# Check a loft conversion quote

> Paste a loft conversion quote and read it against your own measurements: the lines it leaves out, the ones it adds, the quantities outside the computed…

Page: https://craftquantities.com/check/loft-conversion-dormer-quote/ (quote check). This is the page's Markdown copy; the HTML page is the canonical version.

Each line read against your measurements: 30 (US customary) / 29 (metric) lines, 17 measurements. Quantities, never prices.

Step 1

## Your measurements

Measured this job on the [loft conversion with a dormer takeoff](https://craftquantities.com/build/loft-conversion-dormer/)? Send it to My Project, or save a setup, and these boxes fill in one press.

Worked from Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m (metric)

How to take each of these, and what each one feeds, is under the same field on the [loft conversion with a dormer takeoff](https://craftquantities.com/build/loft-conversion-dormer/).

Step 2 · Your quote

## The loft conversion quote you were given

Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.

Nothing you paste or open leaves this device.

or one the job needs:

Step 3 · The reading

## What the quote says, against the job

Loft conversion · Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m (metric)

- What it leaves out

  Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
- What it adds

  Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
- What sits outside the range

  Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
- What to ask

  One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.

Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.

### Outside what this takeoff measures

10

Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the [takeoff](https://craftquantities.com/build/loft-conversion-dormer/).

- The structure
- The stair and its balustrade, made to the loft's rise and headroom and listed as items
- Party wall matters
- Drainage beyond connecting the shower room to the existing soil stack, a new stack, and whether the boiler or heat pump can take another radiator
- The tiles on the cheeks and in the made-good slope round the dormer, the cladding on the face beside the windows, and every fixing for them
- The floor deck over the new joists, listed as work
- Ventilation of the cold roof spaces left behind the knee wall and over the flat ceiling, and the insulation of a gable end wall facing outside
- The shower room's floor finish, its tray, basin and WC, and the tiling above the height you give
- Render on the dormer's cheeks or face, where they are rendered rather than tiled or clad, with its primer, mesh and beads
- Undercoat and gloss (trim enamel) on the new woodwork

No quote read yet

[Open the takeoff](https://craftquantities.com/build/loft-conversion-dormer/)

Paste a quote

## The job

Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m (metric)

## What the job needs

For these measurements, by the site’s calculators.

_US customary:_

- Deck on the dormer's roof 6 sheets (4x8 ft)
- Warm-roof boards on the dormer 6 sheets (4x8 ft)
- EPDM on the dormer 1–2 rolls
- Termination bar at the back upstand 17.3–19 ft
- Termination bar fixings at least 19 fasteners
- Fascia along the dormer's front 2 x 12 ft boards
- Breathable membrane on the cheeks 1 roll
- Flashing down both cheeks 3–4 sheets
- The dormer's own gutter 2 x 10 ft sections
- Flashing tape round the dormer windows 46.2–50.6 ft
- Studs for the knee wall and the partitions 43 studs
- Boards between and under the sloped rafters 4 sheets (4x8 ft)
- Batts in the knee wall, cheeks and face 6 packages
- Sound insulation between the floor joists 8–9 packages
- Insulation over the flat ceiling beyond the dormer 3 packages
- Plasterboard (drywall) on the ceiling and slope 13–14 sheets
- Plasterboard (drywall) on the walls 14–16 sheets
- Board on both faces of the partitions 10–12 sheets
- Joint compound for taping and filling every board 3 x 4.5 gal boxes
- Paper joint tape over every board 601–658 ft
- Tanking in the shower room 8.51–9.79 gal
- Wall tiles in the shower room 85–93 tiles
- Wall tile adhesive 4–5 bags
- Wall tile grout 6.35–6.96 lb
- Mist coat or primer on the ceiling and slope 0.94–1.08 gal
- Mist coat or primer on the walls 1.8–2.06 gal
- Skirting (baseboard)78.8–86.3 linear ft
- Ceiling and slope, two coats 1.87–2.15 gal
- Walls, two coats 3.59–4.13 gal
- Skip (dumpster) for the strip-out at least 6.4 yd³

