Step 1

## Your measurements

Measured this job on the [extension shell, one or two storeys takeoff](https://craftquantities.com/build/extension-shell/)? Send it to My Project, or save a setup, and these boxes fill in one press.

Worked from Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in (US customary) / Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm (metric)

How to take each of these, and what each one feeds, is under the same field on the [extension shell, one or two storeys takeoff](https://craftquantities.com/build/extension-shell/).

Step 2 · Your quote

## The extension shell quote you were given

Paste from an email, or open or drop a PDF, Excel, CSV or text file, or a photo of the quote. Amounts of money are taken out before anything is read — this page compares quantities, never prices.

Nothing you paste or open leaves this device.

or one the job needs:

Step 3 · The reading

## What the quote says, against the job

Extension shell · Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in (US customary) / Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm (metric)

- What it leaves out

  Every line the job needs that nothing on the quote reads as, with the quantity your measurements produce.
- What it adds

  Lines this job's takeoff does not measure — labour, removal, hire, fees, anything else — each named for what it is.
- What sits outside the range

  Quantities above or below the computed range, by how much, in the quote's unit or converted and shown.
- What to ask

  One list of questions, in the quote's order, ready to copy and send. Questions, never a verdict.

Paste the quote above, or add its lines one at a time. The reading appears here as each line is read.

### Outside what this takeoff measures

8

Nothing in the reading measures these. Whether the quote covers each is worth asking in its own right: a scope missing from a quote tends to become a cost after work has started. Why each is left out is on the [takeoff](https://craftquantities.com/build/extension-shell/).

- Every structural size
- A flat roof over a single storey
- The tiles or slates, and their fixings
- The masonry above the eaves
- The precast beams and infill blocks of a beam-and-block floor, laid to the floor supplier's layout, which sizes them; no operation lists them yet
- Planning permission, a party wall notice or agreement where the extension stands on or near a boundary, and a build-over agreement for, or a diversion of, a public sewer under the footprint
- Movement joints in the new brickwork, and the detail where a return meets the house, which the designer chooses between a tie system, a toothed bond and a joint
- Everything after weathertight

No quote read yet

[Open the takeoff](https://craftquantities.com/build/extension-shell/)

Paste a quote

## The job

Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in (US customary) / Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm (metric)

## What the job needs

For these measurements, by the site’s calculators.

_US customary:_

- Footing trenches, dug 13.8 yd³
- Dig over the floor 7.92 yd³
- Footing concrete 8.26–9.05 yd³
- Blocks below the damp-proof course, both leaves 151–165 blocks
- Hardcore under the slab 6–6.9 tons
- Floor insulation boards 6–7 sheets (4x8 ft)
- Floor slab concrete 2.27–2.48 yd³
- Inner leaf blocks, clear of the openings 260–285 blocks
- Inner leaf blocks, above and below the openings 18–20 blocks
- Facing bricks, clear of the openings 1,584–1,735 bricks
- Facing bricks, above and below the openings 108–119 bricks
- Wall ties across the cavity at least 89 ties
- Cavity boards 8–9 sheets (4x8 ft)
- Weep holes at the damp course at least 23 weep holes
- Lean-to rafters at least 10 trusses
- Fascia along the eaves 2 x 12 ft boards
- Underlay over the lean-to 1 roll
- Flashing where the roof meets the house 2–3 sheets
- Gutter along the eaves 2 x 10 ft sections
- Gutter brackets at least 10 hangers
- Flashing tape round the openings 94.5–103 ft
- Skip (dumpster) loads for the spoil at least 21.7 yd³

