# Road Subgrade Excavation Truck Fleet Calculator

> Calculate how many dump truck loads are needed to haul away excavated subgrade material.

Page: https://craftquantities.com/calculators/materials-quantities/subgrade-excavation-truck-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-06, 2 published test vectors.

Truck loads needed: 17 truck loads for Total Excavated Volume 261.5 yd³ and Truck Bed Capacity 15.75 yd³, the page's opening figures; on the metric page, 200 m³ and 12 m³ give 17 truck loads. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Total Excavated Volume | `totalVolume` | 200 m³ | 261.5 yd³ | l, gal, m3, ft3, yd3; range 0.1–5000000 L |
| Truck Bed Capacity | `truckCapacity` | 12 m³ | 15.75 yd³ | l, gal, m3, ft3, yd3; range 0.1–20000 L |

- **Total Excavated Volume**: The total volume of subgrade material to be hauled off site.
- **Truck Bed Capacity**: The heaped or struck capacity of the dump truck bed being used for hauling.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Truck loads needed** | 17 truck loads |

### US customary

| Result | Value |
|---|---|
| **Truck loads needed** | 17 truck loads |

## How it is worked out

The method, derived in full:

- [Bulking, Swell and the Three Volumes of One Soil](https://craftquantities.com/methodology/bulking-and-swell/): Why a hundred cubic metres dug out becomes a hundred and twenty-five to cart away and ninety when it is put back, and why a cut-and-fill balance struck in the wrong state does not balance.

What this calculation does not cover:

- Fills the truck by VOLUME, and a haul truck usually fills by WEIGHT first. Payload is loose volume x loose density, and excavated wet clay at roughly 1.6 t/m³ (about 2,700 lb/yd³) puts 19 tonnes (21 tons) in a 12 m³ (16 yd³) box — past the legal axle load long before the material reaches the top of the sides. On heavy or saturated material the trip count comes off the truck's rated payload in tonnes, and this figure will be optimistic.
- Takes the rated bed capacity at face value. A heaped rating only holds for material that will stand in a heap: wet, sticky subgrade sheds off the sides, has to be sheeted, and leaves a skin in the box on every tip, so the volume actually moved per trip is nearer the struck capacity. Enter the struck figure for anything that will not heap.

## Sources

As the calculator cites them (sources checked 2026-09-06):

- Truck loads = ceil(total excavated volume ÷ truck bed capacity), the standard method for estimating haul truck trips for bulk excavation material

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why is the truck count rounded up?**

A partial truckload still requires a full trip, so the total volume divided by truck capacity is rounded up to the next whole truck load to ensure all material is accounted for.

**Does this account for soil swell (bulking) after excavation?**

No — this only divides the volume you enter by the truck capacity. If you are converting from in-place (bank) volume, apply a swell factor for your soil type first so the volume entered reflects the loose, hauled volume.

**Does this factor in haul distance or cycle time?**

No — this calculates the number of truck loads needed only. Total trucking time or fleet size needed per day depends on haul distance, cycle time, and loading rate, which are separate scheduling calculations.

## Related calculators

- [Trench Excavation & Backfill Volume Calculator](https://craftquantities.com/calculators/materials-quantities/trench-excavation-backfill-calculator/)
- [Slope Cut-and-Fill Earthwork Balance Calculator](https://craftquantities.com/calculators/materials-quantities/cut-fill-earthwork-balance-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/subgrade-excavation-truck-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/subgrade-excavation-truck-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `subgrade-excavation-truck-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/subgrade-excavation-truck-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/subgrade-excavation-truck-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.