# Getting the Incoming Electricity Supply Upgraded

> Reading the cut-out before you promise anything, working out the capacity the network application is really asking for, and living with the answer.

Page: https://craftquantities.com/guides/how-to-upgrade-an-incoming-electricity-supply/ (trade guide, Electrical). This is the page's Markdown copy; the HTML page is the canonical version.

Published 2026-08-31.

## Three Jobs Share One Name

The hob has already been delivered. The heat pump has a deposit on it, the charger is booked for a Tuesday, and somebody has told the customer that the supply needs upgrading to a hundred amps — a sentence that describes four completely different pieces of work, costing anywhere from a call-out fee to the price of a small extension, on lead times separated by an order of magnitude.

Sorted by what has to be dug up, they are these. A larger fuse link in the existing cut-out, where the service cable behind it was always adequate and only the link was conservative. A replacement service cable from the property to the main already lying in the street. A change in the number of phases delivered, which is a new service and a new meter and often a new intake position. And reinforcement, where the main itself, or the transformer feeding it, has no capacity left to give and the work moves out of the garden and into the road.

Which of the four you are in is not your decision and cannot be inferred from anything visible at the property. It turns on the size of the buried service cable, the spare capacity in the low-voltage main, the loading on the transformer, and — increasingly the deciding factor — how many neighbours have asked the same question in the last three years. What you control is the quality of what you send in: an accurate description of what is there, and a capacity figure you can defend when somebody queries it.

## The Fuse Is the Distributor's, and It Is Not a Capacity

Start at the intake with a torch and a camera. On a British service you are reading a moulded carrier with a rating on it, a fuse link inside that carrier with its own rating and standard marking, and a wire-and-lead seal across the assembly. Domestic service cut-out links are made to BS 88-3, which superseded the BS 1361 Type II links still sitting in plenty of older intakes; sixty, eighty and one hundred amperes are what you will normally meet. On a North American service the equivalent reading is the utility transformer and service conductors on one side and the rating of the service disconnecting means on the other, the latter governed by NFPA 70 Article 230.

The carrier and the link are separate ratings and they disagree more often than people expect — a hundred-ampere carrier will happily hold a sixty-ampere link, and on many designs the link rating cannot be read at all without withdrawing the carrier. Do not withdraw it. That assembly is the distributor's property, the seal is there for a reason, and in Great Britain the whole arrangement sits under the Electricity Safety, Quality and Continuity Regulations 2002 and the distributor's own access policy. A booked fuse pull costs very little set against what happens to an installer found working inside sealed equipment.

The more useful thing to understand is what the fuse is for. It is protecting the service cable against fault current, not rationing the household. Its time-current characteristic is drawn to clear faults, which means a sustained modest overload can persist for a very long time without operating anything — so a house that has been fine on sixty amperes for thirty years has told you nothing whatever about whether that service cable has been running warm for a decade. The absence of a blown fuse is not evidence.

The reverse error is commoner and more expensive. A hundred-ampere fuse is not a promise of a hundred amperes. Behind it sit a service cable of unknown size, a main under the pavement shared with the rest of the street, and a transformer, and every one of those was planned on an after-diversity maximum demand — a per-property figure of a few kilowatts, set out in each distributor's own network design standard and its licence-mandated long term development statement, and ask for the current one rather than quoting a number you remember. Nothing in that planning chain assumed your customer would draw the twenty-three kilovolt-amperes a hundred-ampere single-phase service could theoretically deliver, and the whole street's worth of that assumption is what a wave of heat pumps is currently testing.

Record all of it before you leave. You will be asked for every line of it, a second visit is unpaid, and each of these readings is silent about something people routinely assume it covers.