_metric:_

- Footing trenches, dug 9.75 m³ (loose)
- Dig over the floor 6.11 m³ (loose)
- Footing concrete 6.14–6.73 m³
- Blocks below the damp-proof course, both leaves 108–119 blocks
- Hardcore under the slab 5.37–6.18 metric tons
- Floor insulation boards 6–7 sheets (2400x1200 mm)
- Floor slab concrete 1.71–1.87 m³
- Inner leaf blocks, clear of the openings 221–242 blocks
- Inner leaf blocks, above and below the openings 19–21 blocks
- Facing bricks, clear of the openings 1,323–1,449 bricks
- Facing bricks, above and below the openings 112–123 bricks
- Wall ties across the cavity at least 93 ties
- Cavity boards 9–10 sheets (2400x1200 mm)
- Weep holes at the damp course at least 23 weep holes
- Lean-to rafters at least 10 trusses
- Fascia along the eaves 2 x 3.6 m boards
- Underlay over the lean-to 1 roll
- Flashing where the roof meets the house 4–5 sheets
- Gutter along the eaves 2 x 4 m sections
- Gutter brackets at least 10 hangers
- Flashing tape round the openings 28.4–31.1 m
- Skip (dumpster) loads for the spoil at least 15.9 m³

More than one quote

## Level the quotes side by side

Two to six extension shell quotes, each read against this job: included, left out, excluded or added, line by line.

Kept on this device**Figures**The page's opening**Units**Imperial Quantities only, never prices

## How the quote is read

Each line of an extension shell quote is matched to the line of the job it names, or marked as something the [Extension shell, one or two storeys takeoff](https://craftquantities.com/build/extension-shell/) does not measure — labour, removal, hire, fees, or anything else. Work the takeoff lists as part of the job but gives no quantity for is read as that work, not as something the quote adds.

The job’s own figures come from 14 measurements — width along the house, projection from the house, wall height for each storey, cavity wall thickness, doors and windows in the new walls, opening width, each, opening height, each, footing width, from the design, footing concrete depth, from the design, trench depth, damp-proof course above the ground, dig over the floor, roof slope factor, eaves overhang — run through the same calculators as the takeoff, so the two give the same figure for the same job.

## Reading an extension shell quote

An extension quote is written before anyone has seen what is under the lawn, and the groundwork is where two quotes for one drawing can part company. Worth asking what trench depth each price allows, what happens to the price if the inspector wants the trenches taken further down, and how the dug soil leaves the site; its weight, not its bulk, decides how many skips or grab loads it fills, so the number of loads each quote names is the figure to hold against the loads on this check.

The lines on this check stop where the building keeps the weather out, and a shell quote can stop somewhere else. Worth settling whether the price carries the doors and windows themselves, the roof tiles as well as the battens, the gutters with their downpipes and the drain they run to, and knocking through into the house with its steel, padstones and props; and whether the engineer's calculations, the building control fees and any party wall surveyor sit inside the figure or beside it.

## Three steps

1. Give your measurements, or fill them from your own takeoff in one press. The page opens on a typical job so it has something to show.
2. Paste the quote's lines as they came, or add them one at a time. Leave the prices in — they are taken out, never read.
3. Read the report: what is left out, what is added, what sits outside the range, and one list of questions to send.

The reference

## Every line the reading looks for

For Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in (US customary) / Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm (metric). Each is the calculator linked under it, run with those measurements; a range is that calculator at both ends of one choice, not a margin for error.

_US customary:_

- Footing trenches, dug

  13.8 yd³

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Dig over the floor

  7.92 yd³

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Footing concrete

  8.26–9.05 yd³

  8.26 at 5% waste factor, 9.05 at 15%.

  [Open the Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- Blocks below the damp-proof course, both leaves

  151–165 blocks

  151 at 5% waste factor, 165 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Hardcore under the slab

  6–6.9 tons

  Stone is bought by the tonne, and some is always lost into the formation and at the edges. 6 net, 6.9 with 15% added.

  [Open the Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)
- Floor insulation boards

  6–7 sheets (4x8 ft)

  6 at 5% cutting waste, 7 at 15%.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Floor slab concrete

  2.27–2.48 yd³

  2.27 at 5% waste factor, 2.48 at 15%.

