e
Reinforcement
3,805.95 kgCO₂e
Reinforcement share
20.21 %
Per unit volume of element
287.47 kgCO₂e/yd³
Saving against 100% Portland
0 kgCO₂e
Reinforcement mass
11,040.38 lb
Final result18,829.46 kgCO₂e

Confidence note: Emission factors here are typical published ranges for orientation, not product data. A reportable assessment uses the supplier's own Environmental Product Declaration — the spread between two suppliers of the same nominal product routinely exceeds 30%.

What this calculation does not cover

  • Cradle-to-gate only (A1-A3). Transport to site (A4), site operations (A5), the in-use stage and end of life are excluded, and A4 alone can be significant for a remote site.
  • Excludes formwork, which is reused a variable number of times and is genuinely difficult to allocate.
  • Does not credit carbonation over the structure's life, which reabsorbs a modest fraction of the process emissions and is treated inconsistently between assessment methods.

Add the equipment this sizes

This result is a specification — 19,000 kgCO₂e — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-05 · in the site-wide review of 2026-09-06 · v1.1.1

Regulatory standards & verification citations3
  1. EN 15804 modules A1-A3 define cradle-to-gate: raw material supply, transport to the plant, and manufacturing
  2. Typical GWP ranges for structural concrete are drawn from published EPDs and the ICE database; product-specific EPDs vary widely around them
  3. Cement clinker is the dominant contributor — roughly 90% of a plain concrete's A1-A3 figure comes from the Portland cement fraction
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

Still deciding? Operational vs Embodied Carbon — the factors that actually differ, with no invented prices.

How to calculate embodied carbon in concrete in 6 steps

  1. Concrete volumePlaced volume of the element.
  2. Mix and cement replacementReplacement level is the biggest lever available.
  3. Custom factor (kgCO₂e/m³)Used only when the mix above is set to Custom.
  4. ReinforcementSteel content by volume of concrete.
  5. Reinforcement factor (kgCO₂e/kg)Depends heavily on how the steel was made.
  6. Embodied carbon (A1-A3)The tool computes the embodied carbon (A1-A3) from those figures and shows the formula, its sources, and a confidence rating alongside it.

Embodied carbon (A1-A3) by concrete volume

Page defaults, not your figures above.

Concrete volumeEmbodied carbon (A1-A3) (kgCO₂e)
40 yd³11,499
60 yd³17,248
80 yd³22,998
100 yd³28,747
120 yd³34,497

Frequently asked questions

Why is cement replacement such a large lever?
Because almost all of concrete's carbon is in the clinker, not the aggregate or the water. Making Portland cement calcines limestone, and that chemical reaction releases carbon dioxide regardless of how the kiln is fired — it is not a fuel problem that cleaner energy solves. Substituting GGBS or fly ash for part of the cement removes that fraction of the clinker and its emissions with it.
What is the catch with high GGBS levels?
Early strength. A 70% GGBS mix gains strength considerably more slowly than plain Portland, especially in cold weather, which pushes out striking times and can extend the programme. On a fast-cycle frame that delay has its own cost, and sometimes its own carbon. It is a genuine engineering trade, not a free saving.
Should I trust the numbers in the dropdown?
Only for orientation. They are typical published ranges, and the spread between two suppliers of nominally identical concrete regularly exceeds 30% — larger than several of the savings people chase. For anything that will be reported, use the supplier's EPD for the specific mix from the specific plant, and enter it as the custom factor.
Why does reinforcement get its own line?
Because it is routinely a fifth or more of a reinforced element's total, and concrete-only figures quietly omit it. It also carries its own large choice: recycled electric-arc-furnace rebar sits several times below primary blast-furnace steel. The breakdown shows the reinforcement share so you can see whether your attention belongs on the mix or on the steel.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.