# Continuous Footing / Grade Beam Volume Calculator

> Estimate the concrete volume needed for a continuous strip footing or grade beam.

Page: https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.1.0, sources checked 2026-10-31, 18 published test vectors.

Concrete volume needed: 6.84 yd³ for Footing Length 66 ft, Footing Width 24 in and Footing Depth 16 in, the page's opening figures; on the metric page, 20 m, 60 cm and 40 cm give 5.04 m³. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Footing Length | `footingLength` | 20 m | 66 ft | mm, cm, m, in, ft, yd; range 0.01–200 m |
| Footing Width | `footingWidth` | 60 cm | 24 in | mm, cm, m, in, ft, yd; range 0.01–2 m |
| Footing Depth | `footingDepth` | 40 cm | 16 in | mm, cm, m, in, ft, yd; range 0.01–1.5 m |
| Waste Factor (%) | `wasteFactorPercent` | 5 | 5 | range 0–15 |
| Sub-base or blinding depth (0 for none) | `subBaseDepth` | 0 cm | 0 in | mm, cm, m, in, ft, yd; range 0–0.5 m |
| Sub-base compaction allowance (%) | `subBaseCompaction` | 20 | 20 | range 0–50 |
| Edge forms | `edgeForms` | Both sides and the two ends | Both sides and the two ends | `sides`, `none` |
| Form board depth (its face width) | `formBoardDepth` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0.05–0.4 m |
| Reinforcement to count | `reinforcement` | None (concrete only) | None (concrete only) | `none`, `bars` |
| Bar size | `barSize` | #4 (12.7 mm) | #4 (1/2 in) | `0.008`, `0.009525`, `0.01`, `0.0113`, `0.012`, `0.0127`, `0.015875`, `0.016`, `0.01905`, `0.0195`, `0.02`, `0.022225`, `0.025`, `0.0252`, `0.0254` |
| Longitudinal bars (along the footing) | `longBars` | 3 | 3 | range 1–20 |
| Transverse bar spacing (0 for none) | `transverseSpacing` | 0 mm | 0 in | mm, cm, m, in, ft, yd; range 0–1.5 m |
| Cover to the bars | `barCover` | 75 mm | 3 in | mm, cm, m, in, ft, yd; range 0–0.15 m |
| Lap length at each splice | `barLap` | 600 mm | 24 in | mm, cm, m, in, ft, yd; range 0–2 m |

- **Footing Length**: The total linear length of the continuous footing or grade beam.
- **Footing Width**: The cross-sectional width of the footing.
- **Footing Depth**: The cross-sectional depth (height) of the footing.
- **Waste Factor (%)**: Extra concrete for spillage and formwork irregularities.
- **Sub-base or blinding depth (0 for none)**: Compacted stone or a lean blinding layer under the footing, over its plan area.
- **Sub-base compaction allowance (%)**: How much more loose stone it takes to roll down to the compacted depth.
- **Edge forms**: Whether the footing is formed or poured straight into an earth trench.
- **Form board depth (its face width)**: The face width of the boards you form the sides with.
- **Reinforcement to count**: Count the bars your drawing gives; nothing here chooses them.
- **Bar size**: The bar your drawing calls for: US #3 to #8, or a metric bar in mm.
- **Longitudinal bars (along the footing)**: How many bars run the footing's length, side by side.
- **Transverse bar spacing (0 for none)**: Centre to centre, for bars running across the footing's width.
- **Cover to the bars**: Concrete between the footing's faces and the steel.
- **Lap length at each splice**: Overlap where a bar longer than one stock length is joined.

`formBoardDepth` applies only when `edgeForms` is `sides`.
`barSize` applies only when `reinforcement` is `bars`.
`longBars` applies only when `reinforcement` is `bars`.
`transverseSpacing` applies only when `reinforcement` is `bars`.
`barCover` applies only when `reinforcement` is `bars`.
`barLap` applies only when `reinforcement` is `bars`.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Concrete volume needed** | 5.04 m³ |
| Base volume (no waste) | 4.8 m³ |
| Equivalent in cubic yards | 6.59 yd³ |
| Edge forms, both sides and the ends | 41.2 m |
| Edge form face, run by depth | 16.48 m² |
| Form boards to buy, whole boards each side | 36 x 4.8 m boards |

### US customary

| Result | Value |
|---|---|
| **Concrete volume needed** | 6.84 yd³ |
| Base volume (no waste) | 6.52 yd³ |
| Equivalent in cubic yards | 6.84 yd³ |
| Edge forms, both sides and the ends | 136 ft |
| Edge form face, run by depth | 181.33 sq ft |
| Form boards to buy, whole boards each side | 42 x 12 ft boards |

## How it is worked out

The working the page shows, in order: Base volume (no waste); Equivalent in cubic yards; Edge forms, both sides and the ends; Edge form face, run by depth; Form boards to buy, whole boards each side; then concrete volume needed.

The method, derived in full:

- [Quantity, Waste and Rounding](https://craftquantities.com/methodology/quantity-waste-and-rounding/): Why a material count is a ceiling function rather than a division, and why the waste factor — not the geometry — carries the risk.

