# Hardstanding and paved area

> United Kingdom: hardstanding. Australia: hardstand. United States and Canada: (no single term). A made-up area of ground constructed to carry vehicles…

Page: https://craftquantities.com/glossary/hardstanding/ (glossary concept). This is the page's Markdown copy; the HTML page is the canonical version.

A made-up area of ground constructed to carry vehicles, plant or stored materials, as distinct from a footpath or a landscaped surface. Defined as much by what it is for as by what it is made of.

- 4 Markets
- No Same thing everywhere
- 3 Calculators

## What it is called, by market

One concept, four markets. Where a name means something else locally, the card says so rather than leaving you to find out on site.

- ### United Kingdom

  No local equivalent

  hardstanding

  also hard standing, hardstand, paved area, driveway

  A planning term as much as a construction one. Creating one between a house and the highway engages permitted development rules about permeability and surface water.
- ### Australia

  Close, not identical

  hardstand

  also hardstand area, paved area, crossover

  Common in civil and industrial usage for a made-up area taking plant or storage, with crossover naming the section between the property and the road.
- ### United States yours

  No local equivalent

  (no single term)

  also pad, apron, paved area, driveway, hardscape

  Named by function instead: a PAD for equipment, an APRON at a garage or an airfield, HARDSCAPE for the paved element of a landscape scheme. No word covers all of them.
- ### Canada

  No local equivalent

  (no single term)

  also pad, apron, hardscape, parking area

  As the United States, with frost depth governing the construction of anything that carries a vehicle.

## The governing standard, by market

- United Kingdom

  Approved Document H3 / BS 7533

  Rainwater drainage including surface water from paved areas, and the structural design of pavements constructed with modular units.
- United States

  ASCE 58 / ACI 330R

  Structural design of pavements, and guide for the design and construction of concrete parking lots.

## Calculators for this

Each works in either measurement system, and the terminology on the page follows whichever market you have selected.

- [Concrete Driveway Calculator](https://craftquantities.com/calculators/auto-utility/driveway-calculator/)
- [Paver Base & Sand Calculator](https://craftquantities.com/calculators/materials-quantities/paver-base-calculator/)
- [Gravel Driveway Calculator](https://craftquantities.com/calculators/auto-utility/gravel-driveway-calculator/)

## Frequently asked questions

**Why is paving a front garden a regulated act in Britain?**

Because an impermeable front garden sends rain into the drains instead of the ground, so permitted development allows one without planning permission only if it is permeable or drains to a permeable area within the property. Replacing a permeable front garden with an impermeable surface sends rainfall that used to soak into the ground into the drainage system instead, and enough of those in a catchment changes how it floods. British permitted development rules therefore allow a hardstanding to be created without planning permission only if the surface is permeable, or if the water is directed to a permeable area within the property rather than to the highway — above a modest threshold area. That makes the DRAINAGE strategy the planning question and the construction a consequence of it, which is the reverse of how most people approach it. A block-paved drive draining to the road is the common case that needs permission and rarely has it.

**What actually makes a surface permeable?**

The whole construction, not the top layer, and this is where permeable paving schemes most often fail. A permeable pavement works as a system: units with enlarged joints or voids, filled with a clean single-size aggregate that stays open; a laying course of the same; a sub-base of open-graded material that both spreads the load and stores water; and a subgrade able to accept it, or an outlet if it cannot. Using ordinary jointing sand instead of the specified clean grit closes the joints within a season. Using a conventional well-graded sub-base — which is designed to compact to a dense, interlocked layer with few voids — leaves nowhere for the water to go. So a permeable surface laid on a conventional base is an impermeable pavement with a permeable top, and it behaves like one in the first heavy rain.

**What thickness does it need, and what decides it?**

The subgrade and the traffic, in that order, and neither is the paving. The subgrade's strength — how much the ground beneath will deform under load — sets how much construction is needed above it to spread a wheel load to something it can take, and that is why the same driveway needs far more sub-base over soft clay than over gravel. Traffic then sets how much: a domestic car is a small fraction of the load a delivery lorry applies, and a hardstanding that will take a skip lorry or a motorhome is a different pavement from one taking a hatchback. The commonest domestic failure is neither: it is omitting the edge restraint, which lets the whole field creep sideways under braking and turning until the joints open and the surface loses its interlock.

## More terminology

The terms this one is usually confused with, and the rest of the set.

- [Asphalt / tarmac / blacktop](https://craftquantities.com/glossary/tarmac/)
- [Plasterboard / drywall](https://craftquantities.com/glossary/plasterboard/)
- [Timber / lumber](https://craftquantities.com/glossary/timber/)
- [Cladding / siding](https://craftquantities.com/glossary/cladding/)
- [Gutter / eavestrough](https://craftquantities.com/glossary/gutter/)

---
Source: https://craftquantities.com/glossary/hardstanding/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.