_metric:_

- Deck on the dormer's roof 6 sheets (2440x1220 mm)
- Warm-roof boards on the dormer 6 sheets (2400x1200 mm)
- EPDM on the dormer 1–2 rolls
- Termination bar at the back upstand 5.25–5.75 m
- Termination bar fixings at least 19 fasteners
- Fascia along the dormer's front 2 x 3.6 m boards
- Breathable membrane on the cheeks 1 roll
- Flashing down both cheeks 3–4 sheets
- The dormer's own gutter 2 x 4 m sections
- Flashing tape round the dormer windows 13.9–15.2 m
- Studs for the knee wall and the partitions 43 studs
- Boards between and under the sloped rafters 4 sheets (2400x1200 mm)
- Batts in the knee wall, cheeks and face 6 packages
- Sound insulation between the floor joists 8–9 packages
- Insulation over the flat ceiling beyond the dormer 3 packages
- Plasterboard (drywall) on the ceiling and slope 13–15 sheets
- Plasterboard (drywall) on the walls 15–16 sheets
- Board on both faces of the partitions 10–12 sheets
- Skim over every board 269–295 kg
- Tanking in the shower room 32.4–37.2 L
- Wall tiles in the shower room 86–94 tiles
- Wall tile adhesive 4–5 bags
- Wall tile grout 2.79–3.06 kg
- Mist coat or primer on the ceiling and slope 3.53–4.05 L
- Mist coat or primer on the walls 6.73–7.74 L
- Skirting (baseboard)24.2–26.5 m
- Ceiling and slope, two coats 7.05–8.11 L
- Walls, two coats 13.5–15.5 L
- Skip (dumpster) for the strip-out at least 4.95 m³

More than one quote

## Level the quotes side by side

Two to six loft conversion quotes, each read against this job: included, left out, excluded or added, line by line.

Kept on this device**Figures**The page's opening**Units**Imperial Quantities only, never prices

## How the quote is read

Each line of a loft conversion quote is matched to the line of the job it names, or marked as something the [Loft conversion with a dormer takeoff](https://craftquantities.com/build/loft-conversion-dormer/) does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.

The job’s own figures come from 17 measurements — loft length, wall to wall, new floor, knee wall to dormer face, sloped ceiling, on plan, knee wall height, floor to flat ceiling, main roof slope factor, dormer width, dormer depth, on plan, windows in the dormer face, window width, each, window height, each, doors in the new partitions, new stud partitions, height of the eaves above the ground, shower room length (0 if none), shower room width, tiled height in the shower room — run through the same calculators as the takeoff, so the two give the same figure for the same job.

## Reading a loft conversion quote

A loft conversion quote joins three trades' prices into one: the structure, the roofer's dormer and the fit-out. The structural lines are priced before the engineer's calculations exist, so worth asking whether the steels, the joists and the stair are fixed sums or provisional until the design arrives, and whether the calculations, the building control fees and any party wall notices are part of the price or left to you.

The dormer is the part that is open to the sky, so worth seeing named which waterproofing goes on its roof and whose guarantee covers it, how the cheeks are clad, and what keeps the rain out while the rafters are cut. Inside, this check boards every surface of the new room, the partitions included; a quote that boards fewer of them reads lower here. Whether the fire doors, the alarms, the shower room's tanking and the electrical test certificate are inside the figure is worth settling at the start.

How the new boards are finished changes with the units, the same way the takeoff opens: a plaster skim with metric showing, joint compound and paper tape with imperial showing. A skim quote read with imperial showing, or a taped one with metric, finds no finish line to sit against; switch the units and the same room is checked against the other finish.

## Three steps

1. Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
2. Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
3. Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.

The reference

## Every line the reading looks for

For Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft (US customary) / Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m (metric). Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.

_US customary:_

- Deck on the dormer's roof

  6 sheets (4x8 ft)

  The same at 5% waste factor and at 15%, once rounded to what is bought.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Warm-roof boards on the dormer

  6 sheets (4x8 ft)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- EPDM on the dormer

  1–2 rolls

  Membrane is bought by the roll or as a sheet cut from one, and the trimming at the edges and round each detail is lost. 1 net, 2 with 15% added.

