# Skylight Curb Timber Calculator

> The four cut pieces of a skylight curb from the rough opening, and how far the chosen board stands above the finished roof once the covering is on.

Page: https://craftquantities.com/calculators/materials-quantities/skylight-curb-timber-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-20, 2 published test vectors.

Curb stock needed: 15.2 ft for Rough Opening Length 55 in, Rough Opening Width 31 in and Curb Stock Thickness 1.5 in, the page's opening figures; on the metric page, 1400 mm, 780 mm and 38 mm give 4.63 m. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Rough Opening Length | `openingLength` | 1400 mm | 55 in | mm, cm, m, in, ft, yd; range 0.3–3 m |
| Rough Opening Width | `openingWidth` | 780 mm | 31 in | mm, cm, m, in, ft, yd; range 0.3–3 m |
| Curb Stock Thickness | `stockThickness` | 38 mm | 1.5 in | mm, cm, m, in, ft, yd; range 0.015–0.1 m |
| Curb Stock Depth (Board Width, On Edge) | `stockDepth` | 184 mm | 7.25 in | mm, cm, m, in, ft, yd; range 0.08–0.4 m |
| Thickness of the Covering Running Up to the Curb | `roofingThickness` | 30 mm | 1.25 in | mm, cm, m, in, ft, yd; range 0–0.2 m |
| Height Wanted Above the Finished Roof | `targetHeight` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0.05–0.4 m |
| Number of Skylights | `curbCount` | 1 | 1 | range 1–40 |
| Waste Allowance (%) | `wasteAllowance` | 10 | 10 | range 0–40 |

- **Rough Opening Length**: The long dimension of the framed hole, measured up the slope.
- **Rough Opening Width**: The dimension across the slope, between the trimmed rafters.
- **Curb Stock Thickness**: The actual thickness of the board, not its nominal name.
- **Curb Stock Depth (Board Width, On Edge)**: How far the board stands off the deck — this is what sets the curb height.
- **Thickness of the Covering Running Up to the Curb**: Everything between the deck and the weather surface at the curb.
- **Height Wanted Above the Finished Roof**: The clearance your unit's instructions call for, measured from the weather surface.
- **Number of Skylights**: How many curbs of this size are being built.
- **Waste Allowance (%)**: The margin for saw kerfs, a split end and one piece cut the wrong way.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Curb stock needed** | 4.63 m |
| Two long pieces per curb, cut to | 1,400 mm |
| Two short pieces per curb, cut to | 704 mm |
| Stock per curb before waste | 4.21 m |
| Height this board stands above the finished roof | 154 mm |
| Clear of the height you asked for by | 4 mm |

### US customary

| Result | Value |
|---|---|
| **Curb stock needed** | 15.2 ft |
| Two long pieces per curb, cut to | 55 in |
| Two short pieces per curb, cut to | 28 in |
| Stock per curb before waste | 13.83 ft |
| Height this board stands above the finished roof | 6 in |
| Clear of the height you asked for by | 0 in |

- Allowance in the figure: Cutting allowance (10%).

## How it is worked out

The cut list is exact arithmetic on the dimensions you entered. The height is only as good as the covering thickness you gave it, which is the figure most often taken at the roof's thinnest point rather than where it meets the curb.

The working the page shows, in order: Two long pieces per curb, cut to; Two short pieces per curb, cut to; Stock per curb before waste; Height this board stands above the finished roof; Clear of the height you asked for by; then curb stock needed.

The method, derived in full:

- [Perimeter Runs, Stock Lengths and Mitres](https://craftquantities.com/methodology/perimeter-runs-and-mitres/): Why a room's area tells you nothing about how much skirting it needs, why adding a door can increase the trim order, and why a crown moulding mitre is neither forty-five degrees nor half the corner angle.

What this calculation does not cover:

- It does not decide whether your skylight needs a curb at all. Deck-mounted units are flashed straight to the roof plane and have no curb; curb-mounted units need one, and which you have is on the unit's own instructions.
- It does not size the framing around the opening. The trimmers and headers that carry the cut rafters are a structural question and a different page.
- The height check compares your board against a target YOU enter. It is arithmetic, not approval — the number that governs is in the manufacturer's instructions for your unit and your covering, and a shortfall reported here is a prompt to read them rather than a verdict.

A professional must decide:

- It does not size the framing around the opening. The trimmers and headers that carry the cut rafters are a structural question and a different page.

## Sources

As the calculator cites them (sources checked 2026-09-20):

- A curb is built to the rough opening's outside dimensions and stood on the deck, so two pieces run the full opening and two fit between them: stock length per curb = 2 × opening length + 2 × (opening width − 2 × stock thickness)
- The height that matters is measured from the FINISHED roof surface, not the deck — height above the roof = board depth − the thickness of the covering build-up running up to the curb
- Curb height is set by the skylight manufacturer's installation instructions and by the covering. North American instructions commonly call for at least 4 in (100 mm) above the finished roof; 150 mm is the usual upstand in UK and European practice, and a low pitch or a snow site wants more than either

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does the board depth decide the height instead of me entering a height?**

Because a curb is boards on edge, and you buy boards in the widths a merchant stocks. Entering a height would let you specify 165 mm and then discover that nothing between 140 and 184 exists. Choosing the board and reading off what height it buys is the order the job actually happens in, and it is why this page reports a shortfall rather than a size.

**Does the covering thickness really matter that much?**

It is usually the difference between a curb that works and one that does not. A 2x6 curb stands 140 mm off the deck, which is comfortably above a 4 in minimum — until 30 mm of shingle and membrane runs up to it and leaves 110, or until battens and tiles take 90 mm and leave 50. Nothing about the curb changed; the roof grew underneath it.

**Should the curb be built to the outside or the inside of the rough opening?**

This page assumes outside, which is the common instruction: the curb's outer faces sit flush with the framed hole, so it lands on the trimmers and the deck rather than overhanging the void. If your unit's instructions size the curb to the inside instead, add twice the stock thickness to both opening dimensions before entering them, and the cut list comes out right.

**Why is there no fixing or fastener count?**

Because how a curb is fixed depends on what it lands on and how the roof is framed, and a count of screws would be the least useful thing on the page. The one thing worth saying is that a curb is squared and fixed before any flashing arrives — a curb racked out of square cannot be corrected once the step flashing is woven into the covering.

## Related calculators

- [Skylight Rough Opening Calculator](https://craftquantities.com/calculators/materials-quantities/skylight-rough-opening-calculator/)
- [Skylight Curb Perimeter Flashing Length Calculator](https://craftquantities.com/calculators/materials-quantities/skylight-curb-flashing-calculator/)
- [Roof Cricket (Saddle) Framing Calculator](https://craftquantities.com/calculators/materials-quantities/roof-cricket-framing-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/skylight-curb-timber-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/skylight-curb-timber-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `skylight-curb-timber-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/skylight-curb-timber-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/skylight-curb-timber-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.