## Your measurements

Measured this job on the [garden room or backyard office takeoff](https://craftquantities.com/build/garden-room/)? Send it to My Project, or save a setup, and these boxes fill in one press.

Worked from Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in (US customary) / Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm (metric)

How to take each of these, and what each one feeds, is under the same field on the [garden room or backyard office takeoff](https://craftquantities.com/build/garden-room/).

Step 2 · Your quote

## The garden room quote you were given

Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.

Nothing you paste or open leaves this device.

or one the job needs:

Step 3 · The reading

## What the quote says, against the job

Garden room · Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in (US customary) / Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm (metric)

- What it leaves out

  Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
- What it adds

  Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
- What sits outside the range

  Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
- What to ask

  One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.

Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.

### Outside what this takeoff measures

11

Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the [takeoff](https://craftquantities.com/build/garden-room/).

- What the base and the frame must be to carry the room
- Planning
- Whether the house's main board (service panel) has the capacity for the room's circuit, the cable's size and protection, and the earthing arrangement at the room
- A water supply, a toilet, a sink or a shower in the room, and any foul drainage from it
- Whether a soakaway (a dry well) will drain in the ground and how big it must be, where the downpipe runs to one; the drain run to it is listed as work, not measured
- Decking, a veranda, steps up to the door, and a path from the house
- Choosing the door set and the windows
- Heating, cooling or mechanical ventilation for the room
- Architraves (casings) round the door set and the windows, and any window boards (stools): fixed with the skirting as its work, and not counted
- The roof's fall
- A roof covered in anything but a single EPDM sheet

No quote read yet

[Open the takeoff](https://craftquantities.com/build/garden-room/)

Paste a quote

## The job

Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in (US customary) / Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm (metric)

## What the job needs

For these measurements, by the site’s calculators.

_US customary:_

- Turf, topsoil and ground dug out over the footprint 2.01 yd³
- Concrete for the piers 1.1–1.2 yd³
- Weed membrane and stone laid in the dig (gravel or hardcore)2.98–3.42 tons
- Floor insulation boards, cut between the joists 5 sheets (4x8 ft)
- Wall studs, the walls' frame (studwork)53 studs
- Sheathing on the walls, OSB or plywood 13–14 sheets (4x8 ft)
- Roof deck, OSB or plywood 6 sheets (4x8 ft)
- Rigid insulation boards, warm roof 6 sheets (4x8 ft)
- EPDM membrane over the roof 1–2 rolls
- Gutter and downpipe (downspout) along the eaves 2 x 10 ft sections
- Breather membrane (house wrap) on the walls 1 roll
- Flashing tape round the openings, outside 70.4–77 ft
- Furring (battens) fixed upright on the walls 288–331 ft
- Siding (cladding): lap or plank, vinyl, wood or fibre cement 3.33–3.64 squares
- Trims outside: corners, heads and reveals 8–10 sheets
- Mastic (caulk) round the openings 0.16–0.18 gal
- Exterior stain or paint on the clad walls 2.5–2.88 gallons
- Trench for the supply cable, dug and backfilled 4.11 yd³
- Insulation batts, walls 6 packages
- Vapour control layer on the walls 1 roll
- Ceiling board (plasterboard or drywall)4–5 sheets
- Board on the walls inside (plasterboard or drywall)9 sheets
- Joint compound (mud), walls and ceiling 1 x 4.5 gal box
- Joint tape, walls and ceiling 218–239 ft
- Paint on the walls inside 1.23–1.42 gal
- Paint on the ceiling 0.56–0.65 gal
- Laminate or vinyl plank floor 6 packs
- Skirting (baseboard) round the room; architraves (casings) not counted 41.9–45.9 linear ft
- Skip (dumpster) or muck away for the spoil at least 2.01 yd³
- Skip or bags for the offcuts and packaging at least 1.97 yd³