  [Open the EPDM Single-Ply Roofing Roll Calculator](https://craftquantities.com/calculators/materials-quantities/epdm-roll-area-calculator/)
- Termination bar at the back upstand

  17.3–19 ft

  17.3 at 5% waste allowance, 19 at 15%.

  [Open the Roof Perimeter Termination Bar Calculator](https://craftquantities.com/calculators/materials-quantities/roof-perimeter-termination-bar-calculator/)
- Termination bar fixings

  at least 19 fasteners

  The fewest fixings the spacing allows along one continuous bar; each separate length takes one more, and closer fixings are a choice.

  [Open the Roof Membrane Termination Bar Fastener Calculator](https://craftquantities.com/calculators/materials-quantities/termination-bar-fastener-calculator/)
- Fascia along the dormer's front

  2 x 12 ft boards

  The same at 5% cut and scarf allowance and at 15%, once rounded to what is bought.

  [Open the Fascia Board Calculator](https://craftquantities.com/calculators/renovation-construction/fascia-board-calculator/)
- Breathable membrane on the cheeks

  1 roll

  One figure, with the overlap allowance the material needs already inside it at 10%.

  [Open the Roofing Underlayment Calculator](https://craftquantities.com/calculators/renovation-construction/roofing-underlayment-calculator/)
- Flashing down both cheeks

  3–4 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 3 net, 4 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- The dormer's own gutter

  2 x 10 ft sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Flashing tape round the dormer windows

  46.2–50.6 ft

  46.2 at 5% waste allowance, 50.6 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Studs for the knee wall and the partitions

  43 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Boards between and under the sloped rafters

  4 sheets (4x8 ft)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Batts in the knee wall, cheeks and face

  6 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Sound insulation between the floor joists

  8–9 packages

  8 at 5% waste allowance, 9 at 15%.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Insulation over the flat ceiling beyond the dormer

  3 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Plasterboard (drywall) on the ceiling and slope

  13–14 sheets

  13 at 5% waste allowance, 14 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Plasterboard (drywall) on the walls

  14–16 sheets

  14 at 5% waste allowance, 16 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Board on both faces of the partitions

  10–12 sheets

  Board is bought by the sheet and cut at every head, door and corner, and a rated wall's layers are staggered, which leaves narrow offcuts. 10 net, 12 with 15% added.

  [Open the Multi-Layer Fire-Rated (Type X) Gypsum Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/fire-rated-gypsum-layer-calculator/)
- Joint compound for taping and filling every board

  3 x 4.5 gal boxes

  The same at 5% pan and sanding loss and at 15%, once rounded to what is bought.

  [Open the Drywall Joint Compound Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-compound-calculator/)
- Paper joint tape over every board

  601–658 ft

  601 at 5% waste allowance, 658 at 15%.

  [Open the Drywall Joint Tape Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-tape-calculator/)
- Tanking in the shower room

  8.51–9.79 gal

  Resin is bought by the tub and mixed by the batch, and a batch that goes off before it is laid is lost. 8.51 net, 9.79 with 15% added.

  [Open the Cold-Applied Liquid Waterproofing Membrane Volume Calculator](https://craftquantities.com/calculators/materials-quantities/liquid-waterproofing-volume-calculator/)
- Wall tiles in the shower room

  85–93 tiles

  Lay pattern: 85 for Straight / stack bond, 93 for Herringbone.

  [Open the Floor & Wall Tile Calculator](https://craftquantities.com/calculators/renovation-construction/floor-tile-calculator/)
- Wall tile adhesive

  4–5 bags

  Adhesive is mixed by the bag, and whatever goes off in the bucket is not used. 4 net, 5 with 15% added.

  [Open the Thinset & Tile Adhesive Calculator](https://craftquantities.com/calculators/renovation-construction/thinset-mortar-calculator/)
- Wall tile grout

  6.35–6.96 lb

  6.35 at 5% waste allowance, 6.96 at 15%.

