# Soakaway Infiltration Rate Calculator (BRE 365 Trial Pit)

> The soil infiltration rate BRE Digest 365 takes from a trial pit: the water lost from 75% to 25% depth over the wetted area and time, on the slowest fill.

Page: https://craftquantities.com/calculators/materials-quantities/soakaway-infiltration-rate-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-22, 2 published test vectors.

Soil infiltration rate f (slowest fill): 0.44 in/h for Trial Pit Length 5 ft, Trial Pit Width 1.5 ft and Effective Depth of Water 3.5 ft, the page's opening figures; on the metric page, 1.5 m, 0.5 m and 1 m give 11.5 mm/h. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Trial Pit Length | `pitLength` | 1.5 m | 5 ft | mm, cm, m, in, ft, yd; range 0.3–5 m |
| Trial Pit Width | `pitWidth` | 0.5 m | 1.5 ft | mm, cm, m, in, ft, yd; range 0.3–3 m |
| Effective Depth of Water | `effectiveDepth` | 1 m | 3.5 ft | mm, cm, m, in, ft, yd; range 0.3–3 m |
| Fill 1: Time from 75% to 25% Depth (minutes) | `fill1Minutes` | 580 | 580 | range 1–20000 |
| Fill 2: Time from 75% to 25% Depth (minutes, 0 if not run) | `fill2Minutes` | 660 | 660 | range 0–20000 |
| Fill 3: Time from 75% to 25% Depth (minutes, 0 if not run) | `fill3Minutes` | 710 | 710 | range 0–20000 |

- **Trial Pit Length**: The pit's internal length at the level of the test.
- **Trial Pit Width**: The pit's internal width.
- **Effective Depth of Water**: The depth of water the pit is filled to, from its base to the marked fill level.
- **Fill 1: Time from 75% to 25% Depth (minutes)**: The minutes the level took to fall from the 75% mark to the 25% mark on the first fill.
- **Fill 2: Time from 75% to 25% Depth (minutes, 0 if not run)**: The minutes the level took to fall from the 75% mark to the 25% mark on the second fill.
- **Fill 3: Time from 75% to 25% Depth (minutes, 0 if not run)**: The minutes the level took to fall from the 75% mark to the 25% mark on the third fill.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Soil infiltration rate f (slowest fill)** | 11.5 mm/h |
| Water lost between the 75% and 25% marks | 0.38 m³ |
| Wetted area to half depth, base included | 2.75 m² |
| Slowest fill, 75% to 25% | 710 min |
| Rate from fill 1 | 14.11 mm/h |
| Rate from fill 2 | 12.4 mm/h |
| Rate from fill 3 | 11.52 mm/h |

### US customary

| Result | Value |
|---|---|
| **Soil infiltration rate f (slowest fill)** | 0.44 in/h |
| Water lost between the 75% and 25% marks | 0.49 yd³ |
| Wetted area to half depth, base included | 30.25 sq ft |
| Slowest fill, 75% to 25% | 710 min |
| Rate from fill 1 | 0.54 in/h |
| Rate from fill 2 | 0.47 in/h |
| Rate from fill 3 | 0.44 in/h |

## How it is worked out

BRE Digest 365 states the same rate as 3.2 × 10⁻⁶ m/s, the figure the storage and half-emptying sums take. The design runs on the slowest of the three fills, the one closest to the ground's wet-season condition.

The working the page shows, in order: Water lost between the 75% and 25% marks; Wetted area to half depth, base included; Slowest fill, 75% to 25%; Rate from fill 1; Rate from fill 2; Rate from fill 3; then soil infiltration rate f (slowest fill).

The method, derived in full:

- [Stormwater, Runoff and the Water Balance](https://craftquantities.com/methodology/stormwater-and-water-balance/): Why a small catchment is designed for a more intense rainfall than a large one, why a detention basin can make things worse downstream, and why a rainwater tank delivers far less than annual rainfall times roof area.

What this calculation does not cover:

- The trial pit's area is taken to half depth INCLUDING its base; the soakaway's own area in the storage sum is the sides only, because a soakaway's base silts up. Using the pit's figure for the finished soakaway overstates what it will drain.
- It measures the horizon the pit was dug in. A pit that stops in topsoil above a clay, or a rate measured in the first spit, says nothing about the ground the soakaway will actually sit in.
- A rate from one location on one day. Ground varies across a site and through the year, a rising water table stops a soakaway working, and building control may ask for a test in the wetter months.

A professional must decide:

- A rate from one location on one day. Ground varies across a site and through the year, a rising water table stops a soakaway working, and building control may ask for a test in the wetter months.

## Sources

As the calculator cites them (sources checked 2026-09-22):

- BRE Digest 365 Soakaway design: the soil infiltration rate f = Vp75–25 ÷ (ap50 × tp75–25), where Vp75–25 is the volume of water in the pit between 75% and 25% of the effective depth, ap50 the internal surface area of the pit up to 50% of the effective depth including the base, and tp75–25 the time for the level to fall from 75% to 25%; the pit is filled three times and the lowest rate is used

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why the middle half of the drop, from 75% to 25%?**

Because the ends are untrustworthy. The first minutes are dominated by whatever the excavator smeared onto the sides, and the last by the base, which in a finished soakaway is assumed to silt up and stop working. The middle half is the part of the fall that behaves like the soakaway will.

**Why use the slowest of three fills?**

The first fill is influenced by how dry the ground was when the test started; by the third the ground is closer to the wetted condition a soakaway lives in through a wet winter. Designing on the slowest — the longest time and lowest rate — is designing for that condition rather than for the first drink.

**How does this rate compare between units?**

The Digest writes it in metres per second, drainage practice often in millimetres or inches per hour. The guide's pit gives 3.2 × 10⁻⁶ m/s, which is 11.5 mm/h or 0.45 in/h — a sandy clay: not a refusal, but nowhere near free-draining.

## Related calculators

- [Soakaway Storage and Half-Emptying Time Calculator (BRE 365)](https://craftquantities.com/calculators/materials-quantities/soakaway-storage-half-emptying-calculator/)
- [Permeable Reservoir Drawdown Time Calculator](https://craftquantities.com/calculators/sustainability-compliance/reservoir-drawdown-time-calculator/)
- [French Drain Gravel Calculator](https://craftquantities.com/calculators/auto-utility/french-drain-calculator/)
- [Rational Method Peak Runoff Calculator](https://craftquantities.com/calculators/heavy-civil/rational-method-peak-runoff-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/soakaway-infiltration-rate-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/soakaway-infiltration-rate-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `soakaway-infiltration-rate-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/soakaway-infiltration-rate-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/soakaway-infiltration-rate-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.