**What to read at the intake, and what each reading does not tell you**

| What you are looking at | What to write down | What it is silent about |
|---|---|---|
| Cut-out carrier and fuse link | Carrier rating, link rating and standard marking, seal condition, manufacturer | The size of the service cable behind it, and the spare capacity in the street |
| Service entry | Underground or overhead, sheath condition at the gland, apparent age of the termination | The conductor size, which only the distributor's own record will confirm |
| Earthing terminal | Whether the distributor provides an earth, how it is labelled, the conductor size leaving it | Whether the same arrangement will still be offered once the service is replaced |
| Meter and tails | Whole-current or transformer-operated metering, tail size, presence of an isolator | Which supplier and meter operator hold the appointment, which the customer must ask |
| Meter enclosure and position | Internal dimensions, spare width, whether a larger cut-out and meter would fit | Whether the distributor will accept that position for the replacement intake |
| Supply number | The full supply number from the bill or the meter, distribution area digits included | Anything about capacity; it identifies the connection point and nothing more |

## The Loads That Started the Conversation

Three loads arrive together in this decade and none of them behaves like the appliances the service was sized around. The heat pump modulates: for most of the year it draws a fraction of its nameplate, and then on the coldest morning of the year the compressor is at maximum and the resistive backup element energises on top of it. The figure you want is the maximum running current the manufacturer publishes — Mitsubishi Electric, Daikin and Vaillant all state it in the installation manuals for their domestic ranges, along with a starting current — and not any number derived from the heat output on the brochure.

The induction hob's nameplate is the arithmetic sum of every zone at boost, a condition that occurs in a laboratory and not in a kitchen. Nearly every hob sold now has a power limitation setting in its installation menu, stepping the total down to suit a smaller circuit, and configuring it is an entirely legitimate way to reduce the connected load. It is legitimate on one condition: the setting is recorded on the certificate and the householder is told what reversing it would mean, because an assessment resting on a menu option nobody wrote down expires the first time the appliance is serviced.

The charge point is the simple one to characterise and the hardest one to accommodate — full configured current, flat, for hours, on the same winter evenings as everything else. It needs no diversity argument because it does not behave diversely.

Coincidence is the whole question. Individually all three fit; the interesting number is what happens at half past six on a January evening with the hob at three zones, the heat pump in defrost with its backup on, and the car plugged in. Before any of that reaches a whole-house figure, though, each new circuit has to stand on its own against the continuous-load rule, because a service upgrade fixes nothing about a branch circuit that was already at its limit.

Take each new load on its own first — the hob at its configured limit, the heat pump with the backup element energised, the charger at its set current — and see how much of that circuit is genuinely spare. This runner applies the North American continuous-load rule to a 120 or 240 volt circuit on a 15 to 50 ampere breaker, so read the percentage rather than the amperage if your circuit is a British 32 ampere one at 230 volts. Either way the point is the same: a circuit already at its continuous ceiling is not a problem a bigger incoming fuse solves. The page runs [Electrical Circuit Load Calculator](https://craftquantities.com/calculators/electrical/electrical-load-calculator/) here.

## The Figure the Application Form Wants

The form does not ask what the property draws. It asks what capacity you want the network to reserve, which is a different question with a different answer, and confusing the two is how applications come back with queries. The reserved figure has to cover the worst case the installation can present, because the network is committing conductors and transformer capacity against it for the life of the connection.

Build it the way an inspector would recognise. The standard method assembles a general lighting allowance from floor area, the small-appliance and laundry circuits at their fixed values, the nameplate ratings of the fixed appliances, and then applies the published demand factors — NFPA 70 Article 220 in North America, BS 7671 Part 3 read with the maximum demand and diversity appendix of the IET On-Site Guide in the United Kingdom, the maximum demand appendix of AS/NZS 3000 in Australia and New Zealand. Whichever document you work from, note which one it was next to the number. The interesting comparison is not between your figure and the fuse; it is between your figure and the few kilowatts per property the distributor's own planning assumed, and that gap is what a reinforcement decision is made in.

Ask for what the installation needs and resist the temptation to take the largest option on the drop-down. On a constrained network an inflated request is what converts a straightforward service alteration into a reinforcement scheme with a reinforcement timetable, and in some charging regimes reserved capacity carries a standing cost the customer will meet every year. Under-asking is worse in a different way: coming back for another twenty amperes in two years is a second application, a second excavation and a second set of fees, none of which anybody budgeted.

Assemble the whole-dwelling figure before you fill anything in. This one runs the NFPA 70 Article 220 standard method — floor area, small-appliance and laundry circuits, fixed-appliance nameplate, then the demand factor — so take it as the worked shape of the calculation rather than as a British answer; a United Kingdom application wants the same assembly run through the On-Site Guide diversity appendix. Either way it is the number you will be setting against the distributor's own per-property planning assumption. The page runs [Home Electrical Service Panel Amperage Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/service-panel-sizing-calculator/) here.