_metric:_

- Turf, topsoil and ground dug out over the footprint 1.5 m³ (loose)
- Weed membrane and stone laid in the dig (gravel or hardcore)2.64–3.04 metric tons
- Floor insulation boards, cut between the joists 5 sheets (2400x1200 mm)
- Wall studs, the walls' frame (studwork)53 studs
- Sheathing on the walls, OSB or plywood 12–13 sheets (2440x1220 mm)
- Roof deck, OSB or plywood 6 sheets (2440x1220 mm)
- Rigid insulation boards, warm roof 6 sheets (2400x1200 mm)
- EPDM membrane over the roof 1–2 rolls
- Gutter and downpipe (downspout) along the eaves 2 x 4 m sections
- Breather membrane (house wrap) on the walls 1 roll
- Flashing tape round the openings, outside 21–23 m
- Battens and counter-battens 184–212 m
- Cladding boards and cover battens (board-and-batten siding)80–92 boards
- Trims outside: corners, heads and reveals 8–10 sheets
- Mastic (caulk) round the openings 0.53–0.6 L
- Exterior stain or paint on the clad walls 9.46–10.9 L
- Trench for the supply cable, dug and backfilled 3.1 m³ (loose)
- Insulation batts, walls 6 packages
- Vapour control layer on the walls 1 roll
- Ceiling board (plasterboard or drywall)4–5 sheets
- Board on the walls inside (plasterboard or drywall)9–10 sheets
- Skim coat over the boards, walls and ceiling 89.9–98.5 kg
- Paint on the walls inside 4.78–5.49 L
- Paint on the ceiling 2.08–2.39 L
- Laminate or vinyl plank floor 6 packs
- Skirting (baseboard) round the room; architraves (casings) not counted 12.7–14 m
- Skip (dumpster) or muck away for the spoil at least 1.5 m³
- Skip or bags for the offcuts and packaging at least 1.5 m³

More than one quote

## Level the quotes side by side

Two to six garden room quotes, each read against this job: included, left out, excluded or added, line by line.

Kept on this device**Figures**The page's opening**Units**Imperial Quantities only, never prices

## How the quote is read

Each line of a garden room quote is matched to the line of the job it names, or marked as something the [Garden room or backyard office takeoff](https://craftquantities.com/build/garden-room/) does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.

The job’s own figures come from 15 measurements — length, along the front, depth, front to back, height clad outside, room height, floor to ceiling, wall thickness, sheathing to lining, roof overhang, each edge, door opening width, door opening height, windows, window opening width, each, window opening height, each, supply cable route, house to room, cable trench depth, dig over the footprint, membrane turned over each roof edge — run through the same calculators as the takeoff, so the two give the same figure for the same job.

## Reading a garden room quote

A garden room can be bought as a kit to assemble, as a supplier's room built on your ground, or as a builder's own design, and each of the three leaves a different share of the job out of the price. Worth asking whether the figure includes the base as well as the building, who designs and drives the ground screws or pours the piers, whose record of them comes with the handover, and whether the turf and soil dug off the footprint are taken away or left in a heap for you.

The layers between the frame and the weather are where two quotes for one size of room part company. Worth seeing named the breather membrane, the battens that hold the cladding off it, the insulation in the floor, the walls and the roof with its thickness, the vapour control layer, the roof membrane with its edge trims, and whether the cladding is stained or left to weather. The power is another trade's work inside the same price or beside it: worth settling whether the armoured cable, its trench, the new way in the board (panel) back at the house and the electrician's certificate are all in, and where the water off the roof is meant to go.

Whether the room needs planning permission or building control turns on how tall the room is, its distance from the boundary, its floor area and whether anyone will sleep in it, and a price may rest on an assumption about each. Worth asking which one the quote makes, and in North America whether the permit, its drawings and the inspections for an accessory structure are part of the figure.

## Three steps

1. Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
2. Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
3. Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.

The reference

## Every line the reading looks for

For Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in (US customary) / Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm (metric). Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.

_US customary:_

- Turf, topsoil and ground dug out over the footprint

  2.01 yd³

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Concrete for the piers

  1.1–1.2 yd³

  1.1 at 5% waste factor, 1.2 at 15%.

  [Open the Circular Pier / Cylinder Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/circular-pier-concrete-calculator/)
- Weed membrane and stone laid in the dig (gravel or hardcore)

  2.98–3.42 tons

  Stone is bought by the tonne, and some is always lost into the formation and at the edges. 2.98 net, 3.42 with 15% added.