  [Open the Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- Inner leaf blocks, clear of the openings

  260–285 blocks

  260 at 5% waste factor, 285 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Inner leaf blocks, above and below the openings

  18–20 blocks

  18 at 5% waste factor, 20 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Facing bricks, clear of the openings

  1,584–1,735 bricks

  1,584 at 5% waste factor, 1,735 at 15%.

  [Open the Brick Calculator](https://craftquantities.com/calculators/materials-quantities/brick-calculator/)
- Facing bricks, above and below the openings

  108–119 bricks

  108 at 5% waste factor, 119 at 15%.

  [Open the Brick Calculator](https://craftquantities.com/calculators/materials-quantities/brick-calculator/)
- Wall ties across the cavity

  at least 89 ties

  The fewest ties the area one tie may carry allows across this wall; the extra ties up the sides of an opening come on top, and a closer spacing is a choice.

  [Open the Brick Veneer Wall Tie Density Calculator](https://craftquantities.com/calculators/materials-quantities/wall-tie-density-calculator/)
- Cavity boards

  8–9 sheets (4x8 ft)

  8 at 5% cutting waste, 9 at 15%.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Weep holes at the damp course

  at least 23 weep holes

  The fewest weep holes the spacing allows along the base of this wall.

  [Open the Cavity Wall Weep Hole Spacing Calculator](https://craftquantities.com/calculators/materials-quantities/cavity-wall-weep-hole-calculator/)
- Lean-to rafters

  at least 10 trusses

  The fewest rafters or trusses the centres allow along this run, one at each end; closer centres are the designer's choice, and the bracing and straps are extra.

  [Open the Roof Truss Spacing & Count Calculator](https://craftquantities.com/calculators/materials-quantities/roof-truss-spacing-calculator/)
- Fascia along the eaves

  2 x 12 ft boards

  The same at 5% cut and scarf allowance and at 15%, once rounded to what is bought.

  [Open the Fascia Board Calculator](https://craftquantities.com/calculators/renovation-construction/fascia-board-calculator/)
- Underlay over the lean-to

  1 roll

  One figure, with the overlap allowance the material needs already inside it at 10%.

  [Open the Roofing Underlayment Calculator](https://craftquantities.com/calculators/renovation-construction/roofing-underlayment-calculator/)
- Flashing where the roof meets the house

  2–3 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 2 net, 3 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- Gutter along the eaves

  2 x 10 ft sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Gutter brackets

  at least 10 hangers

  The fewest hangers the spacing allows for the runs given, with at most one spare for each run after the first; closer hangers are a choice, often made for snow.

  [Open the Gutter Hanger Spacing Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-hanger-spacing-calculator/)
- Flashing tape round the openings

  94.5–103 ft

  94.5 at 5% waste allowance, 103 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Skip (dumpster) loads for the spoil

  at least 21.7 yd³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Setting-out diagonals

  21 ft

  Worked out, not compared with a quote

  The diagonal the footprint is squared to, which a quote does not list.

  [Open the Court Diagonal and Squaring Triangle Calculator](https://craftquantities.com/calculators/measurements-conversions/rectangle-diagonal-squaring-calculator/)
- Scaffold round the new walls

  340 sq ft of face

  Worked out, not compared with a quote

  The face the scaffold covers; a quote can price erecting, hire and striking as one sum, so one area is not held against it.

  [Open the Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)
- Batten courses up the slope

  15 rows

  Worked out, not compared with a quote

  A count of batten courses up one slope, from which the batten length follows; a quote lists battens by length or the roof by area.

  [Open the Roof Batten Spacing Calculator (Tile Roofing)](https://craftquantities.com/calculators/materials-quantities/roof-batten-spacing-calculator/)

_metric:_

- Footing trenches, dug

  9.75 m³ (loose)

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Dig over the floor

  6.11 m³ (loose)

  One figure, with the loose-volume allowance the material needs already inside it at 25%.

  [Open the Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- Footing concrete

  6.14–6.73 m³

  6.14 at 5% waste factor, 6.73 at 15%.

