# Slope Cut-and-Fill Earthwork Balance Calculator

> Check whether a site's cut material (adjusted for shrinkage) covers its fill requirement, or whether you need to import or haul off material.

Page: https://craftquantities.com/calculators/materials-quantities/cut-fill-earthwork-balance-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-02, 2 published test vectors.

Net earthwork balance: 131 yd³ for Cut Volume 1000, Required Fill Volume 800 and Shrinkage or Bulking -10, the page's opening figures; on the metric page, 1000, 800 and -10 give 100 m³. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Cut Volume (Bank Measure) | `cutVolume` | 1000 | 1000 | range 10–100000 |
| Required Fill Volume (Compacted) | `fillVolume` | 800 | 800 | range 10–100000 |
| Shrinkage or Bulking (%) | `shrinkageFactorPercent` | -10 | -10 | range -25–35 |

- **Cut Volume (Bank Measure)**: The in-situ (undisturbed) volume of soil to be cut, in m³.
- **Required Fill Volume (Compacted)**: The compacted volume needed to build up the fill areas, in m³.
- **Shrinkage or Bulking (%)**: How the compacted fill volume compares with the bank volume it came from. Negative shrinks, positive bulks.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Net earthwork balance** | 100 m³ |
| Cut volume as compacted fill | 900 m³ |

### US customary

| Result | Value |
|---|---|
| **Net earthwork balance** | 131 yd³ |
| Cut volume as compacted fill | 1,177.16 yd³ |

- Confidence: medium.

## How it is worked out

SURPLUS: approximately 100 m³ of cut material will be left over after filling — plan for haul-off or on-site stockpiling.

The working the page shows, in order: Cut volume as compacted fill; then net earthwork balance.

The method, derived in full:

- [Bulking, Swell and the Three Volumes of One Soil](https://craftquantities.com/methodology/bulking-and-swell/): Why a hundred cubic metres dug out becomes a hundred and twenty-five to cart away and ninety when it is put back, and why a cut-and-fill balance struck in the wrong state does not balance.

What this calculation does not cover:

- The balance assumes every cubic metre of cut becomes acceptable fill. Topsoil strip, root mat, made ground, soft spots and anything too wet or too contaminated to place yield spoil without yielding fill, and each also leaves a hole that has to be brought back up — so they hit the balance from both ends and neither effect is in this sum.
- The answer is in compacted measure. Neither muck away nor imported fill is transacted in that measure: convert through a swell factor to get the loose volume lorries actually carry, and through a bulk density to get the tonnage a weighbridge or tip charges on.
- One shrinkage figure is applied to the whole cut. It does not vary by stratum or by moisture content, and it does not move with the compaction specification — the same soil written to a higher percentage of a modified-effort maximum consumes more bank volume per unit placed. Drying, moisture conditioning and lime or cement treatment are not modelled at all.
- This is a volume balance, not a mass-haul plan. It carries no haul distances, phasing, sequencing, stockpile space or seasonal working windows, so a site that balances across the whole job can still need imported fill early and export later.
- This is not a geotechnical assessment or a design. It does not check settlement of the fill or of the ground beneath it, the stability or angle of the cut and fill slopes, or any temporary support the excavation needs — those come from the site investigation and the earthworks specification, and the extra fill that settlement consumes sits outside this calculation.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- Standard earthwork balance: cut volume (bank/in-situ measure) converts to a smaller compacted fill volume via a shrinkage factor; comparing that to the required fill volume gives a net surplus (haul off-site) or deficit (import fill)

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does cut soil 'shrink' when used as fill?**

Undisturbed (bank) soil has a natural structure with void spaces; once excavated and recompacted at a controlled density, the same mass of soil typically occupies less volume than it did in its original undisturbed state.

**What's the difference between shrinkage and swell?**

Swell is loose (hauled or stockpiled) soil taking up MORE volume than in its bank state, and shrinkage is the same soil recompacted into LESS. Loosening causes the swell, and recompaction leaves the soil smaller than its bank state; the Soil Swell & Shrinkage Haul Volume Calculator covers the loose-volume side of this.

**What should I do about a deficit?**

Source imported fill material, adjust the grading design to reduce fill requirements, or import from a nearby cut site — compare against haul-off costs for other project phases too.

## Related calculators

- [Soil Swell & Shrinkage Haul Volume Calculator](https://craftquantities.com/calculators/materials-quantities/soil-swell-shrinkage-calculator/)
- [Topsoil Calculator](https://craftquantities.com/calculators/landscaping-outdoor/topsoil-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/cut-fill-earthwork-balance-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/cut-fill-earthwork-balance-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `cut-fill-earthwork-balance-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/cut-fill-earthwork-balance-calculator.json

---