# Check a strip footing quote

> Paste a strip footing quote and read it against your own measurements: the lines it leaves out, the ones it adds, the quantities outside the computed…

Page: https://craftquantities.com/check/strip-footing-quote/ (quote check). This is the page's Markdown copy; the HTML page is the canonical version.

Each line read against your measurements: 3 lines, 5 measurements. Quantities, never prices.

Step 1

## Your measurements

Measured this job on the [strip footing takeoff](https://craftquantities.com/build/strip-footing/)? Send it to My Project, or save a setup, and these boxes fill in one press.

Worked from Footing length 98 ft · Footing width 2 ft · Footing depth 11.8 in · Trench depth 3 ft · Wall thickness below ground 7.75 in (US customary) / Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm (metric)

How to take each of these, and what each one feeds, is under the same field on the [strip footing takeoff](https://craftquantities.com/build/strip-footing/).

Step 2 · Your quote

## The strip footing quote you were given

Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.

Nothing you paste or open leaves this device.

or one the job needs:

Step 3 · The reading

## What the quote says, against the job

Strip footing · Footing length 98 ft · Footing width 2 ft · Footing depth 11.8 in · Trench depth 3 ft · Wall thickness below ground 7.75 in (US customary) / Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm (metric)

- What it leaves out

  Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
- What it adds

  Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
- What sits outside the range

  Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
- What to ask

  One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.

Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.

### Outside what this takeoff measures

5

Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the [takeoff](https://craftquantities.com/build/strip-footing/).

- The depth the ground actually requires
- The reinforcement schedule
- Formwork, which a trench-poured footing may not need and a stepped or above-ground one certainly does
- Muck-away
- Dewatering, and any ground improvement the inspection turns out to require

No quote read yet

[Open the takeoff](https://craftquantities.com/build/strip-footing/)

Paste a quote

## The job

Footing length 98 ft · Footing width 2 ft · Footing depth 11.8 in · Trench depth 3 ft · Wall thickness below ground 7.75 in (US customary) / Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm (metric)

## What the job needs

For these measurements, by the site’s calculators.

_US customary:_

- Continuous Footing / Grade Beam Volume 7.46–8.17 yd³
- Trench Excavation & Backfill Volume 11.4 yd³
- Rebar 19 x 20 ft sticks

_metric:_

- Continuous Footing / Grade Beam Volume 5.67–6.21 m³
- Trench Excavation & Backfill Volume 8.28 m³ (loose)
- Rebar 10 x 12 m sticks

More than one quote

## Level the quotes side by side

Two to six strip footing quotes, each read against this job: included, left out, excluded or added, line by line.

Kept on this device**Figures**The page's opening**Units**Imperial Quantities only, never prices

## How the quote is read

Each line of a strip footing quote is matched to the line of the job it names, or marked as something the [Strip footing takeoff](https://craftquantities.com/build/strip-footing/) does not measure — labour, removal, hire, fees, or anything else.

The job’s own figures come from 5 measurements — footing length, footing width, footing depth, trench depth, wall thickness below ground — run through the same calculators as the takeoff, so the two give the same figure for the same job.

## Reading a strip footing quote

Footing quotes are dominated by the digging and the concrete, and the concrete volume should allow for a trench dug wider or deeper than drawn.

The backfill here is a loose volume, which is more than the hole it fills. Taking the spoil away is often the largest line nobody mentioned, so whether it is included is worth settling.

## Three steps

1. Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
2. Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
3. Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.

The reference

## Every line the reading looks for

For Footing length 98 ft · Footing width 2 ft · Footing depth 11.8 in · Trench depth 3 ft · Wall thickness below ground 7.75 in (US customary) / Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm (metric). Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.

_US customary:_

- Continuous Footing / Grade Beam Volume

  7.46–8.17 yd³

  7.46 at 5% waste factor, 8.17 at 15%.

  [Open the Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- Trench Excavation & Backfill Volume

  11.4 yd³

  One figure, with the loose-volume allowance the material needs already inside it at 15%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Rebar

  19 x 20 ft sticks

  One figure, with the lap-splice allowance the material needs already inside it at 15%.

  [Open the Rebar Calculator](https://craftquantities.com/calculators/materials-quantities/rebar-calculator/)

_metric:_

- Continuous Footing / Grade Beam Volume

  5.67–6.21 m³

  5.67 at 5% waste factor, 6.21 at 15%.

  [Open the Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- Trench Excavation & Backfill Volume

  8.28 m³ (loose)

  One figure, with the loose-volume allowance the material needs already inside it at 15%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Rebar

  10 x 12 m sticks

  One figure, with the lap-splice allowance the material needs already inside it at 15%.

  [Open the Rebar Calculator](https://craftquantities.com/calculators/materials-quantities/rebar-calculator/)

## How the ranges are taken

Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.

A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.

## What a reading like this cannot see

- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.

The full takeoff

## Every quantity for this job, with its working

The Strip footing takeoff runs the same calculators on the same measurements and shows what sits under each line here.

- [Open the takeoff](https://craftquantities.com/build/strip-footing/)
- [Every quote check](https://craftquantities.com/check/)

- Base, allowance, order

  Each line's quantity before and after its allowance, and what to buy.
- Every allowance editable

  Change a waste figure and the order follows, with its source named.
- Into a project

  Add the whole job to a workspace with your own prices.

## Frequently asked questions

**What quantities does a strip footing job need?**

It depends on the measurements, so this page asks for yours. At the size it opens on — Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm — the lines come to: Continuous Footing / Grade Beam Volume, 5.67–6.21 m³; Trench Excavation & Backfill Volume, 8.28 m³ (loose); Rebar, 10 x 12 m sticks. In imperial units — Footing length 98 ft · Footing width 2 ft · Footing depth 11.8 in · Trench depth 3 ft · Wall thickness below ground 7.75 in — they come to: Continuous Footing / Grade Beam Volume, 7.46–8.17 yd³; Trench Excavation & Backfill Volume, 11.4 yd³; Rebar, 19 x 20 ft sticks.

**Which line on a strip footing quote varies the most?**

The Continuous Footing / Grade Beam Volume: 5.67–6.21 m³ for a job measured Footing length 30 m · Footing width 0.6 m · Footing depth 300 mm · Trench depth 0.9 m · Wall thickness below ground 200 mm, depending on the waste factor allowed, from 5% to 15%.

**What does a strip footing quote often leave out?**

The reading names every line of the job that nothing on the quote reads as — any of the 3 lines the takeoff measures. The takeoff also lists 5 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started.

**Can I paste the quote exactly as it came?**

Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.

**Does this check the price as well?**

No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.

---