  [Open the Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- Blocks below the damp-proof course, both leaves

  108–119 blocks

  108 at 5% waste factor, 119 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Hardcore under the slab

  5.37–6.18 metric tons

  Stone is bought by the tonne, and some is always lost into the formation and at the edges. 5.37 net, 6.18 with 15% added.

  [Open the Gravel Base Layer Tonnage Calculator](https://craftquantities.com/calculators/materials-quantities/gravel-base-tonnage-calculator/)
- Floor insulation boards

  6–7 sheets (2400x1200 mm)

  6 at 5% cutting waste, 7 at 15%.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Floor slab concrete

  1.71–1.87 m³

  1.71 at 5% waste factor, 1.87 at 15%.

  [Open the Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- Inner leaf blocks, clear of the openings

  221–242 blocks

  221 at 5% waste factor, 242 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Inner leaf blocks, above and below the openings

  19–21 blocks

  19 at 5% waste factor, 21 at 15%.

  [Open the Concrete CMU Block Counter & Grout Infill Calculator](https://craftquantities.com/calculators/materials-quantities/cmu-block-grout-calculator/)
- Facing bricks, clear of the openings

  1,323–1,449 bricks

  1,323 at 5% waste factor, 1,449 at 15%.

  [Open the Brick Calculator](https://craftquantities.com/calculators/materials-quantities/brick-calculator/)
- Facing bricks, above and below the openings

  112–123 bricks

  112 at 5% waste factor, 123 at 15%.

  [Open the Brick Calculator](https://craftquantities.com/calculators/materials-quantities/brick-calculator/)
- Wall ties across the cavity

  at least 93 ties

  The fewest ties the area one tie may carry allows across this wall; the extra ties up the sides of an opening come on top, and a closer spacing is a choice.

  [Open the Brick Veneer Wall Tie Density Calculator](https://craftquantities.com/calculators/materials-quantities/wall-tie-density-calculator/)
- Cavity boards

  9–10 sheets (2400x1200 mm)

  9 at 5% cutting waste, 10 at 15%.

  [Open the Foam Board Insulation Calculator](https://craftquantities.com/calculators/insulation-efficiency/foam-board-insulation-calculator/)
- Weep holes at the damp course

  at least 23 weep holes

  The fewest weep holes the spacing allows along the base of this wall.

  [Open the Cavity Wall Weep Hole Spacing Calculator](https://craftquantities.com/calculators/materials-quantities/cavity-wall-weep-hole-calculator/)
- Lean-to rafters

  at least 10 trusses

  The fewest rafters or trusses the centres allow along this run, one at each end; closer centres are the designer's choice, and the bracing and straps are extra.

  [Open the Roof Truss Spacing & Count Calculator](https://craftquantities.com/calculators/materials-quantities/roof-truss-spacing-calculator/)
- Fascia along the eaves

  2 x 3.6 m boards

  The same at 5% cut and scarf allowance and at 15%, once rounded to what is bought.

  [Open the Fascia Board Calculator](https://craftquantities.com/calculators/renovation-construction/fascia-board-calculator/)
- Underlay over the lean-to

  1 roll

  One figure, with the overlap allowance the material needs already inside it at 10%.

  [Open the Roofing Underlayment Calculator](https://craftquantities.com/calculators/renovation-construction/roofing-underlayment-calculator/)
- Flashing where the roof meets the house

  4–5 sheets

  Flashing comes in stock pieces, each run is cut from its own, and the offcut at each end is lost. 4 net, 5 with 15% added.

  [Open the Exterior Flashing Layout Trim Sheet Calculator](https://craftquantities.com/calculators/materials-quantities/flashing-trim-sheet-calculator/)
- Gutter along the eaves

  2 x 4 m sections

  One figure, with the offcut allowance the material needs already inside it at 0%.

  [Open the Gutter Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-calculator/)
- Gutter brackets

  at least 10 hangers

  The fewest hangers the spacing allows for the runs given, with at most one spare for each run after the first; closer hangers are a choice, often made for snow.

