# Underpinning Pit Excavation Volume Calculator

> Estimate the total excavation volume for a sequential (alternating) underpinning pit program.

Page: https://craftquantities.com/calculators/materials-quantities/underpinning-pit-volume-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-02, 2 published test vectors.

Total excavation volume: 13 yd³ for Number of Pits 5, the page's opening figures; on the metric page, 5 gives 9 m³. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Number of Pits | `pitCount` | 5 | 5 | range 1–100 |
| Pit Length | `pitLength` | 1.2 m | 4 ft | mm, cm, m, in, ft, yd; range 0.01–3 m |
| Pit Width | `pitWidth` | 1 m | 3.5 ft | mm, cm, m, in, ft, yd; range 0.01–2 m |
| Pit Depth | `pitDepth` | 1.5 m | 5 ft | mm, cm, m, in, ft, yd; range 0.01–6 m |

- **Number of Pits**: The total number of underpinning pits in the sequence.
- **Pit Length**: The length of each individual pit.
- **Pit Width**: The width of each pit.
- **Pit Depth**: The depth of each pit, down to the new bearing level.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Total excavation volume** | 9 m³ |
| Volume per pit | 1.8 m³ |

### US customary

| Result | Value |
|---|---|
| **Total excavation volume** | 13 yd³ |
| Volume per pit | 2.59 yd³ |

- Confidence: medium.

## How it is worked out

Doesn't include temporary shoring, dewatering, or the new underpinning concrete volume itself — this is excavation volume only.

The working the page shows, in order: Volume per pit; then total excavation volume.

The method, derived in full:

- [Volume from Geometry, and the Order That Follows](https://craftquantities.com/methodology/volume-from-geometry/): Why the depth carries almost all the risk in a volume, why an excavation holds far more than its plan area suggests, and why a bag's yield is not its weight divided by a density.

What this calculation does not cover:

- This is bank volume — soil measured as it sits in the ground. It bulks once it is on the shovel, so skip fills, grab loads and barrow runs all count a larger figure than this, by an amount that depends on the soil. None of it is backfilled either: the hole is filled with concrete, so the whole volume leaves site.
- The calculation takes the three dimensions exactly as typed and adds nothing to them. There is no allowance for working space, shutter and strut clearance, over-dig, or the toe projections a pin is designed to make beyond the existing footing — enter the footing width as the pit width and the dig comes out short.
- Every pit is treated as the same box repeated. Corners, returns, stepped footings, eccentric pins where projection is permitted one way only, and bays crossed by a live drain or service are all different shapes, and folding them into one average bay misprices the exceptions. Run the standard bay here and carry the odd ones as their own lines.
- This is a quantity take-off, not a design and not a temporary works check. Bay length, how many bays may stand open at once, how far apart they must be, the excavation support, and the depth needed to reach a stratum that will bear are decisions for the engineer who signs the sequence. Nothing here verifies that the dimensions you entered are safe to excavate beneath a loaded footing.
- The figure is neither the concrete order nor the price. The pin is cast short of the existing footing so the dry-pack joint can be rammed, and any blinding sits inside the same depth, so pit volume overstates the mass concrete — and a sequenced underpin is bought in visits per bay (dig, shutter, pour, strike, return to dry-pack, monitor, stand while the neighbouring bay makes strength), which does not scale with volume.

A professional must decide:

- This is a quantity take-off, not a design and not a temporary works check. Bay length, how many bays may stand open at once, how far apart they must be, the excavation support, and the depth needed to reach a stratum that will bear are decisions for the engineer who signs the sequence.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- Underpinning is typically excavated as a series of individual pits beneath an existing footing; total excavation volume = pit count x pit length x pit width x pit depth

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why is underpinning done in a sequence of small pits instead of one continuous trench?**

Excavating a continuous trench beneath a loaded footing would remove its support all at once and risk collapse — a sequenced, alternating pit pattern (leaving unexcavated sections between active pits) keeps the existing footing adequately supported throughout construction.

**How is pit sequence typically numbered?**

A common pattern is '1-in-4' or '1-in-5' sequencing, where every 4th or 5th pit is excavated and underpinned first, then the process repeats for the skipped sections once the first set has cured — never excavating two adjacent pits at the same time.

**Does this include the new underpinning concrete itself?**

No — this is excavation volume only. Use a general concrete volume calculator for the new footing/pier concrete once each pit is ready to pour.

## Related calculators

- [Continuous Footing / Grade Beam Volume Calculator](https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/)
- [Isolated Spread Footing Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/spread-footing-sizing-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/underpinning-pit-volume-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/underpinning-pit-volume-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `underpinning-pit-volume-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/underpinning-pit-volume-calculator.json

---