What this calculation does not cover:

- A GRADE BEAM AND A STRIP FOOTING ARE NOT THE SAME ELEMENT, and nothing here distinguishes them. A grade beam spans between piles or pads and is designed in bending, with steel top and bottom; a strip footing bears continuously and spreads load into the ground. They can share a rectangular cross-section and an identical concrete volume while having entirely different reinforcement, and the volume is the only thing this returns.
- A VOLUME, NOT A DESIGN. The width, depth and reinforcement of a footing come from the load it carries and the ground it sits on, and this takes all three as given. It answers what to order, not what to build.
- Excavation is not the same shape as concrete. Trench sides slump, over-dig happens at every corner, and soft spots get dug out and filled — which is why the volume placed routinely exceeds the volume calculated by more than the waste allowance covers, and why the allowance is worth setting from experience of the ground rather than from a default.
- Frost depth, the founding stratum and the water table decide how deep the footing goes before any of this arithmetic starts. A footing at the right size and the wrong depth is a heave failure waiting for a cold winter.
- Steps in a footing on sloping ground add concrete at every step and are easy to leave out of a straight-run take-off.
- Forms, sub-base and bars are counted only as you enter them: the forms as whole boards on both sides and the ends, stacked to the depth, with no stakes or spreaders; the sub-base as its compacted volume and the loose stone at one crushed-stone density; the bars as straight lengths inside the cover with a lap wherever a bar is longer than one stock length. Starter bars, corner and tee bars, hooks, links or stirrups shaped round the longitudinal bars, spacers, chairs, tie wire and any membrane are not counted.
- Footing size, bar size, number, spacing, cover and lap are yours to enter: a structural engineer or the building official decides them. This page lays out and counts what you enter and never says whether it is enough.

A professional must decide:

- Footing size, bar size, number, spacing, cover and lap are yours to enter: a structural engineer or the building official decides them. This page lays out and counts what you enter and never says whether it is enough.
- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-10-31):

- Concrete volume = length x width x depth, the standard geometric formula for a continuous rectangular-section footing or grade beam
- Reinforcing bar mass from its nominal diameter, 7850 kg/m³ x π d² / 4: 12 mm 0.888 kg/m (BS 4449 tables); #4 0.668 lb/ft, #5 1.043 lb/ft (ASTM A615 Table 1); Canadian 10M 11.3 mm and 15M 16.0 mm nominal (CSA G30.18)
- Sub-base stone weighed loose at 1,550 kg/m³ (97 lb/ft³), crushed stone in the site's bulk-density table (lib/materials/bulk-density.ts); compaction allowances of 15 to 25% are common supplier and specification practice for crushed stone and hardcore

The site's pages for the documents these name:

- [ASTM A615](https://craftquantities.com/standards/astm/astm-a615/)

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What's the difference between a footing and a grade beam?**

A footing directly bears on soil; a grade beam typically spans between piers or piles and doesn't rely on continuous soil bearing — geometrically they're calculated the same way.

**Does this include rebar?**

Only as you give it. Choose Bars from my drawing under Reinforcement and enter the bar size, the number of longitudinal bars, any transverse spacing, the cover and the lap: the page draws them in plan and in a section across the footing and lists each bar mark with its count, length, laps and weight. Which bars a footing needs is the engineer's or the building official's decision, not this page's.

**How do I measure the length around a building with corners?**

Along the centreline, as the length field asks, and the corners come out right on their own. Measuring the outside perimeter instead counts each outside corner square twice, adding the footing width squared times the depth at every corner — four of them on a rectangle. Where an internal footing meets an external one in a tee, measure the branch to the face of the footing it joins rather than to its centreline, or the overlap is counted twice as well.

**What depth do I enter for trench-fill, or for a footing under a foundation wall?**

The depth of concrete actually placed, which depends on the foundation type. A UK trench-fill foundation fills the trench with concrete to near ground level, so the depth entered is most of the trench depth and the volume is far larger than a traditional strip foundation's, where a shallower band of concrete carries brick or blockwork up to ground level. In North America a footing carries a poured or block foundation wall (a stem wall); enter only the footing's own thickness and take the wall as a separate volume.

**What goes under a grade beam that this volume leaves out?**

On clay that swells and shrinks with its moisture content, a grade beam spanning between piles is often cast over a void former — a collapsible cardboard form or compressible board in the bottom of the excavation, so that heaving ground cannot lift the beam. The former takes up depth in the dig but no concrete, so enter the beam's own depth rather than the depth excavated, and order the formers separately. UK practice calls this heave protection under ground beams on shrinkable clay; in North America cardboard void forms do the same job on expansive soils.

**How is the concrete ordered in each market?**

The result gives cubic metres with a cubic-yard equivalent: UK and Canadian ready-mixed suppliers take orders in cubic metres, US ones in cubic yards. A UK order also names a designated or designed mix suited to the ground, including any sulfate in the soil, while a North American order names a specified compressive strength — in psi in the US, MPa in Canada — and a slump. The volume is the same whichever you name; round it up to the increment the supplier sells in before booking the delivery.

## Related calculators

- [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- [Isolated Spread Footing Sizing Calculator](https://craftquantities.com/calculators/materials-quantities/spread-footing-sizing-calculator/)
- [Rebar Calculator](https://craftquantities.com/calculators/materials-quantities/rebar-calculator/)
- [Concrete Formwork Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-formwork-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/continuous-footing-grade-beam-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/continuous-footing-grade-beam-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `continuous-footing-grade-beam-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/continuous-footing-grade-beam-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/continuous-footing-grade-beam-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.