# Concrete Evaporation Rate Calculator

> Estimate concrete surface moisture evaporation rate to check plastic shrinkage cracking risk before a pour.

Page: https://craftquantities.com/calculators/materials-quantities/concrete-evaporation-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.1.1, sources checked 2026-09-03, 4 published test vectors.

Estimated evaporation rate: 0.11 lb/ft²/hr for Concrete Temperature 77 °F and Air Temperature 68 °F, the page's opening figures; on the metric page, 25 °C and 20 °C give 0.537 kg/m²/hr. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Concrete Temperature | `concreteTempC` | 25 °C | 77 °F | c, f, k; range 0–45 °C |
| Air Temperature | `airTempC` | 20 °C | 68 °F | c, f, k; range -10–45 °C |
| Relative Humidity (%) | `relativeHumidityPercent` | 50 | 50 | range 5–100 |
| Wind Speed (km/h) | `windSpeedKmh` | 10 | 10 | range 0–60 |

- **Concrete Temperature**: The temperature of the fresh concrete, not the air.
- **Air Temperature**: The ambient air temperature at the job site.
- **Relative Humidity (%)**: The relative humidity at the job site.
- **Wind Speed (km/h)**: The wind speed across the concrete surface during placement and finishing.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Estimated evaporation rate** | 0.537 kg/m²/hr |
| Critical threshold | 1 kg/m²/hr |

### US customary

| Result | Value |
|---|---|
| **Estimated evaporation rate** | 0.11 lb/ft²/hr |
| Critical threshold | 0.2 lb/ft²/hr |

## How it is worked out

Below the critical threshold under these conditions — standard curing practices should be adequate, though conditions can change during a long pour, so re-check if temperature or wind picks up.

The working the page shows, in order: Critical threshold; then estimated evaporation rate.

The method, derived in full:

- [Concrete Mix Design and Fresh-Concrete Behaviour](https://craftquantities.com/methodology/concrete-mix-and-fresh-behaviour/): Why a litre of water added on site costs strength permanently, why yield is the sum of absolute volumes rather than of loose ones, and why strength is a function of temperature and time together rather than of age.

What this calculation does not cover:

- Solar gain is not in the model. The equation reads concrete temperature, air temperature, humidity and wind only, so a slab in full sun and the same slab in shade return an identical rate from identical readings. If the sun is on the pour, take the concrete temperature off the finished surface rather than off the chute, or the answer comes back low.
- Bleed rate is not modelled. Plastic shrinkage cracking is evaporation outrunning the bleed water rising to replace it, and this calculates only the evaporation half. Low-bleed mixes - low water-cement ratio, silica fume, heavy fly ash replacement, high-range water reducers - can crack plastically at rates below the threshold this page flags.
- Nothing about the slab itself is an input. Thickness, subgrade moisture and absorption, restraint from reinforcement and edge conditions, finishing timing, and the curing method actually applied all govern whether cracks form, and none of them reach the calculation.
- This is one moment at one spot. Wind, humidity and temperature move across the hours of a placement and vary across a large slab - funnelled between buildings, faster over a hot deck, calmer behind a windbreak. Re-run it against readings taken at slab level during the pour, not against a forecast from the nearest airport.
- The threshold is a screening line, not a pass/fail verdict and not a curing specification. A rate below it is not a guarantee against cracking and a rate above it is not a prediction of it; the number tells you when to have fogging, evaporation retardant and windbreaks ready, and it does not replace the hot- or cold-weather concreting requirements in your project specification or the supplier's guidance for the mix being placed.

A professional must decide:

- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-09-03):

- ACI 305R / Uno metric evaporation equation: E = 5 x (\[Tc+18\]^2.5 - r x \[Ta+18\]^2.5) x (V+4) x 10^-6, with E in kg/m2/h, temperatures in degrees C and wind speed in km/h
- Widely cited critical threshold: evaporation rate at or above approximately 0.2 lb/sq ft/hr (1.0 kg/m²/hr) significantly raises the risk of plastic shrinkage cracking

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does wind matter so much more than I'd expect?**

Wind continuously replaces the humid air layer right above the concrete surface with drier ambient air, dramatically accelerating moisture loss — this is why job sites often erect temporary windbreaks around large slab pours in exposed, breezy locations.

**What is plastic shrinkage cracking?**

When surface water evaporates faster than bleed water can rise to replace it, the surface shrinks while the concrete below is still plastic (not yet hardened), causing shallow cracks — usually cosmetic but sometimes affecting durability, and preventable with proper curing precautions.

**What should I do if the rate is critical but I can't reschedule the pour?**

Common mitigations include fogging the surface with a fine water mist (not flooding it), applying an evaporation-retardant admixture, erecting windbreaks and sunshades, and finishing/curing as promptly as possible after placement.

**Is concrete temperature the same as air temperature?**

No — fresh concrete generates heat from the cement hydration reaction and is often several degrees warmer than the surrounding air, especially in the first few hours, which is why this calculator asks for both separately.

## Related calculators

- [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- [Concrete Curing Blanket Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-curing-blanket-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/concrete-evaporation-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/concrete-evaporation-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `concrete-evaporation-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/concrete-evaporation-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/concrete-evaporation-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.