# Building an Extension Over or Near a Drain

> A manhole inside the footprint is a consent question before it is a building one: whose pipe it is, whether it moves, and who signs it off.

Page: https://craftquantities.com/guides/how-to-build-over-a-drain/ (trade guide, Drainage). This is the page's Markdown copy; the HTML page is the canonical version.

Published 2026-08-31.

## A cast iron cover 1.4 metres inside the new wall line

The pegs went in on the Saturday. The turf came off on the Monday, and in the second bucket of topsoil the driver caught the corner of a square of cast iron nobody had drawn. It sits about 1.4 m inside what is meant to become the rear wall of a four by six metre kitchen, under what the drawing labels as lawn. The engineer has specified trench fill on the strength of a trial pit dug three metres away in ground he had every reason to think was undisturbed.

Nothing here makes the extension undeliverable. What it does is reorder the job. A drainage question has moved in front of the foundation question, and the answer to it belongs to somebody who does not work for you and is not on your programme. Lift the cover before you do anything else and the day stops being an emergency: what you need from it is who the pipe belongs to, how deep it is, and where it goes.

Three decisions follow from that, and they are separable. Whether the pipe is yours or the sewerage undertaker's decides whether you need a written agreement at all. Whether the chamber can be moved, rebuilt outside the wall line, raised into the new floor or bypassed altogether decides the shape of the drainage works. And whether the run stays under the room decides what the foundations and the slab have to do about it. Take them in that order, because getting the third one designed before the first is answered is how a set of structural drawings gets paid for twice.

## Whose pipe is it, and how to find out for certain

In England and Wales the honest answer is probably not yours, and that surprises homeowners who have owned the house since before the change. On 1 October 2011 the Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011 transferred to the sewerage undertakers almost every private sewer and lateral drain connected to the public system: anything serving more than one property, and the length of your own drain beyond your property boundary. What stayed private is narrow — the pipework inside your own boundary that serves only your house. A chamber in your back garden taking a branch from next door has been the water company's asset for fifteen years, whoever paid to jet it last winter.

The map to check is the statutory public sewer map the undertaker is required to keep under the Water Industry Act 1991, obtained as an asset location search either directly from the company or through a search provider. Read it for what it is. It is a record, not a survey: positions are indicative, depths are usually absent, and transferred lateral drains and shared private sewers are frequently not drawn at all because nobody ever recorded them. A pipe missing from the map is not therefore yours. Ownership follows what the pipe does — how many properties it serves and which side of the boundary it is on — not whether a draughtsman got to it.

Where the map is silent, prove connectivity on site. A dye tablet flushed from the neighbour's downstairs WC, watched from your chamber, settles in ten minutes an argument that can otherwise run for weeks, and a CCTV survey run upstream from the chamber will find the junction that the dye implies. Do both before the application, not after, because an agreement written against the wrong ownership is worth nothing and the undertaker will discover the branch when its own surveyor looks.

1. Order the asset location search and read the plan alongside the deeds, not instead of them.
2. Lift every cover on the plot and the two nearest in the street, and photograph each open.
3. Dye test any chamber with an inlet you cannot account for from your own fixtures.
4. Get a pre-works CCTV survey coded to the WRc Manual of Sewer Condition Classification.
5. Ask the undertaker for its current build-over criteria in writing before the architect redraws anything.

**What the pipe is, who owns it, and what the extension therefore needs — England and Wales, after the 2011 transfer. Scotland, Northern Ireland and Ireland reach the same places by different routes.**

| The pipe | Usually owned by | What the extension needs |
|---|---|---|
| Drain within your boundary serving only your house | You | Building control approval against Approved Document H; no undertaker agreement |
| Lateral drain — your drain, beyond your boundary | The sewerage undertaker | A build over or build near agreement before work starts |
| Shared drain or private sewer serving two or more properties | The undertaker, since 1 October 2011 | An agreement, and normally a diversion where a chamber falls inside the footprint |
| Public sewer shown on the statutory sewer map | The undertaker | An agreement, with building over a manhole normally refused outright |
| Rising main from a pumping station | The undertaker | Normally no build over on any terms — the line is diverted or the extension moves |

## Reading the chamber before deciding anything

Everything downstream of this depends on levels, so take them once and take them properly. Set a temporary bench mark somewhere that will survive the whole job — a nail in a fence post, a mark on the neighbour's threshold — and level from it to the cover and to the invert of every channel in every chamber you can reach. The same bench mark then sets out the extension, which means the drainage levels and the building levels cannot drift apart later. Record pipe diameter and material at each inlet, the direction each one comes from, the state of the benching, and whether the system is foul, surface water or combined. A combined system changes the whole conversation, because the surface water you were planning to send to a soakaway may currently be going somewhere it is no longer allowed to go.

