# Bulking, compaction and weight

> Loose volume from swell, compacted volume from shrinkage, bulked volume from a factor and tonnage from density: earthwork and aggregate states.

Page: https://craftquantities.com/formulas/bulking-and-compaction/ (formula reference). This is the page's Markdown copy; the HTML page is the canonical version.

Soil, rubble and aggregate have three volumes, in the ground, on the truck and placed and rolled, and they are sold by weight. The equations below convert between the volumes with a percentage or a factor, and from volume to mass with a density.

- 4 Formulas
- 3 Calculators that run them
- 10 Test vectors

- [This family as JSON](https://craftquantities.com/formulas/bulking-and-compaction.json)
- [All formula families](https://craftquantities.com/formulas/)

## Loose volume from swell

`loose-volume-from-swell`

The volume dug material occupies once loosened, from its bank volume.

V L=V B×(1+s 100)

_V_L = V_B × (1 + s / 100)_

### Symbols

**Loose volume from swell: Symbols**

| Symbol | Meaning | Metric | Imperial |
|---|---|---|---|
| _V_L | Loose (haul) volume | m³ | ft³ |
| _V_B | Bank volume, in the ground | m³ | ft³ |
| _s_ | Swell, per cent | % | % |

#### Worked example

A pinned test vector of the [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/).

- _V_B = 100 m³ (3,531.47 ft³) (Bank volume, in the ground)
- _s_ = 25% (Swell, per cent)

gives _V_L = **125 m³ (4,414.33 ft³)**. The calculator's own compute function returns 125 m³.

### Calculators that run it

- [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) — its headline answer

### Test vectors

**Loose volume from swell: Test vectors**

| Calculator | Inputs | Formula | Calculator returns |
|---|---|---|---|
| [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) | _V_B = 100 · _s_ = 25 | 125 | 125 m³ pinned |
| [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) | _V_B = 250 · _s_ = 30 | 325 | 325 m³ pinned |

## Compacted volume from shrinkage

`compacted-volume-from-shrinkage`

The volume the same material occupies once placed and compacted.

V C=V B×(1+c 100)

_V_C = V_B × (1 + c / 100)_

### Symbols

**Compacted volume from shrinkage: Symbols**

| Symbol | Meaning | Metric | Imperial |
|---|---|---|---|
| _V_C | Compacted volume | m³ | ft³ |
| _V_B | Bank volume, in the ground | m³ | ft³ |
| _c_ | Shrinkage, per cent (negative when the volume falls) | % | % |

#### Worked example

A pinned test vector of the [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/).

- _V_B = 100 m³ (3,531.47 ft³) (Bank volume, in the ground)
- _c_ = -10% (Shrinkage, per cent (negative when the volume falls))

gives _V_C = **90 m³ (3,178.32 ft³)**. The calculator's own compute function returns 90 m³.

### Calculators that run it

- [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) — its breakdown line “Compacted (recompacted) volume”

### Test vectors

**Compacted volume from shrinkage: Test vectors**

| Calculator | Inputs | Formula | Calculator returns |
|---|---|---|---|
| [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) | _V_B = 100 · _c_ = -10 | 90 | 90 m³ |
| [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/) | _V_B = 250 · _c_ = -15 | 212.5 | 212.5 m³ |

## Bulked volume from a factor

`bulked-volume-from-factor`

The loose volume of demolition debris from its solid volume and a swell factor.

V L=F×V B

_V_L = F × V_B_

### Symbols

**Bulked volume from a factor: Symbols**

| Symbol | Meaning | Metric | Imperial |
|---|---|---|---|
| _V_L | Bulked volume | m³ | ft³ |
| _V_B | Solid volume in place | m³ | ft³ |
| _F_ | Swell factor (1.3 for a 30 % swell) | — | — |

#### Worked example

A pinned test vector of the [Demolition Bulk Volume Swell Calculator](https://craftquantities.com/calculators/materials-quantities/demolition-bulk-volume-swell-calculator/).

- _V_B = 15.2911 m³ (540 ft³) (Solid volume in place)
- _F_ = 1.3 (Swell factor (1.3 for a 30 % swell))

gives _V_L = **19.8784 m³ (702 ft³)**. The calculator's own compute function returns 26 yd³.

