# Check a loft room quote

> Paste a loft room quote and read it against your own measurements: the lines it leaves out, the ones it adds, the quantities outside the computed range…

Page: https://craftquantities.com/check/loft-room-rooflights-quote/ (quote check). This is the page's Markdown copy; the HTML page is the canonical version.

Each line read against your measurements: 15 (US customary) / 14 (metric) lines, 11 measurements. Quantities, never prices.

Step 1

## Your measurements

Measured this job on the [loft room with rooflights takeoff](https://craftquantities.com/build/loft-room-rooflights/)? Send it to My Project, or save a setup, and these boxes fill in one press.

Worked from Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 (metric)

How to take each of these, and what each one feeds, is under the same field on the [loft room with rooflights takeoff](https://craftquantities.com/build/loft-room-rooflights/).

Step 2 · Your quote

## The loft room quote you were given

Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.

Nothing you paste or open leaves this device.

or one the job needs:

Step 3 · The reading

## What the quote says, against the job

Loft room · Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 (metric)

- What it leaves out

  Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
- What it adds

  Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
- What sits outside the range

  Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
- What to ask

  One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.

Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.

### Outside what this takeoff measures

7

Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the [takeoff](https://craftquantities.com/build/loft-room-rooflights/).

- The structure
- The rooflights themselves, their flashing kits, blinds and any electric opener
- The floor deck, listed as work
- Ventilation of the cold voids behind the knee walls and over the flat ceiling, and insulation of a gable end wall facing outside
- Tiles, slates and battens round each rooflight beyond making them good, and any re-covering of the slopes
- A shower room or bathroom in the loft, its drainage and the heating extended to the room beyond a radiator listed as work
- Undercoat and gloss (trim enamel) on the new woodwork

No quote read yet

[Open the takeoff](https://craftquantities.com/build/loft-room-rooflights/)

Paste a quote

## The job

Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 (metric)

## What the job needs

For these measurements, by the site’s calculators.

_US customary:_

- Studs for the two knee walls 39 studs
- Boards between and under the sloped rafters 6–7 sheets (4x8 ft)
- Batts in the knee walls 4 packages
- Sound insulation between the floor joists 7 packages
- Insulation over the flat ceiling 4 packages
- Plasterboard (drywall) on the ceiling, slopes and reveals 12–13 sheets
- Plasterboard (drywall) on the walls 12–13 sheets
- Joint compound for taping and filling every board 2 x 4.5 gal boxes
- Paper joint tape over every board 420–460 ft
- Mist coat or primer on the ceiling, slopes and reveals 0.88–1.02 gal
- Mist coat or primer on the walls 0.88–1.01 gal
- Skirting (baseboard)69.3–76 linear ft
- Ceiling, slopes and reveals, two coats 1.77–2.03 gal
- Walls, two coats 1.77–2.03 gal
- Skip (dumpster) for the strip-out at least 5.29 yd³

_metric:_

- Studs for the two knee walls 39 studs
- Boards between and under the sloped rafters 7 sheets (2400x1200 mm)
- Batts in the knee walls 4 packages
- Sound insulation between the floor joists 6–7 packages
- Insulation over the flat ceiling 3–4 packages
- Plasterboard (drywall) on the ceiling, slopes and reveals 12–13 sheets
- Plasterboard (drywall) on the walls 12–13 sheets
- Skim over every board 170–186 kg
- Mist coat or primer on the ceiling, slopes and reveals 3.24–3.72 L
- Mist coat or primer on the walls 3.22–3.71 L
- Skirting (baseboard)20.9–22.9 m
- Ceiling, slopes and reveals, two coats 6.48–7.45 L
- Walls, two coats 6.44–7.41 L
- Skip (dumpster) for the strip-out at least 3.96 m³

More than one quote

## Level the quotes side by side

Two to six loft room quotes, each read against this job: included, left out, excluded or added, line by line.

Kept on this device**Figures**The page's opening**Units**Imperial Quantities only, never prices

## How the quote is read

Each line of a loft room quote is matched to the line of the job it names, or marked as something the [Loft room with rooflights takeoff](https://craftquantities.com/build/loft-room-rooflights/) does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.

