# Real jobs, estimated end to end

> 18 construction jobs estimated end to end — decks, roofs, slabs, patios — with each measurement, each calculator in order and 146 computed figures.

Page: https://craftquantities.com/examples/ (worked example). This is the page's Markdown copy; the HTML page is the canonical version.

A deck, a roof, a slab, a bathroom: each job from the first tape measurement to the bill of materials, with the calculators run in the order the work is done and every decision shown — the waste allowed, the reason for it, and where the estimate is most likely to be off.

- 18 Jobs worked through
- 158 Takeoff steps, in order
- 146 Figures computed

## Measured first

Each page opens with what was measured and how — and the mistake that makes each measurement wrong — because every quantity after it is only as good as the tape.

## Taken off in order

The steps run in the order the work is done, and each says what it needs from the one before. Getting the order wrong is how a list looks complete and is short in two places.

## Honest about the error

Every page ends with where its estimate is most likely to be wrong, which way, and why — the mechanism, not an invented overrun, because these jobs are modelled rather than recorded.

6 jobs

## Bathrooms and interiors

Where the background decides the product and the finished thickness decides the order, the tile layout decides the waste, and the smallest lines — beads, trims, edge profiles — are bought in whole lengths rather than metres.

- ### [Bathroom gutted and retiled](https://craftquantities.com/examples/bathroom-gutted-and-retiled/)

  UK · metric first

  A 3 × 4 m bathroom, gutted to studs, reboarded and retiled

  9 steps · 7 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/bathroom-gutted-and-retiled/)
- ### [A room replastered](https://craftquantities.com/examples/room-replastered/)

  UK · metric first

  A 4 × 3 m room replastered — board and masonry walls, ceiling included

  6 steps · 6 figures computed · 4 places it can be wrong

  [See every step](https://craftquantities.com/examples/room-replastered/)
- ### [Bedroom repaint](https://craftquantities.com/examples/bedroom-repainted/)

  US · imperial first

  A 12 × 14 ft (3.7 × 4.3 m) bedroom with an 8 ft (2.4 m) ceiling repainted: walls from deep charcoal to off-white, ceiling and trim white like for like

  7 steps · 7 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/bedroom-repainted/)
- ### [Vinyl plank floor](https://craftquantities.com/examples/vinyl-plank-floor-laid/)

  US · imperial first

  Luxury vinyl plank laid through a 15 × 20 ft (4.6 × 6.1 m) living room and a 4 × 12 ft (1.2 × 3.7 m) hallway on a concrete slab, as a floating floor broken at the hallway neck

  7 steps · 7 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/vinyl-plank-floor-laid/)
- ### [Basement room drywall](https://craftquantities.com/examples/basement-room-drywalled/)

  US · imperial first

  A 12 × 20 ft (3.66 × 6.10 m) basement rec room hung and finished in drywall — 8 ft (2.44 m) walls, a soffit boxing the beam and duct down its length and a Level 4 finish

  10 steps · 10 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/basement-room-drywalled/)
- ### [Stud partition with a door](https://craftquantities.com/examples/stud-partition-with-a-door/)

  UK · metric first

  A 3.6 m (11.8 ft) timber stud partition, 2.4 m (7.9 ft) high, with a door, insulated for sound, boarded both sides and skimmed

  10 steps · 10 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/stud-partition-with-a-door/)

3 jobs

## Roofs and lofts

Where the largest quantity is decided by the smallest one — the pitch sets the true area, and the outlets, eaves and ridge set everything laid on it — and where a loft's target is a performance figure, not a thickness.

- ### [Flat roof recovered](https://craftquantities.com/examples/flat-roof-recovered/)

  UK · metric first

  A 40 m² (431 sq ft) flat roof stripped and recovered, warm-roof build-up

  8 steps · 3 figures computed · 4 places it can be wrong

  [See every step](https://craftquantities.com/examples/flat-roof-recovered/)
- ### [Shingle roof replacement](https://craftquantities.com/examples/asphalt-shingle-roof-replaced/)

  US · imperial first

  A 30 × 40 ft (9.14 × 12.19 m) gable roof at 6/12, torn off to the deck and reroofed in architectural asphalt shingles

  11 steps · 10 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/asphalt-shingle-roof-replaced/)
- ### [Loft insulation top up](https://craftquantities.com/examples/loft-insulation-topped-up/)

  UK · metric first

  A 7 × 9 m (23 × 29.5 ft) loft topped up from 100 mm to 270 mm (3.9 to 10.6 in) of mineral wool, with a boarded storage area and the cistern pipework lagged

  7 steps · 7 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/loft-insulation-topped-up/)

3 jobs

## Groundworks, slabs and driveways

Where the dig depth is a sum rather than a choice, and where one material cannot be topped up an hour later.

- ### [Garden room slab](https://craftquantities.com/examples/garden-room-slab/)

  UK · metric first

  A 6 × 4 m ground-bearing slab for a garden room, setting out to curing

  9 steps · 7 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/garden-room-slab/)
- ### [Concrete driveway replaced](https://craftquantities.com/examples/concrete-driveway-replaced/)

  US · imperial first

  A 12 × 50 ft (3.7 × 15.2 m) single-car concrete driveway broken out and repoured at 4 in (102 mm) on a compacted gravel base

  10 steps · 10 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/concrete-driveway-replaced/)
- ### [Gravel driveway](https://craftquantities.com/examples/gravel-driveway-laid/)

  UK · metric first

  A 6 × 10 m (19.7 × 32.8 ft) gravel driveway on 150 mm (5.9 in) of open-graded crushed stone over a geotextile, with a block edge

  8 steps · 8 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/gravel-driveway-laid/)

3 jobs

## Patios and garden walls

Where the levels come before the materials: the fall, the base and the footing decide the order long before the first paver or brick is counted.

