# Pier Adfreeze Uplift Calculator

> Check a frost-zone pier: adfreeze bond dragging the shaft up, against the dead load, self-weight and bell holding it down.

Page: https://craftquantities.com/calculators/materials-quantities/pier-adfreeze-uplift-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-08-30, 3 published test vectors.

Net uplift on the pier: 13.3 kips for Design Frost Depth 5 ft, Shaft Diameter 11.75 in and Adfreeze Bond Stress 9.43 psi, the page's opening figures; on the metric page, 1.5 m, 300 mm and 65 kPa give 58.9 kN. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Design Frost Depth | `frostDepth` | 1.5 m | 5 ft | mm, cm, m, in, ft, yd; range 0.3–4 m |
| Shaft Diameter | `shaftDiameter` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0.1–1.2 m |
| Adfreeze Bond Stress | `adfreezeStress` | 65 kPa | 9.42745 psi | pa, kpa, mpa, psi, psf, in_wc; range 5000–300000 Pa |
| Dead Load Carried | `deadLoad` | 20 kN | 4.49618 kip | n, kn, lbf, kip; range 0–2000000 N |
| Total Pier Depth | `pierLength` | 2.4 m | 8 ft | mm, cm, m, in, ft, yd; range 0.5–8 m |
| Bell or Pad Diameter | `bellDiameter` | 600 mm | 24 in | mm, cm, m, in, ft, yd; range 0.1–2 m |
| Soil Bulk Density | `soilDensity` | 1800 kg/m³ | 112.37 pcf | kgm3, pcf, lbyd3; range 1200–2400 kg/m³ |
| Vertical Steel Area (mm²) | `verticalSteelArea` | 800 | 800 | range 100–8000 |

- **Design Frost Depth**: The design frost penetration at this site.
- **Shaft Diameter**: The outside diameter of the pier shaft through the frost zone.
- **Adfreeze Bond Stress**: The bond stress developed between frozen soil and the shaft face.
- **Dead Load Carried**: The permanent load the pier carries, with no live or snow contribution.
- **Total Pier Depth**: Depth from finished grade to the underside of the base or bell.
- **Bell or Pad Diameter**: Diameter of the bell or footing pad at the base of the pier.
- **Soil Bulk Density**: Bulk density of the soil resting over the projecting bell.
- **Vertical Steel Area (mm²)**: Combined cross-sectional area of the vertical bars, in square millimetres.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Net uplift on the pier** | 58.9 kN |
| Adfreeze uplift on the shaft | 91.89 kN |
| Restraint from dead load, pier and bell | 32.98 kN |
| Tension the vertical steel must carry | 58.92 kN |
| Stress in the vertical steel | 73.64 MPa |
| Bonded shaft area inside the frost zone | 1.41 m² |

### US customary

| Result | Value |
|---|---|
| **Net uplift on the pier** | 13.3 kips |
| Adfreeze uplift on the shaft | 20.88 kips |
| Restraint from dead load, pier and bell | 7.55 kips |
| Tension the vertical steel must carry | 13.33 kips |
| Stress in the vertical steel | 10,753.32 psi |
| Bonded shaft area inside the frost zone | 15.38 sq ft |

- Confidence: medium.

## How it is worked out

Adfreeze exceeds the restraint, so the vertical steel is in tension and has to be developed into both the bell and the cap. The bond stress you entered governs this answer — run it high and low before treating the result as settled.

The working the page shows, in order: Adfreeze uplift on the shaft; Restraint from dead load, pier and bell; Tension the vertical steel must carry; Stress in the vertical steel; Bonded shaft area inside the frost zone; then net uplift on the pier.

The method, derived in full:

- [Pile Capacity: Shaft Friction, End Bearing, and the Sign That Reverses](https://craftquantities.com/methodology/pile-capacity/): Why shaft friction and end bearing cannot simply be added at working load, why settling ground turns friction from a resistance into a load, and why ten piles do not carry ten times what one does.

What this calculation does not cover:

- This is a single-pier force balance. It does not check bearing, lateral capacity, bar development length or the bell's own structural strength.
- Heave forces from ice lensing beneath the base are a separate mechanism and are not included.
- Group effects, sloping ground and a pier alongside a heated structure all change the frost regime and are outside this calculation.

A professional must decide:

- This is a single-pier force balance. It does not check bearing, lateral capacity, bar development length or the bell's own structural strength.
- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-08-30):

- Uplift = adfreeze bond stress × the shaft's bonded surface area inside the frost zone (π × diameter × frost depth). Restraint = dead load + pier self-weight + the weight of soil standing over the bell's projecting annulus.
- The adfreeze bond stress is a SITE-SPECIFIC soil property you supply from the geotechnical report; this page applies no table of published values, because bond stress varies with soil type, moisture, freezing rate and shaft finish.
- ASCE/SEI 32, Design and Construction of Frost-Protected Shallow Foundations — the standard the frost-heave design case belongs to
- ACI 318, Building Code Requirements for Structural Concrete — the code governing development of the vertical bars that carry the tension computed here
- Normalweight concrete self-weight taken as 2,400 kg/m³ (about 150 pcf), the conventional design value

The site's pages for the documents these name:

- [ACI 318](https://craftquantities.com/standards/aci/aci-318/)

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What is adfreeze, and why does it lift a pier that is below frost depth?**

Freezing soil bonds to the side of the shaft and then heaves upward as ice lenses grow. The bond drags the pier with it. Going below frost depth protects the base from heaving underneath, but it does nothing about the grip on the sides, which is why a correctly deep pier can still jack out over several winters.

**Why is live load excluded from the restraint?**

Because adfreeze does its work in midwinter, and the load you can count on then is the load that is physically bolted down. Decks are empty, unheated structures are unoccupied, and a frame part-way through construction may carry nothing at all. Restraint from anything removable is restraint you may not have on the night it matters.

**How much does the bell actually contribute?**

At the page's defaults about 9 kN (2 kips): the weight of the soil standing over the ring a 600 mm (24 in) bell projects past a 300 mm (about 12 in) shaft, which is the part this calculation counts. A bell barely wider than the shaft adds almost nothing; a generous one under a deep pier can hold down several times the pier's own weight. Widening the bell is generally cheaper than deepening the pier.

**Would insulating around the pier help instead?**

It can, by keeping the surrounding ground from freezing hard against the shaft in the first place — that is the strategy ASCE/SEI 32 is built around. It is a different design route from resisting the force, and this page sizes only the resisting one. A smooth sleeve that breaks the bond is a third route again.

## Related calculators

- [Drilled Pier Concrete Volume Calculator (Straight Shaft / Belled)](https://craftquantities.com/calculators/materials-quantities/drilled-pier-volume-calculator/)
- [Foundation Frost-Protection Insulation Depth Calculator](https://craftquantities.com/calculators/materials-quantities/foundation-frost-insulation-calculator/)
- [Deck Footing Calculator](https://craftquantities.com/calculators/renovation-construction/deck-footing-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/pier-adfreeze-uplift-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/pier-adfreeze-uplift-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `pier-adfreeze-uplift-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/pier-adfreeze-uplift-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/pier-adfreeze-uplift-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.