  [Open the Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)
- Floor insulation boards, cut between the joists

  5 sheets (4x8 ft)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Wall studs, the walls' frame (studwork)

  53 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Sheathing on the walls, OSB or plywood

  13–14 sheets (4x8 ft)

  13 at 5% waste factor, 14 at 15%.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Roof deck, OSB or plywood

  6 sheets (4x8 ft)

  The same at 5% waste factor and at 15%, once rounded to what is bought.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Rigid insulation boards, warm roof

  6 sheets (4x8 ft)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- EPDM membrane over the roof

  1–2 rolls

  Membrane is bought by the roll or as a sheet cut from one, and the trimming at the edges and round each detail is lost. 1 net, 2 with 15% added.

  [Open the EPDM Single-Ply Roofing Roll Calculator](https://craftquantities.com/calculators/materials-quantities/epdm-roll-area-calculator/)
- Gutter and downpipe (downspout) along the eaves

  2 x 10 ft sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Breather membrane (house wrap) on the walls

  1 roll

  One figure, with the lap allowance the material needs already inside it at 10%.

  [Open the House Wrap Calculator](https://craftquantities.com/calculators/renovation-construction/house-wrap-calculator/)
- Flashing tape round the openings, outside

  70.4–77 ft

  70.4 at 5% waste allowance, 77 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Furring (battens) fixed upright on the walls

  288–331 ft

  Battens (furring strips) come in stock lengths, and each strip cut from them leaves an offcut. 288 net, 331 with 15% added.

  [Open the Rain-Screen Cladding Furring Strip Calculator](https://craftquantities.com/calculators/materials-quantities/rain-screen-furring-calculator/)
- Siding (cladding): lap or plank, vinyl, wood or fibre cement

  3.33–3.64 squares

  3.33 at 5% waste factor, 3.64 at 15%.

  [Open the Siding Calculator](https://craftquantities.com/calculators/renovation-construction/siding-calculator/)
- Trims outside: corners, heads and reveals

  8–10 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 8 net, 10 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- Mastic (caulk) round the openings

  0.16–0.18 gal

  Sealant comes by the tube, and the end of every tube is left in the gun. 0.16 net, 0.18 with 15% added.

  [Open the Fiber-Cement Siding Caulk Joint Volume Calculator](https://craftquantities.com/calculators/materials-quantities/fiber-cement-caulk-volume-calculator/)
- Exterior stain or paint on the clad walls

  2.5–2.88 gallons

  Paint is bought by the can, and rough or weathered cladding takes more than a smooth wall. 2.5 net, 2.88 with 15% added.

  [Open the Exterior Paint Calculator](https://craftquantities.com/calculators/renovation-construction/exterior-paint-calculator/)
- Trench for the supply cable, dug and backfilled

  4.11 yd³

  One figure, with the loose-volume allowance the material needs already inside it at 15%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Insulation batts, walls

  6 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Vapour control layer on the walls

  1 roll

  One figure, with the seam overlap allowance the material needs already inside it at 10%.

  [Open the Vapor Barrier Calculator](https://craftquantities.com/calculators/insulation-efficiency/vapor-barrier-calculator/)
- Ceiling board (plasterboard or drywall)

  4–5 sheets

  4 at 5% waste allowance, 5 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Board on the walls inside (plasterboard or drywall)

  9 sheets

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Joint compound (mud), walls and ceiling

  1 x 4.5 gal box

  The same at 5% pan and sanding loss and at 15%, once rounded to what is bought.

  [Open the Drywall Joint Compound Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-compound-calculator/)
- Joint tape, walls and ceiling

  218–239 ft

  218 at 5% waste allowance, 239 at 15%.

  [Open the Drywall Joint Tape Calculator](https://craftquantities.com/calculators/renovation-construction/drywall-joint-tape-calculator/)
- Paint on the walls inside

  1.23–1.42 gal

  Paint is bought by the tin, and some always stays in the tray and on the roller. 1.23 net, 1.42 with 15% added.

  [Open the Paint Calculator](https://craftquantities.com/calculators/renovation-construction/paint-calculator/)
- Paint on the ceiling

  0.56–0.65 gal

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 0.56 net, 0.65 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Laminate or vinyl plank floor

  6 packs

  Room and lay: 6 for Simple rectangular room, 6 for Simple rectangular room.