### Calculators that run it

- [Demolition Bulk Volume Swell Calculator](https://craftquantities.com/calculators/materials-quantities/demolition-bulk-volume-swell-calculator/) — its headline answer

### Test vectors

**Bulked volume from a factor: Test vectors**

| Calculator | Inputs | Formula | Calculator returns |
|---|---|---|---|
| [Demolition Bulk Volume Swell Calculator](https://craftquantities.com/calculators/materials-quantities/demolition-bulk-volume-swell-calculator/) | _V_B = 15.2911 · _F_ = 1.3 | 19.8784 | 26 yd³ pinned |
| [Demolition Bulk Volume Swell Calculator](https://craftquantities.com/calculators/materials-quantities/demolition-bulk-volume-swell-calculator/) | _V_B = 11.4683 · _F_ = 1.5 | 17.2025 | 22.5 yd³ pinned |

## Mass from volume and density

`mass-from-volume-and-density`

The mass of a material from its volume and its density in the same state.

m=V×ρ

_m = V × ρ_

### Symbols

**Mass from volume and density: Symbols**

| Symbol | Meaning | Metric | Imperial |
|---|---|---|---|
| _m_ | Mass | kg | lb |
| _V_ | Volume | m³ | ft³ |
| _ρ_ | Density in the state measured | kg/m³ | lb/ft³ |

#### Worked example

A pinned test vector of the [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/).

- _V_ = 30 m³ (1,059.44 ft³) (Volume)
- _ρ_ = 1,700 kg/m³ (106.128 lb/ft³) (Density in the state measured)

gives _m_ = **51,000 kg (112,436 lb)**. The calculator's own compute function returns 51 t.

### Calculators that run it

- [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/) — its headline answer

### Test vectors

**Mass from volume and density: Test vectors**

| Calculator | Inputs | Formula | Calculator returns |
|---|---|---|---|
| [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/) | _V_ = 30 · _ρ_ = 1,700 | 51,000 | 51 t pinned |
| [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/) | _V_ = 70 · _ρ_ = 1,800 | 126,000 | 126 t pinned |
| [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/) | _V_ = 30 · _ρ_ = 2,200 | 66,000 | 66 t pinned |
| [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/) | _V_ = 0.764555 · _ρ_ = 2,195.1 | 1,678.27 | 1.67827 t pinned |

Using the equations

## How to read them

Swell is a percentage added to the bank volume; a 25 % swell turns 100 m³ in the ground into 125 m³ to haul.

Shrinkage is written here as a negative percentage of the bank volume, so −10 % leaves 90 m³ once compacted.

A swell factor is the same idea as a multiplier: 1.3 is a 30 % swell. Demolition tables usually give the factor, earthworks tables the percentage.

Use the density of the state you measured. A compacted base measured in place needs the compacted density; using a loose figure makes the order light.

Read every symbol in one column: the equation holds in either system as long as the units are not mixed.

Each row is a registry test vector, run through the equation and through the calculator. Only rows on which the two agree are published.

These are quantity equations, not design checks. Nothing here sizes a member or confirms that a structure is safe; that is for the engineer or building official responsible for the work.

Limits

## Where they stop describing the job

The factors are properties of a particular material at a particular moisture; a table figure is an average, and site testing replaces it.

- Reinforced concrete does not break into loose pieces until the bar is cut, so no swell factor describes it before then.
- Moisture changes the mass of a load without changing what it builds. Suppliers weigh what they deliver, water and all.

Sources

## What the calculators cite

The citations of the calculators that run these equations, as each calculator states them.

1. Standard earthwork volume states: loose (haul) volume = bank volume x (1 + swell%); compacted volume = bank volume x (1 + shrinkage%), where shrinkage is typically expressed as a negative percentage Cited by: [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/)
2. Bulked volume = In-place volume × Swell (bulking) Factor. Broken masonry and concrete occupy significantly more volume once demolished due to voids created by fracturing — typical swell factors commonly used in demolition estimating: concrete ~1.3x, CMU block ~1.4x, brick masonry ~1.5x, natural stone ~1.5x. These are industry estimating conventions (mirroring the same swell/bulking concept used in this site's Soil Swell & Shrinkage calculator), not a single universal engineering constant — actual swell varies with demolition method and debris size.Cited by: [Demolition Bulk Volume Swell Calculator](https://craftquantities.com/calculators/materials-quantities/demolition-bulk-volume-swell-calculator/)
3. Mass = area x thickness x in-place compacted density Cited by: [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)
4. Wisconsin DOT Standard Specifications for Highway and Structure Construction (2025), §305.4(2): completed in-place dense-graded base converts at 1.85 US tons per cubic yard, about 2,195 kg/m³ (137 pcf)Cited by: [Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)

Data

## Cite or reuse this family

The same equations, symbols, calculators and vectors as one JSON file.

[https://craftquantities.com/formulas/bulking-and-compaction.json](https://craftquantities.com/formulas/bulking-and-compaction.json)

The text and the data of the formula library are published under the Creative Commons Attribution 4.0 licence (CC BY 4.0): reuse them, in any medium and for any purpose, with a credit to Craft Quantities and a link to the page.

Cite as: Craft Quantities, “Bulking, compaction and weight”, https://craftquantities.com/formulas/bulking-and-compaction/

---