The job’s own figures come from 11 measurements — loft length, wall to wall, new floor, knee wall to knee wall, knee wall height, floor to flat ceiling, sloped ceiling on each side, on plan, roof slope factor, rooflights (roof windows), rooflight width, each, rooflight height, each, reveal depth round each rooflight, doors into the room — run through the same calculators as the takeoff, so the two give the same figure for the same job.

## Reading a loft room quote

A loft room quote rests on the structure nobody sees once the room is finished: the new floor joists, a beam put in where a purlin or a prop comes out, and the trimming round the stair and each rooflight. Worth asking who designs them, whether the engineer's fee and the building control or permit fees are in the price, and whether the headroom over the stair and in the room was measured before the figure was written.

Rooflights are usually priced by the unit, each with its flashing kit. Worth seeing the make and size of every one named, whether they are fitted from inside or need a scaffold, whether the tiles or slates round them are made good, and whether the reveals are lined, insulated and finished with the room or left for another trade.

Worth confirming the finishing lines one by one: the insulation, where each layer goes and how thick it is, the boards and whether they are skimmed or taped, the decoration, the skirting, the floor finish, the door, the handrail, the alarms and the electrics, and whether the strip-out and the skip are included.

## Three steps

1. Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
2. Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
3. Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.

The reference

## Every line the reading looks for

For Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 (metric). Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.

_US customary:_

- Studs for the two knee walls

  39 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Boards between and under the sloped rafters

  6–7 sheets (4x8 ft)

  6 at 5% cutting waste, 7 at 15%.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Batts in the knee walls

  4 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Sound insulation between the floor joists

  7 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Insulation over the flat ceiling

  4 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Plasterboard (drywall) on the ceiling, slopes and reveals

  12–13 sheets

  12 at 5% waste allowance, 13 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Plasterboard (drywall) on the walls

  12–13 sheets

  12 at 5% waste allowance, 13 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Joint compound for taping and filling every board

  2 x 4.5 gal boxes

  The same at 5% pan and sanding loss and at 15%, once rounded to what is bought.

  [Open the Drywall Joint Compound Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-compound-calculator/)
- Paper joint tape over every board

  420–460 ft

  420 at 5% waste allowance, 460 at 15%.

  [Open the Drywall Joint Tape Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-tape-calculator/)
- Mist coat or primer on the ceiling, slopes and reveals

  0.88–1.02 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.88 net, 1.02 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Mist coat or primer on the walls

  0.88–1.01 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.88 net, 1.01 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skirting (baseboard)

  69.3–76 linear ft

  69.3 at 5% cutting waste, 76 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Ceiling, slopes and reveals, two coats

  1.77–2.03 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.77 net, 2.03 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Walls, two coats

  1.77–2.03 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.77 net, 2.03 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skip (dumpster) for the strip-out

  at least 5.29 yd³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Dust sheets in the rooms below

  5 items

  Worked out, not compared with a quote

  Dust sheets and tape together, which a quote prices as preparation rather than listing.

  [Open the Masking and Protection Materials Calculator](https://craftquantities.com/calculators/renovation-construction/masking-and-protection-calculator/)

_metric:_

- Studs for the two knee walls

  39 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Boards between and under the sloped rafters

  7 sheets (2400x1200 mm)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Batts in the knee walls

  4 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Sound insulation between the floor joists

  6–7 packages

  6 at 5% waste allowance, 7 at 15%.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Insulation over the flat ceiling

  3–4 packages

  3 at 5% waste allowance, 4 at 15%.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Plasterboard (drywall) on the ceiling, slopes and reveals

  12–13 sheets

  12 at 5% waste allowance, 13 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Plasterboard (drywall) on the walls

  12–13 sheets

  12 at 5% waste allowance, 13 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Skim over every board

  170–186 kg

  170 at 5% waste allowance, 186 at 15%.