## Kilowatts on the Nameplate, Kilovolt-Amperes on the Offer

Everything the customer owns is labelled in kilowatts. Everything the network sells is denominated in kilovolt-amperes. That is not a formatting preference: transformer windings and buried conductors heat according to the current passing through them, current follows apparent power, and so the quantity the distributor has to ration is the one that includes the reactive component it gets no revenue for.

For an all-electric house the two figures nearly coincide, because resistive heating, immersion elements and modern power supplies present something close to unity. A workshop does not. A compressor, a welding set and a couple of motor-driven machines pull the displacement power factor down, and inverter-driven equipment can present a respectable displacement figure while its harmonic content still inflates the current the conductor actually carries. IEC 61000-3-2 and IEC 61000-3-12 set what equipment may inject; the consequence at the intake is that the true power factor and the one on the specification sheet are not always the same number.

The conversion trips people in one direction specifically. Going from a kilowatt load schedule to the kilovolt-ampere capacity you must request means dividing by the power factor, and dividing makes the number bigger — an eighty-kilowatt workshop load at a power factor of 0.8 needs a hundred kilovolt-amperes reserved, not eighty. Where the constraint or the tariff is expressed in kilovolt-amperes, correction equipment genuinely buys capacity back, which is occasionally a cheaper answer than the upgrade the customer came to ask for.

This is the direction that matters on an application: a load schedule in kilowatts, a capacity request in kilovolt-amperes, and a division that makes the number larger. The runner is fixed at a power factor of 0.8 — the mixed-load planning convention, and the figure behind the eighty-kilowatt workshop above — so for any other power factor take the result as the shape of the sum and divide by your own. The page runs [kW to kVA Calculator](https://craftquantities.com/calculators/electrical/kw-to-kva-calculator/) here.

## When the Answer Comes Back Three Phase

The reply is frequently not the bigger single-phase service that was asked for. Where the main in the street is already three-phase and the existing service is simply a spur taken off one of its phases, giving the property all three is often the distributor's cheapest route to more capacity — the trench is the same trench and the cable is barely larger. In Great Britain that turns twenty-three kilovolt-amperes on a single hundred-ampere phase into roughly sixty-nine across three at four hundred volts between lines, which is more headroom than a domestic customer will ever use.

It changes a great deal downstream. A three-phase board with a three-phase main switch, tails per phase plus a neutral, a physically larger intake, and — this one catches people — a different meter. In Great Britain whole-current metering runs out at a hundred amperes per phase; above that the connection moves to transformer-operated metering with a current transformer chamber ahead of the meter, which is a materially different intake enclosure and a materially different price. On the workshop side the gain is real: three-phase machines start properly, and the rotary converter or the drive that has been standing in for a missing phase can come out.

The vocabulary does not travel. In North America a residential three-phase supply is unusual, and a shop building typically receives 208Y/120 or 480Y/277 under ANSI C84.1. Two hundred and eight volts is not two hundred and forty, and equipment rated for a 240-volt single-phase supply run instead across two legs of a 208-volt system delivers materially less than its rating — resistive heating loads suffer most, and the discovery is normally made after the equipment is installed.

Whatever the arrangement, ask two questions before accepting. What becomes of the existing single-phase circuits on the changeover day, and how long the property is without a supply while it happens. A three-phase board in a house means four hundred volts is present between adjacent ways in equipment most people who ever open it will assume is a 230-volt board, so labelling, segregation and the schedule you leave behind matter more here than they do on the single-phase job.

Line voltage, current per phase and power factor give what a three-phase service actually delivers. Set that against the machine schedule for the workshop before agreeing to the offer, not after the switchgear is ordered. The page runs [Three-Phase Power Calculator](https://craftquantities.com/calculators/electrical/three-phase-power-calculator/) here.

## Sharing It Across Three Ways

A three-phase supply feeding a building whose loads are all single-phase is really three separate single-phase supplies that you are obliged to fill evenly. Protection is per phase: the first phase to reach its fuse rating is the limit of the whole service, and it is no consolation at all that the other two were half loaded when it went. A workshop that grew one machine at a time, each landed on whichever way was free that week, is almost always worse than the person who owns it believes.