Do not climb in. A chamber deep enough to stand up in is a confined space, and in Great Britain entry is governed by the Confined Spaces Regulations 1997 with the HSE approved code of practice L101 setting out what a safe system of work looks like — atmospheric testing, a tripod and harness, a competent standby person and rescue arranged before anyone descends. In the United States the equivalent regime is OSHA 29 CFR 1926 Subpart AA for confined spaces in construction. Everything a homeowner needs from the chamber can be measured from the surface with a dipping tape and a mirror.

With two inverts and the distance between them you have the existing gradient, and that single number does more work than any other measurement on the job. It tells you whether the run is already close to its minimum fall, which is the usual reason a diversion around an extension turns out to be impossible. It tells you whether the pipe is unusually steep, which is a hint at an earlier alteration and a reason to look harder at the survey footage. And it is the figure the undertaker will check your proposal against, because a diversion is only acceptable if the new line holds a gradient the standard accepts.

Put the upstream and downstream invert levels in as you levelled them, with the plan distance between the two chambers, and read the existing run as a percentage. Keep that figure at the top of the sheet — every diversion option gets compared against it. The page runs [Storm Drain Pipe Slope Calculator](https://craftquantities.com/calculators/materials-quantities/storm-drain-slope-calculator/) here.

## Three ways past it, and what an agreement actually buys

The regulatory frame is short. Approved Document H to the Building Regulations 2010 carries a section, H4, titled Building over sewers, and it is written for exactly this: work over, or close to, a drain or sewer shown on the public sewer map. Its concern is not aesthetic. It asks that the building does not damage the pipe, that the pipe does not damage the building, and above all that the undertaker can still get at the sewer to maintain it after your kitchen is standing on top of it.

Alongside it runs a mechanism that operates whether or not you go looking for it. Regulation 15 of the Building Regulations 2010 makes the building control body consult the sewerage undertaker wherever H4 applies, hold the application open for fifteen days while it answers, have regard to what it says, and consult it again before any completion certificate is issued. So the water company hears about your extension through building control even if you never write to it — which is why an application submitted with the drainage question still open tends to come back rather than through. Ignore, incidentally, the older hook that half the search results still cite: section 18 of the Building Act 1984, Building over sewer etc., was repealed on 1 April 2002 by the Building (Amendment) Regulations 2001, and H4 with regulation 15 is precisely what replaced it. In practice the consent that matters day to day remains the undertaker's own build over or build near agreement, applied for and granted before work starts.

What the agreement buys is permission plus a set of conditions, and what it costs you is a permanent liability. Read the conditions as a specification: they will normally cover the pre-works and post-works CCTV surveys, the protection detail over the pipe, how close a foundation may come and how deep it must go if it does, whether flexible jointing is required either side of the crossing, and how the works are to be inspected. Read the liability as what it is. The undertaker retains the right to excavate to reach its sewer, and reinstatement of what it has to break through to get there is generally not its problem. That clause is the reason building over a manhole is refused so consistently: a chamber is the access point, and a room built on top of one removes it.

Which leaves three practical routes. Build over, where the pipe runs beneath the new floor and is protected in place — the cheapest when it is allowed and the one most often refused where a chamber is involved. Build near, where the footprint clears the pipe but a foundation comes within the trigger distance, which is the commonest outcome once a scheme has been nudged half a metre. And divert, where the run is relaid around the extension and the chamber is rebuilt outside the wall line — more groundwork, no permanent access problem, and frequently the option the undertaker signs fastest. A fourth exists and is worth a conversation early: move the extension. A scheme shifted 600 mm off a sewer costs a redrawn plan, and everything else on this page costs more than that.

1. Confirm which route the undertaker will entertain before the structural design is commissioned.
2. Ask whether the company offers self-certification for minor works, and what disqualifies a job from it.
3. Allow real time in the programme — an agreement is measured in weeks, not in days.
4. Get the protection detail confirmed in writing, and give the same sheet to building control.
5. Keep the post-works survey obligation visible on the programme; it is the condition most often forgotten once the slab is down.

