# Rooftop Unit Curb Flashing Calculator

> Calculate the flashing material needed around a rooftop mechanical unit curb, with waste allowance.

Page: https://craftquantities.com/calculators/materials-quantities/roof-curb-flashing-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-08-26, 2 published test vectors.

Curb flashing needed: 28.1 ft for Curb Perimeter 26 ft, the page's opening figures; on the metric page, 8 m gives 8.64 m. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Curb Perimeter | `curbPerimeter` | 8 m | 26 ft | mm, cm, m, in, ft, yd; range 0.01–50 m |
| Waste Allowance (%) | `wastePercent` | 8 | 8 | range 0–20 |

- **Curb Perimeter**: The full perimeter of the rooftop unit curb.
- **Waste Allowance (%)**: Extra material to allow for corner cuts, overlaps, and offcuts.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Curb flashing needed** | 8.64 m |

### US customary

| Result | Value |
|---|---|
| **Curb flashing needed** | 28.1 ft |

## How it is worked out

Curb flashing is measured on the curb's perimeter, but its performance depends on the curb's height above the finished roof surface and on whether the upslope side sheds water around the curb rather than into it.

The method, derived in full:

- [Quantity, Waste and Rounding](https://craftquantities.com/methodology/quantity-waste-and-rounding/): Why a material count is a ceiling function rather than a division, and why the waste factor — not the geometry — carries the risk.

What this calculation does not cover:

- Excludes the cricket or saddle needed on the upslope side of any wide curb, which is a fabricated item sized from the curb width and the roof slope.
- Corner pieces are fabricated units rather than cut from a run and are priced individually.
- Does not verify curb height. A curb too low for the covering system leaves nowhere for the upstand to terminate above standing water.

## Sources

As the calculator cites them (sources checked 2026-08-26):

- Total curb flashing = curb perimeter × (1 + waste allowance), the standard method for estimating continuous flashing around a roof curb penetration

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does a curb need a cricket on the upslope side?**

Because a curb sitting across the fall is a dam. Water running down the roof collects against its upslope face, ponds there, and finds the weakest point in the flashing. A cricket is a small ridge behind the curb that splits the flow and sends it around both sides. Above a modest curb width it stops being optional.

**How high should the curb be?**

High enough that the membrane upstand terminates well clear of any water that can stand or back up against it — commonly a minimum stated in the membrane manufacturer's details, measured from the finished roof surface rather than from the deck. Insulation thickness eats into that height, and a curb detailed from the deck level is frequently too short once the build-up is on.

**Can the flashing be run continuously round the corners?**

Not reliably in sheet metal. Corners are formed or welded units because a folded corner in a continuous run leaves a pinhole at the fold that no amount of sealant closes permanently. In single-ply membrane systems the corners are preformed moulded pieces for the same reason.

**What fails first on a curb detail?**

The upslope corner, almost always — it is the point where ponding, a change of direction and a fabricated joint all coincide. It is worth inspecting there first on any roof with a leak near a rooftop unit, and worth detailing there most carefully on a new one.

## Related calculators

- [Roof Hatch Curb Flashing Calculator](https://craftquantities.com/calculators/materials-quantities/roof-hatch-curb-flashing-calculator/)
- [Modified Bitumen Cap Sheet Scrap Factor Calculator](https://craftquantities.com/calculators/materials-quantities/modified-bitumen-scrap-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/roof-curb-flashing-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/roof-curb-flashing-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `roof-curb-flashing-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/roof-curb-flashing-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/roof-curb-flashing-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.