The neutral is where imbalance shows up. In a balanced four-wire system the three line currents largely cancel in it; imbalance puts the difference straight back, and single-phase electronic loads add third-harmonic currents that sum in the neutral instead of cancelling there. That is why the neutral is no longer automatically the smaller conductor it used to be, and why the current-carrying capacity appendix of BS 7671 carries reduction factors tied to harmonic content. Sizing a neutral by habit on a building full of drives and switched-mode supplies is a genuine hazard rather than a paperwork failing.

Rotating plant pays for imbalance directly. Voltage unbalance at the terminals of an induction motor produces a negative-sequence current far out of proportion to it, and NEMA MG 1 publishes the derating curve that follows: a few per cent of voltage unbalance costs a disproportionate share of the motor's thermal margin and its life. Balance is therefore something to measure at commissioning and again after the fit-out, because the day-one schedule is always balanced and the building as occupied never is.

Enter the three phase currents as you measured them, not as the schedule predicted them. The imbalance percentage is what tells you whether the service is genuinely full or whether one phase is simply carrying more than its share. The page runs [Three-Phase Electrical Panel Load Balancing Calculator](https://craftquantities.com/calculators/materials-quantities/panel-phase-balance-calculator/) here.

## A Better Supply Raises the Fault Level

The thing that makes an upgraded service good is exactly the thing that makes it more dangerous at the origin. A larger conductor, a shorter run, a nearer or larger transformer — every one of those lowers the source impedance, and lower source impedance means a higher prospective short-circuit current at the cut-out. The consumer unit downstream, its main switch, and the conditional short-circuit rating of the devices inside it were all selected against whatever the old service could deliver.

So measure the prospective fault current and the external loop impedance after the changeover rather than reusing the survey figures, and record both. Distributors in Great Britain declare a maximum prospective fault current for a domestic service — sixteen kilo-amperes is the figure most commonly quoted at the origin — and an assembly whose rating was justified by a comfortable measurement taken on the old supply is a non-compliance that nothing in the installation's behaviour will ever reveal.

## The Earthing Arrangement Comes With the Offer

A new service can arrive with a different earthing arrangement from the one it replaced, and this is not always flagged. A property that never had a distributor earth may be offered one; a property that had a combined neutral and earth arrangement may find it withdrawn, particularly where the replacement service comes in overhead or where the distributor's policy for that class of connection has moved on. Either change lands on the installation designer, not on the distributor.

The consequences run through the whole protective system. Main protective bonding conductor sizes are set by the earthing arrangement and the size of the supply neutral, not by the load — the requirements where a protective multiple earthing terminal is provided are larger, and BS 7671 Chapter 54 read alongside Energy Networks Association Engineering Recommendation G12 is where that comes from; NFPA 70 Article 250 and its grounding electrode conductor table are the counterpart on the other side of the Atlantic. A new service therefore means going back to the gas and water bonds and the structural steel, which in a house of any age means finding a single undersized conductor clamped somewhere convenient rather than where the service enters.

Where the distributor declines to provide an earth at all, the installation needs its own electrode, and that is a redesign rather than an adjustment: earth fault loop impedance is now dominated by the electrode resistance, every final circuit depends on residual current protection for disconnection, and the soil the electrode is going into is a variable nobody chose. Price that possibility before the offer is accepted, because discovering it afterwards makes it the customer's surprise instead of a line in the quotation.

## Trench, Meter Box, and Who Digs What

Almost every offer splits the physical work at a point of connection: the distributor works up to it, and everything on the customer's side is the customer's to provide. Excavation, ducting, backfill, reinstatement and the meter enclosure are the usual customer-side items, and taking the self-dig option is normally the single largest saving available on the whole job — provided the groundwork is done to their specification and not to a general idea of what a trench looks like.

That specification is prescriptive and it is worth having in writing before anyone hires a machine. Depth of cover, bedding material, warning tape, duct diameter and colour, minimum bend radius, a draw rope left in place, and jointing pits wherever the route changes direction enough to make the pull unreasonable. Have the open trench inspected before it is closed. A trench backfilled early on the assumption that it was obviously fine is a trench that gets reopened, and the second excavation is nobody's contractual obligation but the customer's.