  [Open the LVP, Laminate & Engineered Floor Calculator](https://craftquantities.com/calculators/renovation-construction/resilient-flooring-calculator/)
- Skirting (baseboard) round the room; architraves (casings) not counted

  41.9–45.9 linear ft

  41.9 at 5% cutting waste, 45.9 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Skip (dumpster) or muck away for the spoil

  at least 2.01 yd³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Skip or bags for the offcuts and packaging

  at least 1.97 yd³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)

_metric:_

- Turf, topsoil and ground dug out over the footprint

  1.5 m³ (loose)

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Weed membrane and stone laid in the dig (gravel or hardcore)

  2.64–3.04 metric tons

  Stone is bought by the tonne, and some is always lost into the formation and at the edges. 2.64 net, 3.04 with 15% added.

  [Open the Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)
- Floor insulation boards, cut between the joists

  5 sheets (2400x1200 mm)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Wall studs, the walls' frame (studwork)

  53 studs

  One figure, with the spare studs the material needs already inside it at 10%.

  [Open the Framing Stud Calculator](https://craftquantities.com/calculators/renovation-construction/framing-stud-calculator/)
- Sheathing on the walls, OSB or plywood

  12–13 sheets (2440x1220 mm)

  12 at 5% waste factor, 13 at 15%.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Roof deck, OSB or plywood

  6 sheets (2440x1220 mm)

  The same at 5% waste factor and at 15%, once rounded to what is bought.

  [Open the Plywood and OSB Sheet Calculator (Subfloor, Wall and Roof)](https://craftquantities.com/calculators/materials-quantities/plywood-sheet-calculator/)
- Rigid insulation boards, warm roof

  6 sheets (2400x1200 mm)

  The same at 5% cutting waste and at 15%, once rounded to what is bought.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- EPDM membrane over the roof

  1–2 rolls

  Membrane is bought by the roll or as a sheet cut from one, and the trimming at the edges and round each detail is lost. 1 net, 2 with 15% added.

  [Open the EPDM Single-Ply Roofing Roll Calculator](https://craftquantities.com/calculators/materials-quantities/epdm-roll-area-calculator/)
- Gutter and downpipe (downspout) along the eaves

  2 x 4 m sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Breather membrane (house wrap) on the walls

  1 roll

  One figure, with the lap allowance the material needs already inside it at 10%.

  [Open the House Wrap Calculator](https://craftquantities.com/calculators/renovation-construction/house-wrap-calculator/)
- Flashing tape round the openings, outside

  21–23 m

  21 at 5% waste allowance, 23 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Battens and counter-battens

  184–212 m

  Battens (furring strips) come in stock lengths, and each strip cut from them leaves an offcut. 184 net, 212 with 15% added.

  [Open the Rain-Screen Cladding Furring Strip Calculator](https://craftquantities.com/calculators/materials-quantities/rain-screen-furring-calculator/)
- Cladding boards and cover battens (board-and-batten siding)

  80–92 boards

  Boards and battens are cut to the wall's height, and the offcuts at openings are rarely long enough to use. 80 net, 92 with 15% added.

  [Open the Board and Batten Siding Calculator](https://craftquantities.com/calculators/renovation-construction/board-and-batten-siding-calculator/)
- Trims outside: corners, heads and reveals

  8–10 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 8 net, 10 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- Mastic (caulk) round the openings

  0.53–0.6 L

  Sealant comes by the tube, and the end of every tube is left in the gun. 0.53 net, 0.6 with 15% added.

  [Open the Fiber-Cement Siding Caulk Joint Volume Calculator](https://craftquantities.com/calculators/materials-quantities/fiber-cement-caulk-volume-calculator/)
- Exterior stain or paint on the clad walls

  9.46–10.9 L

  Paint is bought by the can, and rough or weathered cladding takes more than a smooth wall. 9.46 net, 10.9 with 15% added.

  [Open the Exterior Paint Calculator](https://craftquantities.com/calculators/renovation-construction/exterior-paint-calculator/)
- Trench for the supply cable, dug and backfilled

  3.1 m³ (loose)

  One figure, with the loose-volume allowance the material needs already inside it at 15%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Insulation batts, walls

  6 packages

  The same at 5% waste allowance and at 15%, once rounded to what is bought.

  [Open the Mineral Wool Insulation Batt Calculator](https://craftquantities.com/calculators/materials-quantities/mineral-wool-batt-calculator/)
- Vapour control layer on the walls

  1 roll

  One figure, with the seam overlap allowance the material needs already inside it at 10%.