  [Open the Grout Calculator](https://craftquantities.com/calculators/renovation-construction/grout-calculator/)
- Mist coat or primer on the ceiling and slope

  0.94–1.08 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.94 net, 1.08 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Mist coat or primer on the walls

  1.8–2.06 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.8 net, 2.06 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skirting (baseboard)

  78.8–86.3 linear ft

  78.8 at 5% cutting waste, 86.3 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Ceiling and slope, two coats

  1.87–2.15 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 1.87 net, 2.15 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Walls, two coats

  3.59–4.13 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.59 net, 4.13 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skip (dumpster) for the strip-out

  at least 6.4 yd³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Dust sheets in the rooms below

  5 items

  Worked out, not compared with a quote

  Dust sheets and tape together, which a quote prices as preparation rather than listing.

  [Open the Masking and Protection Materials Calculator](https://craftquantities.com/calculators/renovation-construction/masking-and-protection-calculator/)
- Scaffold across the back

  478 sq ft of face

  Worked out, not compared with a quote

  The face the scaffold covers; a quote can price erecting, hire and striking as one sum, so one area is not held against it.

  [Open the Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)

_metric:_

- Deck on the dormer's roof

  6 sheets (2440x1220 mm)

  The same at 5% waste factor and at 15%, once rounded to what is bought.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Warm-roof boards on the dormer

  6 sheets (2400x1200 mm)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- EPDM on the dormer

  1–2 rolls

  Membrane is bought by the roll or as a sheet cut from one, and the trimming at the edges and round each detail is lost. 1 net, 2 with 15% added.

  [Open the EPDM Single-Ply Roofing Roll Calculator](https://craftquantities.com/calculators/materials-quantities/epdm-roll-area-calculator/)
- Termination bar at the back upstand

  5.25–5.75 m

  5.25 at 5% waste allowance, 5.75 at 15%.

  [Open the Roof Perimeter Termination Bar Calculator](https://craftquantities.com/calculators/materials-quantities/roof-perimeter-termination-bar-calculator/)
- Termination bar fixings

  at least 19 fasteners

  The fewest fixings the spacing allows along one continuous bar; each separate length takes one more, and closer fixings are a choice.

  [Open the Roof Membrane Termination Bar Fastener Calculator](https://craftquantities.com/calculators/materials-quantities/termination-bar-fastener-calculator/)
- Fascia along the dormer's front

  2 x 3.6 m boards

  The same at 5% cut and scarf allowance and at 15%, once rounded to what is bought.

  [Open the Fascia Board Calculator](https://craftquantities.com/calculators/renovation-construction/fascia-board-calculator/)
- Breathable membrane on the cheeks

  1 roll

  One figure, with the overlap allowance the material needs already inside it at 10%.

  [Open the Roofing Underlayment Calculator](https://craftquantities.com/calculators/renovation-construction/roofing-underlayment-calculator/)
- Flashing down both cheeks

  3–4 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 3 net, 4 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- The dormer's own gutter

  2 x 4 m sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Flashing tape round the dormer windows

  13.9–15.2 m

  13.9 at 5% waste allowance, 15.2 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Studs for the knee wall and the partitions

  43 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Boards between and under the sloped rafters

  4 sheets (2400x1200 mm)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Batts in the knee wall, cheeks and face

  6 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Sound insulation between the floor joists

  8–9 packages

  8 at 5% waste allowance, 9 at 15%.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Insulation over the flat ceiling beyond the dormer

  3 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Plasterboard (drywall) on the ceiling and slope

  13–15 sheets

  13 at 5% waste allowance, 15 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Plasterboard (drywall) on the walls

  15–16 sheets

  15 at 5% waste allowance, 16 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Board on both faces of the partitions

  10–12 sheets

  Board is bought by the sheet and cut at every head, door and corner, and a rated wall's layers are staggered, which leaves narrow offcuts. 10 net, 12 with 15% added.

  [Open the Multi-Layer Fire-Rated (Type X) Gypsum Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/fire-rated-gypsum-layer-calculator/)
- Skim over every board

  269–295 kg

  269 at 5% waste allowance, 295 at 15%.

  [Open the Skim Coat Plaster Calculator](https://craftquantities.com/calculators/materials-quantities/skim-coat-plaster-calculator/)
- Tanking in the shower room

  32.4–37.2 L

  Resin is bought by the tub and mixed by the batch, and a batch that goes off before it is laid is lost. 32.4 net, 37.2 with 15% added.