Land the customer does not own stops jobs dead. A service crossing a neighbour's garden, a shared drive, a farm track or an access strip requires a wayleave or an easement, and that is a legal instrument on a legal timescale measured in months rather than weeks. On rural connections it is the commonest reason a scheme stalls after the offer has been signed and the money paid.

Settle the intake position early, because it decides more than it looks like it decides. Moving a meter from an internal cupboard to an external box is frequently bundled into the upgrade, and where the intake ends up sets the tail lengths, the board position, the route of the main protective bonding, and whether the consumer unit finishes somewhere with the clear working space the rules in force require in front of it.

1. Walk the route with the distributor's engineer before anybody prices the groundwork.
2. Establish the point of connection on the ground and confirm in writing who owns each side of it.
3. Get the duct, depth, bedding and reinstatement specification in writing and read it before hiring plant.
4. Establish ownership of every metre of the route, and start the wayleave or easement the same week if any of it is not the customer's.
5. Hand-dig at every crossing with an existing service and record the depth and separation you found.
6. Have the trench inspected and photographed open, dimensioned from two fixed points on the building.
7. Leave the duct roped, sealed at both ends and drawn through, and fit the enclosure before the energisation date.

## Three Organisations, One Energisation

The connection involves three separate parties and only one of them is the distributor. The distributor owns the service cable and the cut-out. The supplier holds the customer's account. The meter operator, appointed by the supplier rather than by the customer, owns and fits the meter. Nothing coordinates the three by default, and the customer is the only person with a contractual relationship with all of them.

The failure this produces is predictable enough to plan around: a new service energised and sealed, and no meter, because the metering appointment was never raised. A change in phase count almost always means a new meter, sometimes a new supply number, and always a fresh appointment booked through the supplier — who will ask the customer for it and not you. Raise it at the same time the offer is accepted, not when the distributor has finished.

Sequence your own work to be genuinely ready. Tails of the right size and length, an isolator where one is needed, the board fitted, the earthing and bonding complete and tested, and the installation certificate available. The energisation visit is short and it is not a fault-finding visit; an installation still open when the engineer arrives becomes a second appointment at a lead time nobody quoted for.

## What the Next Person Needs From You

Leave a record that survives you. The offer reference and the capacity requested; the new fuse rating with its standard marking; the earthing arrangement actually provided and whether it changed; the prospective fault current and external loop impedance measured after energisation; the duct route dimensioned from two fixed points; and every configured setting — the hob's power limit, the heat pump's backup element, the charge point's output — that the demand assessment quietly depends on. Whoever adds a battery to this property in three years is either building on that or repeating all of it.

Then be straight with the customer about what has and has not been bought. A reserved capacity is a commitment about this connection, not a statement about the street. If the network was already tight, the next few applications on the same main are the ones that get the conditional answers, and if the property is on the end of a rural spur then voltage at the far end — the range every distributor must hold under its own statutory obligation — may govern long before capacity does. Saying so on the day is a better conversation than having it after a complaint.

## Settling the numbers before the form is filed

Nearly all of this is decided at the property with a torch and a camera, and the rest of it on a desk before anything is submitted. These are the lines that decide whether the answer comes back in a fortnight or in eighteen months.

- **Carrier rating, link rating and standard marking, read at the cut-out**: Photographed with the seal intact; the two ratings disagree often enough that recording only one is worthless.
- **Whole-installation demand assembled by a named method**: Write down which document supplied the demand factors, because the application will be queried against it and the note is free at the time.
- **Manufacturer maximum running current for each new load**: Heat pump with its backup element, hob at its configured limit, charger at its set output — not figures derived from heat output.
- **Requested capacity converted to kilovolt-amperes at a real power factor**: Divide, do not multiply; a workshop schedule in kilowatts always understates what has to be reserved.
- **Phase count decision and its downstream cost**: Board, main switch, meter type and whether whole-current metering still applies above a hundred amperes per phase.
- **Ownership of every metre of the cable route**: A wayleave or easement across a neighbour or a track is a legal timescale, and it is the usual reason a signed offer then stalls.
- **Earthing arrangement offered with the new service**: Bonding conductor sizes follow the arrangement rather than the load, and a withdrawn distributor earth is a redesign to be priced early.

