SettingsSettings for this calculationUS
The transformer's nameplate kVA rating.
Use the transformer's nameplate apparent power rating in kVA.
The three-phase line-to-line secondary voltage.
Line to line, not line to neutral — the two differ by the square root of three, and entering the line-to-neutral figure inflates the available fault current by about 73%. Take it from the transformer nameplate rather than from a measurement: fault current is computed from the nominal secondary and the impedance, and a measured no-load voltage runs above nominal.
The transformer's nameplate percent impedance.
A lower impedance percentage allows more fault current to flow, since impedance is what limits the fault current in this simplified method.
Estimated maximum available fault current
11,000 A
This is a transformer-only screening approximation (the 'infinite source' method), and it is NOT a worst case in either direction. It ignores upstream utility source impedance and downstream conductor impedance, which reduce the current available at a point further from the transformer. It also ignores two things that push the real figure ABOVE it: running motors feed a fault for the first few cycles at roughly four to six times their own full-load current, and nameplate impedance carries an ANSI/IEEE tolerance of plus or minus 7.5%, so a transformer at the low end of that band delivers proportionally more. Do not select an interrupting rating from this number. This is NOT a substitute for a complete short-circuit study (per IEEE 141/242 or equivalent software) required for proper overcurrent protective device rating, selective coordination, and arc-flash hazard analysis, which must be performed by a qualified electrical engineer.
- Transformer full-load amps
- 601.41 A
They open the calculator with your figures already in it
Transformer-Limited Short-Circuit Current Calculator: 10,935 A — shown in imperial, US market. The link sets both, so the result they see is the one on your screen.
Show calculation logicHide calculation logic
How this was calculated
Formula source(s)
- Simplified transformer-only fault current estimate: full-load amps = (transformer kVA × 1000) ÷ (voltage × √3) for three-phase; available fault current = full-load amps ÷ (transformer impedance percentage ÷ 100) — this is the classical 'infinite source' approximation used for preliminary screening. It ignores upstream utility source impedance and downstream conductor impedance, which reduce the current available at a given point — and it also ignores motor contribution and the tolerance on nameplate impedance, which raise it
Inputs used
- Transformer Rating (kVA)
- 500
- Secondary Voltage (V, Line-to-Line)
- 480
- Transformer Impedance (%, from Nameplate)
- 5.5
Intermediate steps
- Transformer full-load amps
- 601.41 A
Confidence note: This is a transformer-only screening approximation (the 'infinite source' method), and it is NOT a worst case in either direction. It ignores upstream utility source impedance and downstream conductor impedance, which reduce the current available at a point further from the transformer. It also ignores two things that push the real figure ABOVE it: running motors feed a fault for the first few cycles at roughly four to six times their own full-load current, and nameplate impedance carries an ANSI/IEEE tolerance of plus or minus 7.5%, so a transformer at the low end of that band delivers proportionally more. Do not select an interrupting rating from this number. This is NOT a substitute for a complete short-circuit study (per IEEE 141/242 or equivalent software) required for proper overcurrent protective device rating, selective coordination, and arc-flash hazard analysis, which must be performed by a qualified electrical engineer.
What this calculation does not cover
- The secondary voltage is used once, as the nominal line-to-line figure in (kVA × 1000) ÷ (volts × √3), and no input asks what the bus was actually sitting at in the moment before the fault, so a system running a few percent above nominal drives proportionally more current than this arithmetic returns — and typing that elevated voltage into the box moves the answer the wrong way, because the term sits in the denominator.
- Entries outside 15 to 2,500 kVA, 120 to 600 V or 2 to 8% impedance are pulled back to the nearest bound and answered there, so a 3,000 kVA unit or a 1.8% nameplate produces a figure lower than the transformer in front of you would actually deliver.
- One division by the impedance decimal serves for every kind of fault, and no input describes the winding connection or the grounding arrangement, so a line-to-ground fault — whose return path those two things govern — is not the event this number describes.
- The transformer full-load amps carried in the breakdown is the dividend of that same division, derived from nameplate kVA, so it is the working shown rather than an independent check, and it is rated capacity rather than the load actually connected to the secondary.
- Nothing in the arithmetic has a time dimension: the output is a magnitude at the instant of the fault, with no duration behind it, so it says nothing about how long the transformer or the bus it feeds can hold that current.
Add the equipment this sizes
This result is a specification — 11,000 A — not a quantity. Put the thing it sizes into your project: how many, what you call it, and your supplier’s price.
Computed in your browser — nothing you enter is uploaded. Presented in US customary units and US trade terminology. Where a formula follows a published standard, that standard and its edition are cited beside it on this page; where none governs, the page says so. Local amendments override model codes — verify against the code in force where you build.
Sources checked 2026-09-05 · in the site-wide review of 2026-09-06 · v1.0.1
Regulatory standards & verification citations1
- Simplified transformer-only fault current estimate: full-load amps = (transformer kVA × 1000) ÷ (voltage × √3) for three-phase; available fault current = full-load amps ÷ (transformer impedance percentage ÷ 100) — this is the classical 'infinite source' approximation used for preliminary screening. It ignores upstream utility source impedance and downstream conductor impedance, which reduce the current available at a given point — and it also ignores motor contribution and the tolerance on nameplate impedance, which raise it
Cite this page
Your workspace
Most jobs need more than one number. Add the calculators you need next and they open right here, underneath this one — your figures stay on screen and nothing is lost to a page change.
Protection this work requires
- Stop and check first. Textured ceiling coatings, board behind panels, floor tiles and bitumen adhesive in older buildings — built before asbestos was banned or phased out where you are — can contain asbestos, and drilling or sanding them releases fibres. Do not disturb it — have it sampled first. This is not a job for better PPE.
Tools and safety for this job
To first-fix electrical. Generic types, no brands, no prices.
- Assume every cable is live until proved dead at the point you will touch, with a two-pole tester you have just proved on a known source.
First-fix electrical: This site does not publish a tool list for electrical installation work. In every market it serves, fixed wiring is either reserved to a registered electrician or notifiable to a building authority, and the failure mode is a fire or an electrocution months later rather than a visibly bad job on the day. The calculator gives you the quantities to discuss and to buy against. The installation is a job for a qualified electrician, and the certificate they issue is the point of them.