## If the line moves, fall is the whole constraint

A diversion is arithmetic against a fixed pair of ends. The upstream invert you are working from does not move and the connection you are heading for does not move, so the fall between them is a fixed budget — and going around three sides of an extension instead of straight under it spends more of that budget on length. Where the existing run was laid close to its minimum, the longer route simply does not fit, and that is discovered with a level and a tape rather than on site with a machine standing idle.

The minimum gradients are published. For foul drains, Approved Document H1 recommends 1 in 40 for a 100 mm pipe at low peak flow, 1 in 80 for a 100 mm pipe serving at least one WC, and 1 in 150 for 150 mm pipe serving at least five WCs — the flatter figures being conditional on the flow being enough to keep the invert scoured. In North America the International Plumbing Code sets the same idea as a slope table by pipe size, a quarter inch per foot on small horizontal drainage pipe and an eighth of an inch per foot on larger sizes. Both traditions share the unstated second half of the rule: too steep is also a defect. A pipe laid at 1 in 10 lets liquid run away from the solids it was carrying, and the blockage arrives a year after the plasterer has left.

Where fall genuinely runs out, the answer is usually a backdrop rather than a flatter pipe — the level is dropped vertically at a chamber and the gradient is restored downstream of it. That is a design decision for the undertaker to accept, not a site improvisation, and it changes the chamber from something you buy off a pallet into something detailed.

Enter the horizontal length of the diverted run and the pipe size band to get the minimum drop it must be given, then set that against the fall you actually measured between the two chambers. If the drop needed exceeds the fall available, the route around the extension is the wrong route. The page runs [Drain Pipe Slope Calculator](https://craftquantities.com/calculators/plumbing-hvac/drain-pipe-slope-calculator/) here.

## Rebuilding the chamber outside the wall line

Moving a chamber is not moving a chamber. It is building a new one on a new base, cutting the line into it, and taking the old one out to below foundation level so it cannot leave a soft spot under the extension. Where the depth to invert is modest, a moulded plastic inspection chamber base with preformed channels and branches is quicker and holds its levels better than anything built by hand. Where the depth is greater, the structure is precast: a base with benching, straight ring sections stacked to the height required, a reducing slab or a cone at the top, and thin adjusting units under the frame so the cover can be brought exactly to finished level. In the United Kingdom those components are made to BS EN 1917 with the complementary BS 5911-3; in North America the equivalent is ASTM C478 for precast reinforced concrete manhole sections, with the joints gasketed to ASTM C443.

Two details decide whether the rebuilt chamber is a success. The first is the cover. Load class is set by BS EN 124, and the class follows where the cover ends up rather than where it started — a chamber that used to sit in a lawn and now sits in the new driveway needs a cover rated for wheel loads, not the light duty tray that came out of the grass. The second is the depth at which a chamber stops being something you reach into and becomes something a person has to enter. Approved Document H1 scales its access provisions with depth, and past a certain point the choices are a man-entry structure or a restricted access cover that keeps people out. Choosing the second deliberately is a legitimate design decision and a kindness to whoever owns the house next.

Count the rings from the depth, not from the drawing. The stack has to make up the distance from the top of the base unit to the underside of the cover slab, and it can only do that in whole standard heights — which is why the adjusting units exist and why the last hundred millimetres is the fiddly part. Order the base, the rings, the cover slab, the frame and the sealant as one delivery, because a chamber left open overnight in a live drain run is a hole full of foul water in a garden with a gate.

Give it the depth you levelled and the ring height of the product the merchant actually stocks, not a nominal figure. The count comes back rounded up, which is correct — rings do not come in halves, and the shortfall is made up in adjusting units under the frame. The page runs [Manhole Ring/Riser Segment Calculator](https://craftquantities.com/calculators/materials-quantities/manhole-ring-segment-calculator/) here.

## When the pipe stays under the room

Building over a live drain is ordinary work done to an unforgiving detail, and the detail exists because the ground under a new extension moves and the pipe does not get to choose. Approved Document H1 sets out the protection: a granular surround around the pipe rather than dumped spoil, and short rocker lengths with a flexible joint at each end where the run passes through or beside a structure, so a small settlement is absorbed at a joint instead of cracking a barrel. Where cover above the pipe is thin, the Approved Document asks for it to be protected — concrete encasement worked in with the slab above, or a bridge over it. Take the cover threshold from the current edition of the document rather than from anybody's memory, including this page: it has moved between editions and it is the sort of figure that gets quoted long after it changed.