  [Open the Vapor Barrier Calculator](https://craftquantities.com/calculators/insulation-efficiency/vapor-barrier-calculator/)
- Ceiling board (plasterboard or drywall)

  4–5 sheets

  4 at 5% waste allowance, 5 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Board on the walls inside (plasterboard or drywall)

  9–10 sheets

  9 at 5% waste allowance, 10 at 15%.

  [Open the Ceiling Plasterboard Calculator (Gypsum Board Sheets)](https://craftquantities.com/calculators/materials-quantities/ceiling-plasterboard-sheet-calculator/)
- Skim coat over the boards, walls and ceiling

  89.9–98.5 kg

  89.9 at 5% waste allowance, 98.5 at 15%.

  [Open the Skim Coat Plaster Calculator](https://craftquantities.com/calculators/materials-quantities/skim-coat-plaster-calculator/)
- Paint on the walls inside

  4.78–5.49 L

  Paint is bought by the tin, and some always stays in the tray and on the roller. 4.78 net, 5.49 with 15% added.

  [Open the Paint Calculator](https://craftquantities.com/calculators/renovation-construction/paint-calculator/)
- Paint on the ceiling

  2.08–2.39 L

  Paint is bought by the tin, and rolling overhead loses more to the floor and the roller than wall work does. 2.08 net, 2.39 with 15% added.

  [Open the Ceiling Paint Calculator](https://craftquantities.com/calculators/renovation-construction/ceiling-paint-calculator/)
- Laminate or vinyl plank floor

  6 packs

  Room and lay: 6 for Simple rectangular room, 6 for Simple rectangular room.

  [Open the LVP, Laminate & Engineered Floor Calculator](https://craftquantities.com/calculators/renovation-construction/resilient-flooring-calculator/)
- Skirting (baseboard) round the room; architraves (casings) not counted

  12.7–14 m

  12.7 at 5% cutting waste, 14 at 15%.

  [Open the Baseboard & Trim Calculator](https://craftquantities.com/calculators/renovation-construction/baseboard-trim-calculator/)
- Skip (dumpster) or muck away for the spoil

  at least 1.5 m³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Skip or bags for the offcuts and packaging

  at least 1.5 m³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)

## How the ranges are taken

Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.

A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.

## What a reading like this cannot see

- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.

The full takeoff

## Every quantity for this job, with its working

The Garden room or backyard office takeoff runs the same calculators on the same measurements and shows what sits under each line here.

- [Open the takeoff](https://craftquantities.com/build/garden-room/)
- [Every quote check](https://craftquantities.com/check/)

- Base, allowance, order

  Each line's quantity before and after its allowance, and what to buy.
- Every allowance editable

  Change a waste figure and the order follows, with its source named.
- Into a project

  Add the whole job to a workspace with your own prices.