  [Open the Cold-Applied Liquid Waterproofing Membrane Volume Calculator](https://craftquantities.com/calculators/materials-quantities/liquid-waterproofing-volume-calculator/)
- Wall tiles in the shower room

  86–94 tiles

  Lay pattern: 86 for Straight / stack bond, 94 for Herringbone.

  [Open the Floor & Wall Tile Calculator](https://craftquantities.com/calculators/renovation-construction/floor-tile-calculator/)
- Wall tile adhesive

  4–5 bags

  Adhesive is mixed by the bag, and whatever goes off in the bucket is not used. 4 net, 5 with 15% added.

  [Open the Thinset & Tile Adhesive Calculator](https://craftquantities.com/calculators/renovation-construction/thinset-mortar-calculator/)
- Wall tile grout

  2.79–3.06 kg

  2.79 at 5% waste allowance, 3.06 at 15%.

  [Open the Grout Calculator](https://craftquantities.com/calculators/renovation-construction/grout-calculator/)
- Mist coat or primer on the ceiling and slope

  3.53–4.05 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 3.53 net, 4.05 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Mist coat or primer on the walls

  6.73–7.74 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 6.73 net, 7.74 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skirting (baseboard)

  24.2–26.5 m

  24.2 at 5% cutting waste, 26.5 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Ceiling and slope, two coats

  7.05–8.11 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 7.05 net, 8.11 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Walls, two coats

  13.5–15.5 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 13.5 net, 15.5 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Skip (dumpster) for the strip-out

  at least 4.95 m³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Dust sheets in the rooms below

  5 items

  Worked out, not compared with a quote

  Dust sheets and tape together, which a quote prices as preparation rather than listing.

  [Open the Masking and Protection Materials Calculator](https://craftquantities.com/calculators/renovation-construction/masking-and-protection-calculator/)
- Scaffold across the back

  45 m² of face

  Worked out, not compared with a quote

  The face the scaffold covers; a quote can price erecting, hire and striking as one sum, so one area is not held against it.

  [Open the Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)

## How the ranges are taken

Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.

A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.

## What a reading like this cannot see

- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.

The full takeoff

## Every quantity for this job, with its working

The Loft conversion with a dormer takeoff runs the same calculators on the same measurements and shows what sits under each line here.

- [Open the takeoff](https://craftquantities.com/build/loft-conversion-dormer/)
- [Every quote check](https://craftquantities.com/check/)

- Base, allowance, order

  Each line's quantity before and after its allowance, and what to buy.
- Every allowance editable

  Change a waste figure and the order follows, with its source named.
- Into a project

  Add the whole job to a workspace with your own prices.