  [Open the Gutter Hanger Spacing Calculator](https://craftquantities.com/calculators/renovation-construction/gutter-hanger-spacing-calculator/)
- Flashing tape round the openings

  28.4–31.1 m

  28.4 at 5% waste allowance, 31.1 at 15%.

  [Open the Window Opening Flashing Membrane Calculator](https://craftquantities.com/calculators/materials-quantities/opening-flashing-membrane-calculator/)
- Skip (dumpster) loads for the spoil

  at least 15.9 m³

  The loose volume the waste takes up; the container quoted is at least this big, and a bigger one is a choice.

  [Open the Skip & Dumpster Size Calculator](https://craftquantities.com/calculators/auto-utility/skip-and-dumpster-size-calculator/)
- Setting-out diagonals

  6.4 m

  Worked out, not compared with a quote

  The diagonal the footprint is squared to, which a quote does not list.

  [Open the Court Diagonal and Squaring Triangle Calculator](https://craftquantities.com/calculators/measurements-conversions/rectangle-diagonal-squaring-calculator/)
- Scaffold round the new walls

  32.5 m² of face

  Worked out, not compared with a quote

  The face the scaffold covers; a quote can price erecting, hire and striking as one sum, so one area is not held against it.

  [Open the Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)
- Batten courses up the slope

  15 rows

  Worked out, not compared with a quote

  A count of batten courses up one slope, from which the batten length follows; a quote lists battens by length or the roof by area.

  [Open the Roof Batten Spacing Calculator (Tile Roofing)](https://craftquantities.com/calculators/materials-quantities/roof-batten-spacing-calculator/)

## How the ranges are taken

Where the choice is cutting waste, the ends are the site’s own allowances: 5%, the tight buffer of a crew with a planned set-out, and 15%, the wider one a first-timer orders. Where the calculator decides between patterns or materials, the ends are the options it offers. Where it adds nothing for loss, the range runs from the net quantity to 15% over it.

A minimum — the fewest hangers a spacing allows, the least airflow a room needs — has no upper end. A single figure carries an allowance the material itself needs, such as a lap, and names it.

## What a reading like this cannot see

- It does not know your prices, your market, or what the work ought to cost.
- It does not know the building — the access, the condition of what is there, or what has to happen first.
- It cannot check a lump sum, because there is no quantity in one.
- A line it reads as missing may be priced under another name. A quantity outside the range is not evidence of anything. Each is a reason to ask a question.
- Two quotes are not comparable until their scopes are.
- It is not advice, and it is no substitute for a second quote.

The full takeoff

## Every quantity for this job, with its working

The Extension shell, one or two storeys takeoff runs the same calculators on the same measurements and shows what sits under each line here.

- [Open the takeoff](https://craftquantities.com/build/extension-shell/)
- [Every quote check](https://craftquantities.com/check/)

- Base, allowance, order

  Each line's quantity before and after its allowance, and what to buy.
- Every allowance editable

  Change a waste figure and the order follows, with its source named.
- Into a project

  Add the whole job to a workspace with your own prices.