- ### [Paver patio](https://craftquantities.com/examples/paver-patio-laid/)

  US · imperial first

  A 12 × 16 ft (3.7 × 4.9 m) concrete paver patio against the house, on 4 in (102 mm) of compacted base and 1 in (25 mm) of bedding sand, with polymeric sand joints

  10 steps · 10 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/paver-patio-laid/)
- ### [Block retaining wall](https://craftquantities.com/examples/block-retaining-wall-built/)

  US · imperial first

  A 40 ft (12.19 m) segmental block retaining wall, 3 ft (0.91 m) exposed plus one buried course, with drainage stone and a perforated heel drain laid to fall

  11 steps · 11 figures computed · 7 places it can be wrong

  [See every step](https://craftquantities.com/examples/block-retaining-wall-built/)
- ### [Brick garden wall](https://craftquantities.com/examples/brick-garden-wall-built/)

  UK · metric first

  A 10 m (32 ft 10 in) one-brick garden wall, its brickwork 1.2 m (3 ft 11 in) out of the ground on average under the coping, on a concrete strip footing stepped down a sloping garden

  8 steps · 8 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/brick-garden-wall-built/)

2 jobs

## Decks and fences

Where the frame is the quantity nobody sees: the spans, posts and footings are taken off first, and the boards and pickets follow from them.

- ### [Attached deck](https://craftquantities.com/examples/attached-deck-built/)

  US · imperial first

  A 16 × 12 ft (4.9 × 3.7 m) pressure-treated deck, 3 ft (0.9 m) off grade and ledgered to the house, with one stair and a railing on three sides

  11 steps · 10 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/attached-deck-built/)
- ### [Privacy fence](https://craftquantities.com/examples/privacy-fence-built/)

  US · imperial first

  150 ft (45.7 m) of 6 ft (1.83 m) wood privacy fence on 4x4 posts at 8 ft (2.44 m) centres, with one walk gate, on a gently sloping yard

  7 steps · 7 figures computed · 6 places it can be wrong

  [See every step](https://craftquantities.com/examples/privacy-fence-built/)

1 job

## Circuits

Where the load decides everything after it: the breaker, the conductor, the voltage drop and the conduit each take the previous answer as their input.

- ### [Electric vehicle charger circuit](https://craftquantities.com/examples/ev-charger-circuit-installed/)

  US · imperial first

  A 48 A Level 2 EV charger, hardwired on a new 240 V circuit run 45 ft (13.72 m) in 3/4 in EMT from a 200 A panel to an attached garage

  9 steps · 8 figures computed · 5 places it can be wrong

  [See every step](https://craftquantities.com/examples/ev-charger-circuit-installed/)

## Just one calculator, one job?

Some searches are narrower than a whole takeoff: how many yards for one slab, how many sheets for one room. The [calculator examples, by trade](https://craftquantities.com/examples/calculators/) run a single job through a single calculator, with its working shown step by step and a link that opens the calculator with the same inputs.

## A whole house rather than one job?

Six houses are taken off whole in the [House Estimator](https://craftquantities.com/house-estimator/), footing to roof, each with its plan to scale and what changes if one choice is swapped.

- [A ranch for a cold winter](https://craftquantities.com/house-estimator/cold-climate-ranch/)One storey, 2×4 walls, batts, vinyl, ice-dam eaves
- [A two-storey house in advanced framing](https://craftquantities.com/house-estimator/two-storey-advanced-framing/)2×6 at 24 in, mineral wool, plywood, fibre cement
- [A concrete block house for a hot coast](https://craftquantities.com/house-estimator/concrete-block-house/)Block walls, bond beams, a low roof, no ice-dam strip
- [A small mountain cabin](https://craftquantities.com/house-estimator/mountain-cabin/)Spray foam, board and batten, a 12 in 12 roof
- [A British timber-frame house](https://craftquantities.com/house-estimator/uk-timber-frame-house/)140 mm studs, a vapour control layer, larch cladding
- [A two-storey block townhouse](https://craftquantities.com/house-estimator/two-storey-block-townhouse/)Block on both floors, a bond beam at each level

Your own job

## Run the same chain with your measurements

A takeoff asks for each measurement once and runs every calculator a job needs; My Project turns the results into a bill of materials you can export.

- [Job takeoffs](https://craftquantities.com/build/)
- [Every calculator](https://craftquantities.com/calculators/)

- Figures that are re-run, not typed

  Each page's numbers come from the calculator its step names, checked every build.
- Both unit systems

  Modelled in one market's units, with the other system in brackets throughout.
- No prices

  Quantities only: a price is yours to enter, and it never leaves your device.

## Frequently asked questions

**What is a worked construction estimate?**

One job taken from the first measurement to the bill of materials, in the order the work is done: what was measured and how, which calculator produces each quantity and what it needs from the step before, the waste allowed on each material and why, and where the estimate is most likely to be wrong.

**Are these real jobs?**

No, and each page says so at the top. They are modelled: every figure is computed by the calculator the step names and re-run whenever the site is built, but no job was carried out, so nothing is presented as a measured overrun.

**Can I run the same takeoff with my own measurements?**

Yes. Every step links the calculator it uses, and most jobs also exist as a takeoff that asks for each measurement once and runs the whole chain; the results can be sent to My Project and exported as a bill of materials.

**Why are some examples in feet and others in metres?**

Each job is modelled for one market — the United States in imperial units, the United Kingdom in metric — because product sizes and codes differ, not just units. Every figure gives the other system in brackets.

---
Source: https://craftquantities.com/examples/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.