# Raft Slab Concrete Volume Calculator (Edge Thickenings and Downstands)

> The concrete in a raft or ground-bearing slab and the thickenings the plan does not show: edge bands, internal downstands and pads, plus waste.

Page: https://craftquantities.com/calculators/materials-quantities/raft-slab-thickenings-volume-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-22, 3 published test vectors.

Concrete to order, waste included: 21.7 yd³ for Slab Length 33 ft, Slab Width 26 ft and Slab Thickness 6 in, the page's opening figures; on the metric page, 10 m, 8 m and 150 mm give 16.5 m³. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Slab Length | `slabLength` | 10 m | 33 ft | mm, cm, m, in, ft, yd; range 1–200 m |
| Slab Width | `slabWidth` | 8 m | 26 ft | mm, cm, m, in, ft, yd; range 1–200 m |
| Slab Thickness | `slabThickness` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0.075–1.5 m |
| Edge Thickening Width at Its Base (0 if none) | `edgeWidth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0–2 m |
| Edge Thickening Depth Below the Slab | `edgeDepth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0–2 m |
| Inner Face of the Edge Thickening | `edgeInnerFace` | Vertical | Vertical | `vertical`, `haunch-45` |
| Internal Downstands — Total Length (0 if none) | `internalLength` | 8 m | 26 ft | mm, cm, m, in, ft, yd; range 0–1000 m |
| Internal Downstand Width | `internalWidth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0–2 m |
| Internal Downstand Depth Below the Slab | `internalDepth` | 250 mm | 9.75 in | mm, cm, m, in, ft, yd; range 0–2 m |
| Pad Thickenings (count, 0 if none) | `padCount` | 0 | 0 | range 0–200 |
| Pad Length | `padLength` | 1 m | 3.5 ft | mm, cm, m, in, ft, yd; range 0–10 m |
| Pad Width | `padWidth` | 1 m | 3.5 ft | mm, cm, m, in, ft, yd; range 0–10 m |
| Pad Depth Below the Slab | `padDepth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0–3 m |
| Waste Allowance (%) | `wastePercent` | 5 | 5 | range 0–20 |

- **Slab Length**: The slab's overall length.
- **Slab Width**: The slab's overall width.
- **Slab Thickness**: The general thickness of the slab away from the thickenings.
- **Edge Thickening Width at Its Base (0 if none)**: The flat width of the thickened band round the perimeter, measured at its underside.
- **Edge Thickening Depth Below the Slab**: How far the thickened edge goes below the underside of the slab.
- **Inner Face of the Edge Thickening**: A thickened edge often slopes back to the slab on its inner side rather than stepping down vertically.
- **Internal Downstands — Total Length (0 if none)**: The total length of thickenings under internal walls, between the edge thickenings.
- **Internal Downstand Width**: The width of the internal thickenings.
- **Internal Downstand Depth Below the Slab**: How far the internal thickenings go below the slab.
- **Pad Thickenings (count, 0 if none)**: Local thickenings under columns or point loads.
- **Pad Length**: The length of one pad thickening.
- **Pad Width**: The width of one pad thickening.
- **Pad Depth Below the Slab**: How far one pad goes below the slab.
- **Waste Allowance (%)**: An allowance for over-dig, the sub-base's surface and spillage.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Concrete to order, waste included** | 16.5 m³ |
| Slab | 12 m³ |
| Edge thickening | 3.13 m³ |
| Internal downstands | 0.6 m³ |
| Pad thickenings | 0 m³ |
| Concrete before waste | 15.73 m³ |

### US customary

| Result | Value |
|---|---|
| **Concrete to order, waste included** | 21.7 yd³ |
| Slab | 15.89 yd³ |
| Edge thickening | 4.05 yd³ |
| Internal downstands | 0.77 yd³ |
| Pad thickenings | 0 yd³ |
| Concrete before waste | 20.71 yd³ |

## How it is worked out

The slab and everything below it that the section shows, with the edge band's corners counted once. The thickenings are the part of a raft most often left off a take-off, because the plan does not draw them.

The working the page shows, in order: Slab; Edge thickening; Internal downstands; Pad thickenings; Concrete before waste; then concrete to order, waste included.

The method, derived in full:

- [Volume from Geometry, and the Order That Follows](https://craftquantities.com/methodology/volume-from-geometry/): Why the depth carries almost all the risk in a volume, why an excavation holds far more than its plan area suggests, and why a bag's yield is not its weight divided by a density.

What this calculation does not cover:

- A rectangular raft. An L-shaped or stepped raft is taken as rectangles, each run on its own, with the edge band only on the outside faces.
- The internal downstands are taken at the length you give; measure each between the inner faces of the edge band so the crossings are not counted twice.
- It is the concrete only: the sub-base, blinding, membrane, insulation and reinforcement are separate lines, and the thickness of any blinding below the thickenings adds to the dig, not to the pour.

A professional must decide:

- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-09-22):

- Volume from the plan and the section: slab area × thickness, plus each thickening's length × width × depth below the slab; a perimeter band of width b round an L × W slab has a centre line of 2(L + W) − 4b, so its corners are counted once
- A 45° inner face on the edge thickening adds a triangle of depth² ÷ 2, run along its own centroid line, 2(L + W) − 8(b + depth ÷ 3)

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does a raft take more concrete than its plan area times its thickness?**

Because the plan gives the area and only the section gives the depths — the thickened edge under the external walls, downstands under internal ones, pads under columns. On a 10 by 8 m (33 by 26 ft) raft 150 mm (6 in) thick, a 300 by 300 mm (12 by 12 in) edge band alone adds 3.1 m³ (4.1 yd³) to the slab's 12 m³ (15.7 yd³), about a quarter.

**Why is the edge band's length 2(L + W) − 4b?**

Because measuring round the outside counts every corner twice. The band's centre line is inset half its width from each edge, so its length is the outside perimeter less four times the width, and with that length the corners look after themselves.

**Should the waste allowance be larger than for a flat slab?**

Often, because the thickenings are dug rather than formed, and a machine-dug trench is trimmed to a tolerance rather than to a line. The concrete fills the hole, not the drawing; ACI 117 sets out the tolerances on formed and excavated surfaces that explain how much more.

## Related calculators

- [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- [Concrete Slab + Rebar Combined Mass Calculator](https://craftquantities.com/calculators/materials-quantities/slab-rebar-combined-mass-calculator/)
- [Under-Slab Perimeter Rigid Foam Board Calculator](https://craftquantities.com/calculators/materials-quantities/under-slab-perimeter-foam-calculator/)
- [Concrete Steps Volume Calculator (Solid and Waist-Slab Flights)](https://craftquantities.com/calculators/materials-quantities/concrete-steps-volume-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/raft-slab-thickenings-volume-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/raft-slab-thickenings-volume-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `raft-slab-thickenings-volume-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/raft-slab-thickenings-volume-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/raft-slab-thickenings-volume-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.