Heavy Civil & Infrastructure

Soil Nail Pull-Out Safety Factor Calculator

Check a soil nail's pull-out safety factor against the standard FHWA minimum of 2.0.

  • Answers as you type
  • Every formula cited
  • Calculated in your browser
SettingsSettings for this calculationUS
Market
Imperial · sales tax
The grout-to-soil bond strength, from FHWA GEC-7 tables or site-specific pullout testing.

Varies substantially by soil type and installation method (e.g. rotary drilled vs. driven casing).

The diameter of the drilled hole for the nail and grout.

Typically 3-8 in (75-200mm) for soil nails.

The length of the nail bonded (grouted) beyond the potential failure surface.

Only the length beyond the failure plane contributes to pullout resistance.

The nail's design tensile load.

From the overall wall stability analysis.

Pull-out safety factor

3.56 (target ≥2.0)

ComparisonA comparison, not a check — no result here is an approval.

The design load on this nail is below the most the grout-to-ground bond would carry at a pullout safety factor of 2.0 shown with it — FHWA's minimum for soil nailing gives it. Site-specific pullout testing can establish a bond strength the assumed value does not. Being under the allowable pressure is not the whole ground question: settlement, groundwater and the footings alongside are all untouched here.

Pullout capacity
63.97 kips
Then change the inputs to see how far the answer moves.

Show calculation logic

How this was calculated

Formula source(s)

  • FHWA GEC No. 7 soil nail wall design: pullout capacity = nominal bond strength x pi x drill hole diameter x bonded length; a minimum pullout safety factor of 2.0 is standard practice

Inputs used

Nominal Bond Strength (qs)
2088.54 psf
Drill Hole Diameter
6 in
Bonded Length
19.5 ft
Design (Working) Load
17.98 kip

Intermediate steps

Pullout capacity
63.97 kips
Final result3.56 (target ≥2.0)

Confidence note: The design load on this nail is below the most the grout-to-ground bond would carry at a pullout safety factor of 2.0 shown with it — FHWA's minimum for soil nailing gives it. Site-specific pullout testing can establish a bond strength the assumed value does not. Being under the allowable pressure is not the whole ground question: settlement, groundwater and the footings alongside are all untouched here.

What this calculation does not cover

  • This checks the grout-to-ground bond and nothing else. The nail bar's own tensile capacity, the grout-to-steel bond, and the head plate and facing connection are separate checks — a nail can pass this one and still fail by yielding the bar or punching through the shotcrete face.
  • It is a check on one nail, not a wall design. Global and sliding stability, bearing at the toe, facing reinforcement and the analysis that produced the design load per nail all sit outside it, and the design load you type in is taken as given rather than tested.
  • Only the bonded length beyond the potential failure surface earns capacity, and the calculation cannot locate that surface for you. Enter the whole nail length instead of the portion past the failure plane and the answer is overstated in direct proportion.
  • Bond strength is treated as one uniform value along the whole bonded length. Soil layering, change with depth, drilling method, groundwater and grout pressure all move it, and a tabulated figure remains an assumption until verification and proof pull-out tests on site confirm what the ground actually delivers.
  • Static, short-term conditions only, and the 2.0 target is the common static minimum. Seismic loading, construction surcharge, creep in fine-grained soils and corrosion over a permanent wall's life are not in the arithmetic, and a project specification or a load-and-resistance-factor design can demand a different margin. This does not replace a geotechnical engineer's design.
6 in
Schematic, drawn to the proportions you entered — not to scale on screen.

Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.

Sources checked 2026-09-06 · in the site-wide review of 2026-09-06 · v1.0.1

Regulatory standards & verification citations1
  1. FHWA GEC No. 7 soil nail wall design: pullout capacity = nominal bond strength x pi x drill hole diameter x bonded length; a minimum pullout safety factor of 2.0 is standard practice
Cite this page

Your workspace

Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.

Now that you have the number

These guides cover the work this quantity is for — the first ones run this calculator inside the section that raises the question.

Still deciding? Soil Nailing vs Reinforced Soil Wall — the factors that actually differ, with no invented prices.

How to calculate soil nail pull-out safety factor in 5 steps

  1. Nominal Bond Strength (qs)The grout-to-soil bond strength, from FHWA GEC-7 tables or site-specific pullout testing.
  2. Drill Hole DiameterThe diameter of the drilled hole for the nail and grout.
  3. Bonded LengthThe length of the nail bonded (grouted) beyond the potential failure surface.
  4. Design (Working) LoadThe nail's design tensile load.
  5. Pull-out safety factorThe tool computes the pull-out safety factor from those figures and shows the formula, its sources, and a confidence rating alongside it.

Pull-out safety factor by nominal bond strength (qs)

Page defaults, not your figures above.

Nominal Bond Strength (qs)Pull-out safety factor ((target ≥2.0))
1,000 psf1.69
1,500 psf2.54
2,000 psf3.38
2,500 psf4.23
3,000 psf5.08
3,500 psf5.92
4,000 psf6.77

Frequently asked questions

Why does soil nailing need a pullout safety factor specifically?
Pullout (the grout column sliding out of the surrounding soil) is one of the primary failure modes for a soil nail — the safety factor ensures a comfortable margin between the design load and the actual resistance the bond can provide.
What if my bonded length seems very long?
Weaker soils (lower bond strength) need proportionally longer bonded lengths to develop the same capacity — this is normal and expected in soft or loose soil conditions.
Should I always use FHWA GEC-7 bond strength values?
They're a reasonable starting point for preliminary design, but site-specific pullout testing (required on most soil nail projects before or during production) gives a much more reliable bond strength value for your actual soil and installation method.
Preliminary estimate, not certified engineering. This tool produces an indicative quantity calculation for planning purposes only — it is not a certified structural analysis, a guaranteed material takeoff, or a substitute for building department approval. Always verify measurements on-site and have a licensed contractor or structural engineer review any load-bearing, code-sensitive, or safety-critical work before purchasing materials or starting construction. Spotted an arithmetic or standards error? Report it to contact@craftquantities.com with your inputs — a confirmed fix gets a permanent check of its own, so the same mistake cannot come back.