Bridging is the detail worth understanding, because it is what most agreements ask for and what most quotations describe badly. A reinforced concrete lintel or a small grade beam spans across the line of the drain and bears on undisturbed ground on both sides, well clear of the trench, so the load from the wall above travels around the pipe rather than onto it. The span, the depth and the reinforcement are an engineer's design under Eurocode 2 (BS EN 1992-1-1) or ACI 318 depending on where you are, and the bearing at each end is the part a groundworker can get wrong without noticing — a beam bearing on backfill is not a beam.

What does not happen is a chamber under a habitable room. On an undertaker's asset that is the refusal, plain. On a purely private drain inside your own boundary it is technically possible and still a bad idea, and if it is unavoidable then Approved Document H1's requirement for a mechanically fixed, airtight cover is the minimum, with a double sealed and screwed frame the practical answer. Anyone who has met a chamber under a kitchen floor knows the sequence: the seal is broken to clear a blockage, the seal is not properly remade, and the room tells the whole street about it.

Drawing, A protected drain crossing under an extension: _A drain run passing beneath a new single-storey extension, in section from the trench bottom upward: granular bedding and surround, the pipe itself, a reinforced concrete beam bridging the line onto undisturbed ground each side, compacted backfill above it, and the ground-bearing floor slab on top._

- **Ground-bearing floor slab**: poured last and measured as a rectangular prism; its thickness is set by the floor build-up, not by what is buried beneath it ([Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/))
- **Backfill and sub-base**: granular material compacted in lifts back to formation level, ordered loose and delivered by the tonne rather than by the finished cubic metre ([Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/))
- **Bridging beam over the line**: a reinforced concrete lintel or grade beam spanning the drain and bearing on undisturbed ground, so the wall load travels around the pipe and never onto it ([Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/))
- **The drain run**: laid to the gradient the standard sets, with a flexible joint each side of the structure so settlement is absorbed at a joint instead of cracking a barrel ([Drain Pipe Slope Calculator](https://craftquantities.com/calculators/plumbing-hvac/drain-pipe-slope-calculator/))
- **Granular bedding and surround**: single-size aggregate under and around the pipe, placed by hand and never compacted directly onto the crown until there is cover over it

Once the engineer has fixed the beam section, this is the pour. Length is the span plus the bearing at each end, and the width and depth come off the detail — a bridging beam is a short strip footing turned into a bridge, and it is ordered from the same rectangle. The page runs [Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/) here.

## The foundation beside the trench

A foundation next to a drain trench is a load and a void sitting close together, and the rule that keeps them apart is one of the more useful things in Approved Document H1. Where a trench runs within a metre of a foundation and goes deeper than it, the trench is filled with concrete up to the underside of the foundation. Where it runs further away than a metre, the concrete is taken to a level below the underside of the foundation equal to the distance between them less 150 mm. Read it once and it is obvious: it is a way of writing down a load spread so that the foundation never bears onto ground that has been dug out from beneath it, without asking a groundworker to draw a line at an angle in a hole.

That fill is a real quantity and it is regularly left out of a price, because it belongs to neither the drainage subcontractor nor the bricklayer. It is also concrete going into aggressive ground, which is where the specification stops being generic: BS 8500-1 sets the exposure classes and BRE Special Digest 1 gives the aggressive chemical environment classification that turns a soil test into a concrete specification, while in North America the sulfate exposure classes of ACI 318 do the same job. Foul ground beside an old sewer is a plausible place to find sulfates, and the soil test that answers it is cheap next to the pour.

Sequence matters as much as the mix. Dig, protect and backfill the drain before the foundation trench is opened wherever the programme allows, because a live drain excavated alongside an open foundation is two unsupported faces sharing one corner. Where the order has to be the other way round, the foundation goes in first and full depth, and the drain is threaded past it afterwards with the trench kept outside the line the Approved Document draws.

The fields are named for a slab, but a concrete trench fill is the same rectangular prism: length along the trench, width across it, and the depth the rule above gives you. Order it as one item on the ready-mix ticket rather than hoping the foundation load covers it. The page runs [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/) here.

## The hole, the bedding and what goes back in

The trench for a domestic diversion is deeper than its width and runs beside a house, which puts it squarely in the category that kills people. Support or batter is not optional because the job is short — in Great Britain the duty sits under the Construction (Design and Management) Regulations 2015 and is met with proprietary trench boxes or drag boxes on a run like this, and in the United States OSHA 29 CFR 1926 Subpart P sets out the protective system requirements by soil type. A trench alongside an existing foundation carries the extra problem that the foundation is a surcharge on the trench face, and the older and shallower the house, the more careful the answer has to be.