## Frequently asked questions

**What quantities does an extension shell job need?**

It depends on the measurements, so this page asks for yours. At the size it opens on — Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm — the lines come to: Footing trenches, dug, 9.75 m³ (loose); Dig over the floor, 6.11 m³ (loose); Footing concrete, 6.14–6.73 m³; Blocks below the damp-proof course, both leaves, 108–119 blocks; Hardcore under the slab, 5.37–6.18 metric tons; Floor insulation boards, 6–7 sheets (2400x1200 mm); Floor slab concrete, 1.71–1.87 m³; Inner leaf blocks, clear of the openings, 221–242 blocks; Inner leaf blocks, above and below the openings, 19–21 blocks; Facing bricks, clear of the openings, 1,323–1,449 bricks; Facing bricks, above and below the openings, 112–123 bricks; Wall ties across the cavity, 93 ties; Cavity boards, 9–10 sheets (2400x1200 mm); Weep holes at the damp course, 23 weep holes; Lean-to rafters, 10 trusses; Fascia along the eaves, 2 x 3.6 m boards; Underlay over the lean-to, 1 roll; Flashing where the roof meets the house, 4–5 sheets; Gutter along the eaves, 2 x 4 m sections; Gutter brackets, 10 hangers; Flashing tape round the openings, 28.4–31.1 m; Skip (dumpster) loads for the spoil, 15.9 m³. In imperial units — Width along the house 16.5 ft · Projection from the house 13 ft · Wall height for each storey 8 ft · Cavity wall thickness 11.8 in · Doors and windows in the new walls 3 · Opening width, each 5 ft · Opening height, each 7 ft · Footing width, from the design 2 ft · Footing concrete depth, from the design 2.5 ft · Trench depth 3.5 ft · Damp-proof course above the ground 6 in · Dig over the floor 11.8 in · Roof slope factor 1.06 · Eaves overhang 11.8 in — they come to: Footing trenches, dug, 13.8 yd³; Dig over the floor, 7.92 yd³; Footing concrete, 8.26–9.05 yd³; Blocks below the damp-proof course, both leaves, 151–165 blocks; Hardcore under the slab, 6–6.9 tons; Floor insulation boards, 6–7 sheets (4x8 ft); Floor slab concrete, 2.27–2.48 yd³; Inner leaf blocks, clear of the openings, 260–285 blocks; Inner leaf blocks, above and below the openings, 18–20 blocks; Facing bricks, clear of the openings, 1,584–1,735 bricks; Facing bricks, above and below the openings, 108–119 bricks; Wall ties across the cavity, 89 ties; Cavity boards, 8–9 sheets (4x8 ft); Weep holes at the damp course, 23 weep holes; Lean-to rafters, 10 trusses; Fascia along the eaves, 2 x 12 ft boards; Underlay over the lean-to, 1 roll; Flashing where the roof meets the house, 2–3 sheets; Gutter along the eaves, 2 x 10 ft sections; Gutter brackets, 10 hangers; Flashing tape round the openings, 94.5–103 ft; Skip (dumpster) loads for the spoil, 21.7 yd³.

**Which line on an extension shell quote varies the most?**

The Flashing where the roof meets the house: 4–5 sheets for a job measured Width along the house 5 m · Projection from the house 4 m · Wall height for each storey 2.5 m · Cavity wall thickness 300 mm · Doors and windows in the new walls 3 · Opening width, each 1.5 m · Opening height, each 2.1 m · Footing width, from the design 0.6 m · Footing concrete depth, from the design 0.75 m · Trench depth 1 m · Damp-proof course above the ground 150 mm · Dig over the floor 300 mm · Roof slope factor 1.06 · Eaves overhang 300 mm, depending on how much is allowed for loss over the net figure, up to 15%.

**What does an extension shell quote often leave out?**

The reading names every line of the job that nothing on the quote reads as — any of the 22 lines the takeoff measures. The takeoff also lists 8 things it does not measure, shown under the reading, and each is worth asking about: a scope missing from a quote tends to become a cost after work has started.

**Can I paste the quote exactly as it came?**

Yes — from an email, a PDF or a spreadsheet, one item to a line. Amounts of money are taken out before anything is read, headings and totals are skipped, and each line is shown with what it was read as, so a misreading is one correction. Quantities in the other unit system are converted and the conversion is shown; a count of boxes is never compared with a count of tiles.

**Does this check the price as well?**

No. It reads quantities, never prices, and this site publishes none: an installed price moves with the market, the season, the access and the specification, so a figure for what the work ought to cost would give you confidence in a number nobody can defend. A quantity against your own measurements is checkable, and every figure here links to the calculator that produced it.

---
Source: https://craftquantities.com/check/extension-shell-quote/