  [Open the Skim Coat Plaster Calculator](https://craftquantities.com/calculators/materials-quantities/skim-coat-plaster-calculator/)
- Mist coat or primer on the ceiling, slopes and reveals

  3.24–3.72 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.24 net, 3.72 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Mist coat or primer on the walls

  3.22–3.71 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.22 net, 3.71 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skirting (baseboard)

  20.9–22.9 m

  20.9 at 5% cutting waste, 22.9 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Ceiling, slopes and reveals, two coats

  6.48–7.45 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 6.48 net, 7.45 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Walls, two coats

  6.44–7.41 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 6.44 net, 7.41 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skip (dumpster) for the strip-out

  at least 3.96 m³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Dust sheets in the rooms below

  5 items

  Worked out, not compared with a quote

  Dust sheets and tape together, which a quote prices as preparation rather than listing.

  [Open the Masking and Protection Materials Calculator](https://craftquantities.com/calculators/renovation-construction/masking-and-protection-calculator/)

## How the ranges are taken

Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.

A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.

## What a reading like this cannot see

- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.

The full takeoff

## Every quantity for this job, with its working

The Loft room with rooflights takeoff runs the same calculators on the same measurements and shows what sits under each line here.

- [Open the takeoff](https://craftquantities.com/build/loft-room-rooflights/)
- [Every quote check](https://craftquantities.com/check/)

- Base, allowance, order

  Each line's quantity before and after its allowance, and what to buy.
- Every allowance editable

  Change a waste figure and the order follows, with its source named.
- Into a project

  Add the whole job to a workspace with your own prices.

## Frequently asked questions

**What quantities does a loft room job need?**

It depends on the measurements, so this page asks for yours. At the size it opens on — Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1 — the lines come to: Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 7 sheets (2400x1200 mm); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 6–7 packages; Insulation over the flat ceiling, 3–4 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 12–13 sheets; Plasterboard (drywall) on the walls, 12–13 sheets; Skim over every board, 170–186 kg; Mist coat or primer on the ceiling, slopes and reveals, 3.24–3.72 L; Mist coat or primer on the walls, 3.22–3.71 L; Skirting (baseboard), 20.9–22.9 m; Ceiling, slopes and reveals, two coats, 6.48–7.45 L; Walls, two coats, 6.44–7.41 L; Skip (dumpster) for the strip-out, 3.96 m³. In imperial units — Loft length, wall to wall 20 ft · New floor, knee wall to knee wall 14.5 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Sloped ceiling on each side, on plan 3.5 ft · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 2.5 ft · Rooflight height, each 4 ft · Reveal depth round each rooflight 11.8 in · Doors into the room 1 — they come to: Studs for the two knee walls, 39 studs; Boards between and under the sloped rafters, 6–7 sheets (4x8 ft); Batts in the knee walls, 4 packages; Sound insulation between the floor joists, 7 packages; Insulation over the flat ceiling, 4 packages; Plasterboard (drywall) on the ceiling, slopes and reveals, 12–13 sheets; Plasterboard (drywall) on the walls, 12–13 sheets; Joint compound for taping and filling every board, 2 x 4.5 gal boxes; Paper joint tape over every board, 420–460 ft; Mist coat or primer on the ceiling, slopes and reveals, 0.88–1.02 gal; Mist coat or primer on the walls, 0.88–1.01 gal; Skirting (baseboard), 69.3–76 linear ft; Ceiling, slopes and reveals, two coats, 1.77–2.03 gal; Walls, two coats, 1.77–2.03 gal; Skip (dumpster) for the strip-out, 5.29 yd³.

**Which line on a loft room quote varies the most?**

The Insulation over the flat ceiling: 3–4 packages for a job measured Loft length, wall to wall 6 m · New floor, knee wall to knee wall 4.4 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Sloped ceiling on each side, on plan 1.1 m · Roof slope factor 1.41 · Rooflights (roof windows) 2 · Rooflight width, each 0.78 m · Rooflight height, each 1.18 m · Reveal depth round each rooflight 300 mm · Doors into the room 1, depending on the waste allowance allowed, from 5% to 15%.

**What does a loft room quote often leave out?**

The reading names every line of the job that nothing on the quote reads as — any of the 15 lines the takeoff measures. The takeoff also lists 7 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (US customary) / The reading names every line of the job that nothing on the quote reads as — any of the 14 lines the takeoff measures. The takeoff also lists 7 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (metric)

**Can I paste the quote exactly as it came?**

Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.

**Does this check the price as well?**

No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.

---