Bedding is where a competent job separates itself. BS EN 1610 governs construction and testing of drains and sewers in Europe and describes the bedding classes; ASTM D2321 is the equivalent installation practice for thermoplastic pipe in North America. The principle is common to both: the pipe is supported evenly along its whole length on granular material, never on the trench bottom and never on brick or timber packers, and the surround is worked in under the haunches by hand before anything heavier arrives. Compaction happens beside the pipe and above it once there is cover, never directly onto the crown.

The backfill is not the spoil. Clay dug out of a trench comes back as lumps with voids between them and it settles for years, which is how a strip of driveway over a diversion ends up as a trough. Import granular fill for the surround and, under anything trafficked, for the full depth. Then count both directions: the spoil leaves bigger than the hole it came from because it bulks, and the imported fill arrives loose and finishes compacted, so the tonnage ordered is more than the finished void. Skips and grab lorries fill by weight long before they fill by volume when what is in them is wet clay.

Length, width and depth of the trench, the outside diameter of the pipe, and the compaction allowance you are working to. What comes back is the loose material to order; the excavation figure in the breakdown is what has to leave the site, before any bulking allowance is added to it. The page runs [Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/) here.

## Proving it before it disappears

A diverted or protected drain gets tested twice: once before it is buried and once after the building is on top of it. In Europe the test is set out in BS EN 1610, which gives both an air test and a water test, and the air test is the one used on site because it is quick and because a failed air test is a cheap way to find out you have a problem. Air is also unforgiving of small things — a wet joint, a temperature swing, a plug seating badly — so a run that fails on air is usually retested on water before anyone starts digging up joints. The water test is the definitive one, and it needs the run filled to a stated head and left to stand while the drop is measured.

The other proof is visual. The pre-works CCTV survey established the condition of the pipe before your machine arrived, and the post-works survey shows what condition it is in now, both coded to the WRc Manual of Sewer Condition Classification so that two surveys done months apart by different contractors can actually be compared. That pair of surveys is what stands between you and a claim for a defect that was there in the first place, which is the main reason the undertaker asks for the first one and the main reason it is worth having even when nobody does.

Then close the paperwork while the people who did the work still remember it. The completed build over agreement, the two surveys, the test certificates, the engineer's beam detail and a measured record of where the diverted line actually runs — not where it was drawn — belong together in one file, handed to the homeowner and repeated in the property information the next time the house is sold. A buyer's solicitor will ask whether the extension over the sewer had consent. A file that answers in one document is worth a great deal more than a memory of a phone call with a water company.

For the water test you need to know what the run holds before you start filling it from a hose. Enter the inside diameter — not the nominal size — and the length under test, and you have the volume to fill, the volume to dispose of afterwards, and a sense of whether a bowser is needed. The page runs [Pipe Volume Calculator](https://craftquantities.com/calculators/plumbing-hvac/pipe-volume-calculator/) here.

## Have these measured before the application goes in

The workspace opens on the trench for the diversion sketched above — a 14 m run, 750 mm wide, 1.5 m deep to invert, around a 160 mm pipe, with a fifteen per cent compaction allowance — because that is the excavation the undertaker's conditions usually create. Replace the geometry with what you levelled, then carry the same inverts through the slope, chamber and concrete pages stacked beneath it. Switch the page to imperial first if that is how you measured; the seeded figures are metric.

- **Cover level and every invert, all from one bench mark**: Levelled from a mark that will survive the whole job, so the drainage levels and the extension setting out cannot drift apart between now and the slab.
- **Pipe diameter, material and the direction of every inlet**: An inlet you cannot account for from your own fixtures is a shared drain until a dye test says otherwise, and a shared drain has an owner who is not you.
- **The existing gradient, written as a percentage and as one in n**: It is the number the diversion is judged against. A run already close to its minimum fall cannot be lengthened around three sides of an extension.
- **Distance from the pipe to the nearest new foundation, and the depth of each**: Under a metre and over a metre are two different concrete fills under Approved Document H1, and the fill belongs to neither trade by default.
- **Depth from finished level to invert at the rebuilt chamber**: It sets the ring count, whether the structure is man-entry, and which BS EN 124 cover class the new position demands.
- **The undertaker's build-over criteria, in writing, dated**: Maximum diameter, maximum depth, what disqualifies a job from self-certification. These vary by company and are the one input nobody should take from a website.