Calculators for these quantities: [Home Electrical Service Panel Amperage Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/service-panel-sizing-calculator/), [Electrical Circuit Load Calculator](https://craftquantities.com/calculators/electrical/electrical-load-calculator/), [kW to kVA Calculator](https://craftquantities.com/calculators/electrical/kw-to-kva-calculator/), [Three-Phase Power Calculator](https://craftquantities.com/calculators/electrical/three-phase-power-calculator/), [Three-Phase Electrical Panel Load Balancing Calculator](https://craftquantities.com/calculators/materials-quantities/panel-phase-balance-calculator/).

## Calculators this guide uses

- [Electrical Circuit Load Calculator](https://craftquantities.com/calculators/electrical/electrical-load-calculator/)
- [Home Electrical Service Panel Amperage Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/service-panel-sizing-calculator/)
- [kW to kVA Calculator](https://craftquantities.com/calculators/electrical/kw-to-kva-calculator/)
- [Three-Phase Power Calculator](https://craftquantities.com/calculators/electrical/three-phase-power-calculator/)
- [Three-Phase Electrical Panel Load Balancing Calculator](https://craftquantities.com/calculators/materials-quantities/panel-phase-balance-calculator/)
- [Transformer Sizing Calculator](https://craftquantities.com/calculators/electrical/transformer-sizing-calculator/)
- [Transformer-Limited Short-Circuit Current Calculator](https://craftquantities.com/calculators/materials-quantities/short-circuit-current-calculator/)
- [Amperage to Wire Gauge Calculator](https://craftquantities.com/calculators/electrical/amperage-to-wire-gauge-calculator/)
- [Equipment Grounding Conductor Sizing Reference Calculator](https://craftquantities.com/calculators/materials-quantities/grounding-conductor-sizing-calculator/)
- [kVA to kW Calculator](https://craftquantities.com/calculators/electrical/kva-to-kw-calculator/)
- [Cable Voltage Drop Calculator (mm², Copper or Aluminium)](https://craftquantities.com/calculators/electrical/cable-voltage-drop-calculator/)
- [Copper to Aluminum Wire Size Calculator (Aluminium Equivalent, AWG and mm²)](https://craftquantities.com/calculators/electrical/copper-aluminum-wire-equivalent-calculator/)
- [Electrical Panel Circuit Directory Slot Calculator](https://craftquantities.com/calculators/materials-quantities/panel-slot-calculator/)

## Sources

- Electricity Safety, Quality and Continuity Regulations 2002 (Great Britain), including the declared supply voltage and the distributor's duties at the supply terminals
- Electricity Act 1989, the duty on a distributor to make a connection on request
- BS 88-3 Low-voltage fuses — Supplementary requirements for fuses for use by unskilled persons (fuses mainly for household or similar applications)
- BS 7671 Requirements for Electrical Installations (IET Wiring Regulations), Part 3 Assessment of General Characteristics and Chapter 54 Earthing Arrangements and Protective Conductors
- IET On-Site Guide, the appendix on maximum demand and diversity
- IET Guidance Note 1: Selection and Erection
- Energy Networks Association Engineering Recommendation G12, Requirements for the Application of Protective Multiple Earthing to Low Voltage Networks
- Energy Networks Association Engineering Recommendation P2, Security of Supply
- Energy Networks Association, National Terms of Connection
- Distribution Connection and Use of System Agreement (DCUSA), the common connection charging methodology
- NFPA 70 National Electrical Code, Article 220 Branch-Circuit, Feeder, and Service Load Calculations
- NFPA 70 National Electrical Code, Article 230 Services
- NFPA 70 National Electrical Code, Article 250 Grounding and Bonding
- ANSI C84.1 Electric Power Systems and Equipment — Voltage Ratings (60 Hz)
- NEMA MG 1 Motors and Generators, the derating of polyphase motors for voltage unbalance
- IEC 60038 IEC Standard Voltages
- IEC 61000-3-2 and IEC 61000-3-12, limits for harmonic current emissions
- AS/NZS 3000 Electrical Installations (Wiring Rules), the appendix on maximum demand
- CSA C22.1 Canadian Electrical Code, Section 6 Services and Service Equipment
- Mitsubishi Electric Ecodan, Daikin Altherma and Vaillant aroTHERM installation manuals, for maximum running and starting current

---