# Concrete Maturity Method Calculator (Nurse-Saul)

> Compute a concrete pour's maturity index from its average curing temperature and elapsed time, per ASTM C1074.

Page: https://craftquantities.com/calculators/materials-quantities/concrete-maturity-method-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.1.1, sources checked 2026-09-05, 4 published test vectors.

Maturity index: 3,360 °C-hours for Average Concrete Temperature 68 °F, the page's opening figures; on the metric page, 20 °C gives 3,360 °C-hours. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Average Concrete Temperature | `averageTemp` | 20 °C | 68 °F | c, f, k; range -5–50 °C |
| Elapsed Curing Time | `elapsedTime` | 168 | 168 | range 1–720 |
| Datum Temperature (T0) | `datumTemp` | 0 °C | 32 °F | c, f, k; range -15–15 °C |

- **Average Concrete Temperature**: The average concrete temperature over the elapsed curing period, in °C.
- **Elapsed Curing Time**: The total elapsed curing time, in hours.
- **Datum Temperature (T0)**: The temperature below which the mix gains no useful strength. ASTM C1074 recommends 0°C.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Maturity index** | 3,360 °C-hours |
| Elapsed time | 7 days |
| Datum temperature used (°C) | 0 °C |
| Temperature above datum (Δ°C) | 20 Δ°C |

### US customary

| Result | Value |
|---|---|
| **Maturity index** | 3,360 °C-hours |
| Elapsed time | 7 days |
| Datum temperature used (°C) | 0 °C |
| Temperature above datum (Δ°C) | 20 Δ°C |

- Confidence: medium.

## How it is worked out

This uses a single average temperature for simplicity — a real maturity study integrates continuously logged temperature data over time, which is more accurate when temperature varies significantly during curing (e.g. cold nights, hot days). The datum belongs to your mixture: 0°C is ASTM C1074's recommendation for plain Type I cement, and Annex A1 sets out how to measure it for anything else.

The working the page shows, in order: Elapsed time; Datum temperature used (°C); Temperature above datum (Δ°C); then maturity index.

The method, derived in full:

- [Concrete Mix Design and Fresh-Concrete Behaviour](https://craftquantities.com/methodology/concrete-mix-and-fresh-behaviour/): Why a litre of water added on site costs strength permanently, why yield is the sum of absolute volumes rather than of loose ones, and why strength is a function of temperature and time together rather than of age.

What this calculation does not cover:

- A maturity index is not a strength. Until a strength-maturity relationship has been developed for the mix actually supplied — cylinders from that mix, broken at several ages against their own logged maturity — this number cannot be read as an in-place compressive strength, and on its own it does not release formwork, tendons, sawcutting or traffic.
- Nurse-Saul sums temperature over successive intervals; this takes one average for the whole period instead. Cold nights, the hydration peak and any spell the concrete spent below the datum are all flattened into a single figure, so the wider the temperature swing over the period the further this sits from what an embedded logger would report.
- It covers one temperature, not a position in the pour. Corners, edges, thin sections and the top surface run colder than the core and reach a given maturity later, and a striking decision belongs to the coldest critical location rather than to an average of the element.
- The datum is taken exactly as entered — nothing here checks it against your cement, admixtures or supplementary cementitious materials. The Nurse-Saul function is also linear in temperature, so it does not capture the reduced ultimate strength of concrete cured hot: a warm pour can accumulate maturity quickly and still fall short at later ages, which is what the Arrhenius equivalent-age methods exist to address.
- At or below the datum the index reports zero. That is the method's bookkeeping convention, not a verdict on the concrete: it says nothing about whether a pour that got cold or froze has been damaged, and it does not cover cold-weather protection requirements.
- The index is reported in °C-hours whichever measurement system you are reading the site in, and the two temperature rows beneath it are shown in Celsius terms for the same reason: the figure is only meaningful against the strength-maturity curve it is compared to, and that curve carries the units its own cylinders were logged in. Enter your temperatures in whichever units you measured — those fields convert — but if your calibration curve is in °F-hours, multiply this figure by 1.8 before reading a strength off it.

A professional must decide:

- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-09-05):

- ASTM C1074 Nurse-Saul maturity function: M(t) = Σ(T − T0) × Δt, where T is the concrete temperature, T0 is the datum temperature and Δt is the elapsed time interval. C1074 recommends T0 = 0°C (32°F) for Type I cement without admixtures cured between 0 and 40°C, and gives Annex A1 for determining it experimentally for any other mixture
- ASTM C1074: the increment (T − T0) is taken as zero for any interval in which the concrete is at or below the datum temperature

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What is the maturity method used for?**

It correlates a concrete's temperature history with its strength development, letting field crews estimate in-place strength (for formwork stripping or post-tensioning timing) without waiting for a lab-cured cylinder break.

**Which datum temperature should I use?**

0°C is ASTM C1074's recommendation for Type I cement without admixtures cured between 0 and 40°C, and it is this page's default. Anything else — a Type III cement, an accelerator, a supplementary cementitious material — has its own datum, and C1074's Annex A1 sets out how to measure it: cure mortar cubes at several temperatures, plot the strength-gain rate against temperature and read off the intercept. If your ready-mix supplier has done a maturity calibration for the mix, the datum will come with it.

**Why do older references say −10°C?**

That is the value from Saul's original 1951 work, on the reasoning that hydration continues slowly a little below freezing rather than stopping at 0°C. It is still met in older texts and in some European practice, but it is not what ASTM C1074 recommends, and the difference is not academic: adding 10 degrees to every hour reports roughly 50% more maturity at 20°C. Since maturity is read through a strength curve to decide when to strike formwork, the higher figure is the one that lets you load concrete early.

**Can I convert this maturity index directly to compressive strength?**

Not without a mix-specific strength-maturity calibration curve, developed by testing cylinders of your actual mix at several ages and correlating their strength to their maturity index — this calculator only gives you the maturity index itself.

## Related calculators

- [Concrete Curing Blanket Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-curing-blanket-calculator/)
- [Mass Concrete Thermal Gradient Calculator](https://craftquantities.com/calculators/materials-quantities/mass-concrete-thermal-gradient-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/concrete-maturity-method-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/concrete-maturity-method-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `concrete-maturity-method-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/concrete-maturity-method-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/concrete-maturity-method-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.