Calculators for these quantities: [Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/), [Storm Drain Pipe Slope Calculator](https://craftquantities.com/calculators/materials-quantities/storm-drain-slope-calculator/), [Drain Pipe Slope Calculator](https://craftquantities.com/calculators/plumbing-hvac/drain-pipe-slope-calculator/), [Manhole Ring/Riser Segment Calculator](https://craftquantities.com/calculators/materials-quantities/manhole-ring-segment-calculator/), [Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/), [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/).

## Calculators this guide uses

- [Storm Drain Pipe Slope Calculator](https://craftquantities.com/calculators/materials-quantities/storm-drain-slope-calculator/)
- [Drain Pipe Slope Calculator](https://craftquantities.com/calculators/plumbing-hvac/drain-pipe-slope-calculator/)
- [Manhole Ring/Riser Segment Calculator](https://craftquantities.com/calculators/materials-quantities/manhole-ring-segment-calculator/)
- [Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- [Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- [Pipe Volume Calculator](https://craftquantities.com/calculators/plumbing-hvac/pipe-volume-calculator/)
- [Trench Sloping & Excavation Width Calculator](https://craftquantities.com/calculators/heavy-civil/trench-safety-slope-calculator/)
- [Road Subgrade Excavation Truck Fleet Calculator](https://craftquantities.com/calculators/materials-quantities/subgrade-excavation-truck-calculator/)
- [Footing Soil Bearing Pressure Checker](https://craftquantities.com/calculators/materials-quantities/footing-bearing-pressure-calculator/)
- [Isolated Spread Footing Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/spread-footing-sizing-calculator/)
- [Concrete Formwork Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-formwork-calculator/)
- [Culvert Pipe Length Calculator](https://craftquantities.com/calculators/heavy-civil/culvert-pipe-length-calculator/)

## See also

- [Trench Safety and Support](https://craftquantities.com/guides/how-to-work-safely-in-a-trench/)
- [Running Drain, Waste and Vent](https://craftquantities.com/guides/how-to-run-drain-waste-vent/)
- [Sizing a Soakaway From a Percolation Test](https://craftquantities.com/guides/how-to-size-a-soakaway/)
- [Setting Foundation Depth Near Trees on Shrinkable Clay](https://craftquantities.com/guides/how-to-found-a-building-near-trees/)

## Sources

- The Building Regulations 2010, Approved Document H: Drainage and waste disposal — H1 Foul water drainage (protection of pipes under and near buildings, recommended minimum gradients, access and cover requirements) and H4 Building over sewers
- The Building Regulations 2010, regulation 15 — consultation with the sewerage undertaker wherever paragraph H4 of Schedule 1 applies. Section 18 of the Building Act 1984, Building over sewer etc., is NOT cited: it was repealed on 1 April 2002 by the Building (Amendment) Regulations 2001 (SI 2001/3335), regulation 3(1), and H4 with regulation 15 is what took its place
- Water Industry Act 1991 — the sewerage undertaker's duties and the statutory map of public sewers
- The Water Industry (Schemes for Adoption of Private Sewers) Regulations 2011 — the transfer of private sewers and lateral drains on 1 October 2011
- Water UK, Design and Construction Guidance for foul and surface water sewers offered for adoption (the Codes for Adoption guidance that replaced Sewers for Adoption)
- BS EN 752, Drain and sewer systems outside buildings
- BS EN 1610, Construction and testing of drains and sewers — air and water tightness testing
- BS EN 124, Gully tops and manhole tops for vehicular and pedestrian areas — load classes
- BS EN 1917 and BS 5911-3 — precast concrete manholes, inspection chambers and ring sections
- ASTM C478, Standard Specification for Circular Precast Reinforced Concrete Manhole Sections; ASTM C443, gasketed joints; ASTM D2321, Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
- International Plumbing Code — slope of horizontal drainage piping, and trenching, excavation and backfill
- BS 8500-1, Concrete — complementary British Standard to BS EN 206, and BRE Special Digest 1, Concrete in aggressive ground
- BS EN 1992-1-1 (Eurocode 2) and ACI 318, Building Code Requirements for Structural Concrete — design of the bridging beam
- Construction (Design and Management) Regulations 2015; Confined Spaces Regulations 1997 with HSE ACOP L101, Safe work in confined spaces; OSHA 29 CFR 1926 Subpart P (Excavations) and Subpart AA (Confined Spaces in Construction)
- WRc, Manual of Sewer Condition Classification — the coding standard for pre-works and post-works CCTV surveys

---