# Permeable Reservoir Drawdown Time Calculator

> How long an aggregate stormwater reservoir takes to drain into the subgrade at the design infiltration rate, beside the drawdown limit your manual sets.

Page: https://craftquantities.com/calculators/sustainability-compliance/reservoir-drawdown-time-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-08-30, 2 published test vectors.

Reservoir drawdown time: 30.5 hours for Aggregate Reservoir Depth 18 in, the page's opening figures; on the metric page, 450 mm gives 30 hours. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Aggregate Reservoir Depth | `reservoirDepth` | 450 mm | 18 in | mm, cm, m, in, ft, yd; range 0.1–1.5 m |
| Aggregate Void Ratio | `voidRatio` | 0.4 | 0.4 | range 0.2–0.45 |
| Measured Subgrade Infiltration Rate (mm/hr) | `measuredInfiltrationRate` | 12 | 12 | range 0.5–300 |
| Design Safety Factor on the Measured Rate | `safetyFactor` | 2 | 2 | range 1–10 |
| Underdrain | `underdrain` | None — full infiltration section | None — full infiltration section | `none`, `present` |
| Underdrain Invert Height Above Subgrade | `underdrainInvertHeight` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0.02–1 m |
| Permitted Maximum Drawdown (hours) | `permittedDrawdownHours` | 48 | 48 | range 6–120 |

- **Aggregate Reservoir Depth**: Depth of the open-graded storage layer, measured from the subgrade up to the top of the reservoir stone.
- **Aggregate Void Ratio**: Fraction of the reservoir layer that is open void space rather than stone.
- **Measured Subgrade Infiltration Rate (mm/hr)**: Field-measured rate at the excavation bottom, before any safety factor is applied (1 in/hr is 25.4 mm/hr).
- **Design Safety Factor on the Measured Rate**: Divisor applied to the measured rate to obtain the design rate, as required by the governing manual.
- **Underdrain**: Whether a perforated underdrain relieves the upper part of the reservoir.
- **Underdrain Invert Height Above Subgrade**: Height of the pipe invert above the subgrade — everything below this line can only leave by infiltrating.
- **Permitted Maximum Drawdown (hours)**: The longest drawdown the governing manual allows for this system.

`underdrainInvertHeight` applies only when `underdrain` is `present`.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Reservoir drawdown time** | 30 hours |
| Design infiltration rate after the safety factor | 6 mm/hr |
| Depth of stored water that must infiltrate | 180 mm |
| Permitted maximum drawdown | 48 hours |
| Margin against the permitted maximum | 18 hours |

### US customary

| Result | Value |
|---|---|
| **Reservoir drawdown time** | 30.5 hours |
| Design infiltration rate after the safety factor | 0.24 in/hr |
| Depth of stored water that must infiltrate | 7.2 in |
| Permitted maximum drawdown | 48 hours |
| Margin against the permitted maximum | 17.52 hours |

- Confidence: medium.

## How it is worked out

The reservoir empties with about 18.0 hours in hand against the permitted maximum. That margin is only as good as the infiltration test behind it — a single test on a variable soil is thin evidence for a whole footprint.

The working the page shows, in order: Design infiltration rate after the safety factor; Depth of stored water that must infiltrate; Permitted maximum drawdown; Margin against the permitted maximum; then reservoir drawdown time.

The method, derived in full:

- [Stormwater, Runoff and the Water Balance](https://craftquantities.com/methodology/stormwater-and-water-balance/): Why a small catchment is designed for a more intense rainfall than a large one, why a detention basin can make things worse downstream, and why a rainwater tank delivers far less than annual rainfall times roof area.

What this calculation does not cover:

- One-dimensional vertical infiltration only: no credit is taken for lateral seepage out of the sides of the excavation, and none for evaporation.
- Assumes the reservoir starts full. A design storm that only part-fills it drains proportionally faster.

## Sources

As the calculator cites them (sources checked 2026-08-30):

- ASTM D3385, Standard Test Method for Infiltration Rate of Soils in Field Using Double-Ring Infiltrometer, is one accepted way of measuring the subgrade rate; the measurement is taken at the elevation of the finished excavation, not at the ground surface
- The safety factor applied to the measured rate and the permitted maximum drawdown time are both set by the governing stormwater manual, which is why both are entered here rather than supplied by this page
- Drawdown time = depth of stored water divided by the design infiltration rate; the stored water depth is the aggregate depth multiplied by its void ratio, since only the voids hold water

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why divide the measured rate by a safety factor at all?**

Because the number a double-ring test produces on a clean excavation bottom is the best the soil will ever do. Construction traffic, sediment carried in over the years, and natural variation across the footprint all move the real rate downwards, and the factor in the manual is the reviewer's allowance for that gap. Designing on the measured rate is designing on day one only.

**Why does the void ratio appear in a drawdown calculation?**

Because the reservoir is stone, not a pond. A 450 mm layer of open-graded aggregate at a void ratio of 0.4 holds only 180 mm of actual water, and it is that water depth — not the depth of the layer — that has to pass through the subgrade. Using the layer depth instead would overstate the drawdown time by roughly two and a half times.

**Does an underdrain make the drawdown check go away?**

No, it changes which part of the section the check applies to. Water above the pipe invert leaves through the pipe; the stone below it can still only empty into the soil, so that lower depth is what gets tested against the limit. Raising the invert is how a marginal soil is brought inside the window without abandoning infiltration altogether.

## Related calculators

- [PICP Permeable Pavement Infiltration Storage Calculator](https://craftquantities.com/calculators/sustainability-compliance/picp-infiltration-storage-calculator/)
- [Open-Graded Bedding Course Stone Calculator](https://craftquantities.com/calculators/materials-quantities/open-graded-bedding-course-calculator/)
- [Foundation Sheet Drain Drainage Rate Calculator](https://craftquantities.com/calculators/materials-quantities/sheet-drain-rate-calculator/)
- [French Drain Gravel Calculator](https://craftquantities.com/calculators/auto-utility/french-drain-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/reservoir-drawdown-time-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/reservoir-drawdown-time-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `reservoir-drawdown-time-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/reservoir-drawdown-time-calculator.json

---