# Heated Screed Volume Calculator

> Screed quantity for an underfloor heating build-up, taking the cover over the tube crown and subtracting what the tube itself displaces.

Page: https://craftquantities.com/calculators/materials-quantities/heated-screed-volume-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-02, 3 published test vectors.

Screed volume required: 6.8 yd³ for Heated Floor Area 860 sq ft, Cover Over the Tube Crown 1.75 in and Tube Outside Diameter 0.63 in, the page's opening figures; on the metric page, 80 m², 45 mm and 16 mm give 5.25 m³. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Heated Floor Area | `floorArea` | 80 m² | 860 sq ft | m2, ft2, mm2, in2; range 1–1000 m² |
| Cover Over the Tube Crown | `coverDepth` | 45 mm | 1.75 in | mm, cm, m, in, ft, yd; range 0.015–0.15 m |
| Tube Outside Diameter | `tubeOuterDiameter` | 16 mm | 0.63 in | mm, cm, m, in, ft, yd; range 0.008–0.032 m |
| Tube Centres | `tubeCentres` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0.075–0.4 m |
| Hardened Screed Density | `screedDensity` | 2100 kg/m³ | 131.099 pcf | kgm3, pcf, lbyd3; range 1200–2500 kg/m³ |
| Yield per Bag | `bagYield` | 13 L | 0.5 ft³ | l, gal, m3, ft3, yd3; range 5–40 L |
| Waste Allowance (%) | `wasteAllowance` | 10 | 10 | range 0–30 |

- **Heated Floor Area**: The floor area the screed covers.
- **Cover Over the Tube Crown**: Screed depth measured from the top of the tube to the finished surface.
- **Tube Outside Diameter**: Outside diameter of the heating tube itself.
- **Tube Centres**: Centre-to-centre spacing of the tube runs across the floor.
- **Hardened Screed Density**: Density of the hardened screed mix being placed.
- **Yield per Bag**: The finished volume one bag makes up, taken from the bag itself.
- **Waste Allowance (%)**: Extra for an uneven substrate, spillage and the mixer's leavings.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Screed volume required** | 5.25 m³ |
| Screed thickness over the substrate | 61 mm |
| Volume before the tube displacement is taken out | 4.88 m³ |
| Volume displaced by the tube | 0.11 m³ |
| Length of tube in the floor | 533.33 m |
| Screed mass at the density entered | 11.03 tonnes |
| Bags to order | 404 bags |

### US customary

| Result | Value |
|---|---|
| **Screed volume required** | 6.8 yd³ |
| Screed thickness over the substrate | 2.38 in |
| Volume before the tube displacement is taken out | 6.32 yd³ |
| Volume displaced by the tube | 0.14 yd³ |
| Length of tube in the floor | 1,720 ft |
| Screed mass at the density entered | 12.03 tons |
| Bags to order | 368 bags |

- Allowance in the figure: Substrate tolerance and waste allowance (10%).

## How it is worked out

The working the page shows, in order: Screed thickness over the substrate; Volume before the tube displacement is taken out; Volume displaced by the tube; Length of tube in the floor; Screed mass at the density entered; Bags to order; then screed volume required.

The method, derived in full:

- [Quantity, Waste and Rounding](https://craftquantities.com/methodology/quantity-waste-and-rounding/): Why a material count is a ceiling function rather than a division, and why the waste factor — not the geometry — carries the risk.

What this calculation does not cover:

- Assumes the tube sits on the substrate or a thin clip rail. Tube carried on a raised rail or a profiled panel needs that build-up added to the cover depth.
- Perimeter edge strip, movement joint fill and any levelling compound over the finished screed are separate items.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- Gross volume = floor area × (cover over the tube crown + tube outside diameter). Displaced volume = π/4 × diameter² × total tube length, with tube length taken as area ÷ tube centres. Net screed is the difference, before the waste allowance.
- BS 8204, Screeds, bases and in-situ floorings — the series covering screed thickness, strength and soundness over a heated build-up
- EN 1264, Water-based surface embedded heating and cooling systems — where the required cover over the tube comes from; take the figure from it or from the system supplier rather than assuming one here

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does the tube displacement get its own line?**

Because it is small enough to look ignorable and large enough to matter on a big pour. On a floor tubed at close centres the pipe pushes out a couple of percent of the screed, which on several hundred square metres is a mixer load. Showing it separately lets you decide whether to carry it.

**Is the cover depth the same as the total screed depth?**

No, and treating it as such is the commonest error in this take-off. Cover is measured from the crown of the tube upward. The total depth is that cover plus the tube's own outside diameter, since the pipe sits below it — which is what this calculator adds before working out volume.

**Does a heated screed need to be thicker than an unheated one?**

It needs enough cover over the tube to spread heat evenly and to have the strength the floor finish requires, which usually makes it thicker than a bonded screed doing no heating work. The specific figure belongs to the screed system and the standard it is designed to, so it is an input here rather than an assumption.

**Can I use this for a screed over an electric heating mat?**

Partly. The gross volume arithmetic holds, but the displacement term is built around a round tube on a spacing, and a flat cable mat displaces very little. Set the tube diameter to its minimum for a mat, or simply read the gross volume line and ignore the displacement.

## Related calculators

- [Radiant Floor PEX Tubing Calculator](https://craftquantities.com/calculators/plumbing-hvac/radiant-floor-pex-calculator/)
- [Radiant Floor Heating Cable Spacing Calculator](https://craftquantities.com/calculators/materials-quantities/radiant-cable-spacing-calculator/)
- [Floor Drain Slope Screed Volume Calculator](https://craftquantities.com/calculators/materials-quantities/floor-drain-screed-calculator/)
- [Floor Screed Calculator — Sand and Cement, Bagged or Liquid](https://craftquantities.com/calculators/materials-quantities/floor-screed-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/heated-screed-volume-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/heated-screed-volume-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `heated-screed-volume-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/heated-screed-volume-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/heated-screed-volume-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.