## Frequently asked questions

**What quantities does a garden room job need?**

It depends on the measurements, so this page asks for yours. At the size it opens on — Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm — the lines come to: Turf, topsoil and ground dug out over the footprint, 1.5 m³ (loose); Weed membrane and stone laid in the dig (gravel or hardcore), 2.64–3.04 metric tons; Floor insulation boards, cut between the joists, 5 sheets (2400x1200 mm); Wall studs, the walls' frame (studwork), 53 studs; Sheathing on the walls, OSB or plywood, 12–13 sheets (2440x1220 mm); Roof deck, OSB or plywood, 6 sheets (2440x1220 mm); Rigid insulation boards, warm roof, 6 sheets (2400x1200 mm); EPDM membrane over the roof, 1–2 rolls; Gutter and downpipe (downspout) along the eaves, 2 x 4 m sections; Breather membrane (house wrap) on the walls, 1 roll; Flashing tape round the openings, outside, 21–23 m; Battens and counter-battens, 184–212 m; Cladding boards and cover battens (board-and-batten siding), 80–92 boards; Trims outside: corners, heads and reveals, 8–10 sheets; Mastic (caulk) round the openings, 0.53–0.6 L; Exterior stain or paint on the clad walls, 9.46–10.9 L; Trench for the supply cable, dug and backfilled, 3.1 m³ (loose); Insulation batts, walls, 6 packages; Vapour control layer on the walls, 1 roll; Ceiling board (plasterboard or drywall), 4–5 sheets; Board on the walls inside (plasterboard or drywall), 9–10 sheets; Skim coat over the boards, walls and ceiling, 89.9–98.5 kg; Paint on the walls inside, 4.78–5.49 L; Paint on the ceiling, 2.08–2.39 L; Laminate or vinyl plank floor, 6 packs; Skirting (baseboard) round the room; architraves (casings) not counted, 12.7–14 m; Skip (dumpster) or muck away for the spoil, 1.5 m³; Skip or bags for the offcuts and packaging, 1.5 m³. In imperial units — Length, along the front 13 ft · Depth, front to back 10 ft · Height clad outside 8 ft · Room height, floor to ceiling 7 ft · Wall thickness, sheathing to lining 4.75 in · Roof overhang, each edge 6 in · Door opening width 5 ft · Door opening height 6.5 ft · Windows 2 · Window opening width, each 3 ft · Window opening height, each 3.5 ft · Supply cable route, house to room 49 ft · Cable trench depth 2 ft · Dig over the footprint 4 in · Membrane turned over each roof edge 4 in — they come to: Turf, topsoil and ground dug out over the footprint, 2.01 yd³; Concrete for the piers, 1.1–1.2 yd³; Weed membrane and stone laid in the dig (gravel or hardcore), 2.98–3.42 tons; Floor insulation boards, cut between the joists, 5 sheets (4x8 ft); Wall studs, the walls' frame (studwork), 53 studs; Sheathing on the walls, OSB or plywood, 13–14 sheets (4x8 ft); Roof deck, OSB or plywood, 6 sheets (4x8 ft); Rigid insulation boards, warm roof, 6 sheets (4x8 ft); EPDM membrane over the roof, 1–2 rolls; Gutter and downpipe (downspout) along the eaves, 2 x 10 ft sections; Breather membrane (house wrap) on the walls, 1 roll; Flashing tape round the openings, outside, 70.4–77 ft; Furring (battens) fixed upright on the walls, 288–331 ft; Siding (cladding): lap or plank, vinyl, wood or fibre cement, 3.33–3.64 squares; Trims outside: corners, heads and reveals, 8–10 sheets; Mastic (caulk) round the openings, 0.16–0.18 gal; Exterior stain or paint on the clad walls, 2.5–2.88 gallons; Trench for the supply cable, dug and backfilled, 4.11 yd³; Insulation batts, walls, 6 packages; Vapour control layer on the walls, 1 roll; Ceiling board (plasterboard or drywall), 4–5 sheets; Board on the walls inside (plasterboard or drywall), 9 sheets; Joint compound (mud), walls and ceiling, 1 x 4.5 gal box; Joint tape, walls and ceiling, 218–239 ft; Paint on the walls inside, 1.23–1.42 gal; Paint on the ceiling, 0.56–0.65 gal; Laminate or vinyl plank floor, 6 packs; Skirting (baseboard) round the room; architraves (casings) not counted, 41.9–45.9 linear ft; Skip (dumpster) or muck away for the spoil, 2.01 yd³; Skip or bags for the offcuts and packaging, 1.97 yd³.

**Which line on a garden room quote varies the most?**

The EPDM membrane over the roof: 1–2 rolls for a job measured Length, along the front 4 m · Depth, front to back 3 m · Height clad outside 2.4 m · Room height, floor to ceiling 2.2 m · Wall thickness, sheathing to lining 120 mm · Roof overhang, each edge 150 mm · Door opening width 1.5 m · Door opening height 2 m · Windows 2 · Window opening width, each 0.9 m · Window opening height, each 1 m · Supply cable route, house to room 15 m · Cable trench depth 0.6 m · Dig over the footprint 100 mm · Membrane turned over each roof edge 100 mm, depending on how much is allowed for loss over the net figure, up to 15%.

**What does a garden room quote often leave out?**

The reading names every line of the job that nothing on the quote reads as — any of the 30 lines the takeoff measures. The takeoff also lists 11 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (US customary) / The reading names every line of the job that nothing on the quote reads as — any of the 28 lines the takeoff measures. The takeoff also lists 11 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started. (metric)

**Can I paste the quote exactly as it came?**

Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.

**Does this check the price as well?**

No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.

---