## Frequently asked questions

**What quantities does a loft conversion job need?**

It depends on the measurements, so this page asks for yours. At the size it opens on — Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m — the lines come to: Deck on the dormer's roof, 6 sheets (2440x1220 mm); Warm-roof boards on the dormer, 6 sheets (2400x1200 mm); EPDM on the dormer, 1–2 rolls; Termination bar at the back upstand, 5.25–5.75 m; Termination bar fixings, 19 fasteners; Fascia along the dormer's front, 2 x 3.6 m boards; Breathable membrane on the cheeks, 1 roll; Flashing down both cheeks, 3–4 sheets; The dormer's own gutter, 2 x 4 m sections; Flashing tape round the dormer windows, 13.9–15.2 m; Studs for the knee wall and the partitions, 43 studs; Boards between and under the sloped rafters, 4 sheets (2400x1200 mm); Batts in the knee wall, cheeks and face, 6 packages; Sound insulation between the floor joists, 8–9 packages; Insulation over the flat ceiling beyond the dormer, 3 packages; Plasterboard (drywall) on the ceiling and slope, 13–15 sheets; Plasterboard (drywall) on the walls, 15–16 sheets; Board on both faces of the partitions, 10–12 sheets; Skim over every board, 269–295 kg; Tanking in the shower room, 32.4–37.2 L; Wall tiles in the shower room, 86–94 tiles; Wall tile adhesive, 4–5 bags; Wall tile grout, 2.79–3.06 kg; Mist coat or primer on the ceiling and slope, 3.53–4.05 L; Mist coat or primer on the walls, 6.73–7.74 L; Skirting (baseboard), 24.2–26.5 m; Ceiling and slope, two coats, 7.05–8.11 L; Walls, two coats, 13.5–15.5 L; Skip (dumpster) for the strip-out, 4.95 m³. In imperial units — Loft length, wall to wall 19.5 ft · New floor, knee wall to dormer face 18 ft · Sloped ceiling, on plan 4 ft · Knee wall height 4 ft · Floor to flat ceiling 7.5 ft · Main roof slope factor 1.3 · Dormer width 16.5 ft · Dormer depth, on plan 10 ft · Windows in the dormer face 2 · Window width, each 4 ft · Window height, each 4 ft · Doors in the new partitions 2 · New stud partitions 19.5 ft · Height of the eaves above the ground 17 ft · Shower room length (0 if none) 6.5 ft · Shower room width 5 ft · Tiled height in the shower room 6.5 ft — they come to: Deck on the dormer's roof, 6 sheets (4x8 ft); Warm-roof boards on the dormer, 6 sheets (4x8 ft); EPDM on the dormer, 1–2 rolls; Termination bar at the back upstand, 17.3–19 ft; Termination bar fixings, 19 fasteners; Fascia along the dormer's front, 2 x 12 ft boards; Breathable membrane on the cheeks, 1 roll; Flashing down both cheeks, 3–4 sheets; The dormer's own gutter, 2 x 10 ft sections; Flashing tape round the dormer windows, 46.2–50.6 ft; Studs for the knee wall and the partitions, 43 studs; Boards between and under the sloped rafters, 4 sheets (4x8 ft); Batts in the knee wall, cheeks and face, 6 packages; Sound insulation between the floor joists, 8–9 packages; Insulation over the flat ceiling beyond the dormer, 3 packages; Plasterboard (drywall) on the ceiling and slope, 13–14 sheets; Plasterboard (drywall) on the walls, 14–16 sheets; Board on both faces of the partitions, 10–12 sheets; Joint compound for taping and filling every board, 3 x 4.5 gal boxes; Paper joint tape over every board, 601–658 ft; Tanking in the shower room, 8.51–9.79 gal; Wall tiles in the shower room, 85–93 tiles; Wall tile adhesive, 4–5 bags; Wall tile grout, 6.35–6.96 lb; Mist coat or primer on the ceiling and slope, 0.94–1.08 gal; Mist coat or primer on the walls, 1.8–2.06 gal; Skirting (baseboard), 78.8–86.3 linear ft; Ceiling and slope, two coats, 1.87–2.15 gal; Walls, two coats, 3.59–4.13 gal; Skip (dumpster) for the strip-out, 6.4 yd³.

**Which line on a loft conversion quote varies the most?**

The EPDM on the dormer: 1–2 rolls for a job measured Loft length, wall to wall 6 m · New floor, knee wall to dormer face 5.5 m · Sloped ceiling, on plan 1.25 m · Knee wall height 1.2 m · Floor to flat ceiling 2.3 m · Main roof slope factor 1.3 · Dormer width 5 m · Dormer depth, on plan 3 m · Windows in the dormer face 2 · Window width, each 1.2 m · Window height, each 1.2 m · Doors in the new partitions 2 · New stud partitions 6 m · Height of the eaves above the ground 5.2 m · Shower room length (0 if none) 2 m · Shower room width 1.5 m · Tiled height in the shower room 2 m, depending on how much is allowed for loss over the net figure, up to 15%.

**What does a loft conversion quote often leave out?**

The reading names every line of the job that nothing on the quote reads as — any of the 30 lines the takeoff measures. The takeoff also lists 10 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (US customary) / The reading names every line of the job that nothing on the quote reads as — any of the 29 lines the takeoff measures. The takeoff also lists 10 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (metric)

**Can I paste the quote exactly as it came?**

Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.

**Does this check the price as well?**

No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.

---
Source: https://craftquantities.com/check/loft-conversion-dormer-quote/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.