# Concrete Anchor Proof Load Test Calculator

> The load a site proof test on concrete anchors is held at, and how many anchors in a lot to pull, from your specification's multiplier and sample rate.

Page: https://craftquantities.com/calculators/materials-quantities/anchor-proof-load-test-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-02, 3 published test vectors.

Proof load to apply and hold: 2,700 lbf for Design Tension per Anchor 1798.47 lbf, the page's opening figures; on the metric page, 8 kN gives 12,000 N. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Design Tension per Anchor | `designTension` | 8 kN | 1798.47 lbf | n, kn, lbf, kip; range 500–400000 N |
| Specified Proof-Load Multiplier | `proofMultiplier` | 1.5 | 1.5 | range 1–3 |
| Anchors in the Test Lot | `lotSize` | 120 | 120 | range 1–5000 |
| Specified Sample Rate | `samplePercent` | 5 | 5 | range 0.5–100 |
| Specified Minimum per Lot | `minimumTests` | 2 | 2 | range 0–50 |

- **Design Tension per Anchor**: The tension the anchor is designed to carry in service.
- **Specified Proof-Load Multiplier**: How many times the design tension the specification asks the test to reach.
- **Anchors in the Test Lot**: How many anchors this lot covers — one installer, one product, one condition.
- **Specified Sample Rate**: The proportion of the lot the specification requires to be tested.
- **Specified Minimum per Lot**: The floor the specification puts under the sample, whatever the percentage gives.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Proof load to apply and hold** | 12,000 N |
| Anchors to test in this lot | 6 anchors |
| Sample size before the specified floor | 6 anchors |
| Load applied above the design tension | 4,000 N |
| Anchors covered by each tested anchor | 20 anchors |

### US customary

| Result | Value |
|---|---|
| **Proof load to apply and hold** | 2,700 lbf |
| Anchors to test in this lot | 6 anchors |
| Sample size before the specified floor | 6 anchors |
| Load applied above the design tension | 899.24 lbf |
| Anchors covered by each tested anchor | 20 anchors |

- Confidence: medium.

## How it is worked out

The sample rate governs this lot. A proof test demonstrates that the installation holds the specified load without measurable displacement; it is not a capacity test and must not be taken to the anchor's ultimate. Confirm the specification's cap on the applied load, and confirm what counts as a failure and what happens to the rest of the lot when one occurs.

The working the page shows, in order: Anchors to test in this lot; Sample size before the specified floor; Load applied above the design tension; Anchors covered by each tested anchor; then proof load to apply and hold.

The method, derived in full:

- [Fastener Capacity and the Failure Mode That Governs](https://craftquantities.com/methodology/fastener-capacity-modes/): Why an anchor's capacity is the smallest of several modes rather than one number, why concrete breakout grows with embedment to the power of one and a half, and why hole cleaning is the largest variable on site.

What this calculation does not cover:

- Does not set the multiplier or the sample rate. Both are contract values, and a page that supplied them would be inventing the specification.
- Does not check that the proof load is safe to apply. A multiplier taken against a load close to the anchor's capacity can exceed the steel or the concrete during the test itself.

A professional must decide:

- Structure: sizes, thicknesses, spans, reinforcement and bearing are a structural engineer's or the building official's decision. This is a quantity, not a design.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- ASTM E488/E488M, Standard Test Methods for Strength of Anchors in Concrete Elements — the reference method for applying and measuring a tension load on an installed anchor
- The proof-load multiplier and the sampling rate are project values, not standard ones: they come from the contract specification and the special inspection programme, which is why both are entered here rather than assumed
- Arithmetic only: proof load = design tension × the specified multiplier; anchors to test = the specified percentage of the lot, rounded up, subject to the specified minimum and never more than the lot holds

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What counts as passing a proof test?**

Reaching the specified load and holding it for the specified duration without the anchor displacing beyond the allowance the specification sets, and without the concrete showing distress around it. The criterion is displacement, not survival: an anchor that creeps steadily under a held load has failed even though nothing has come out of the hole.

**Why not simply test every anchor?**

Because proof testing is not free of consequence. Each test loads the anchor and the concrete around it, and testing to a high multiplier can damage the very installation you are certifying. Sampling exists to detect a systematic installation problem — the wrong hole size, an uncleaned hole, a crew skipping a step — which shows up in a sample if it is present at all.

**One anchor in my sample failed. What happens to the lot?**

That is a specification question and the answers vary widely: some require two further anchors tested for every failure, some require the whole lot tested, some require the lot removed and reinstalled. Agree the rule before testing starts rather than after a failure, because the difference between those outcomes is days of programme.

**Does a passed proof test mean the anchor design is right?**

No, and confusing the two is a real risk on site. A proof test verifies the installation — that this anchor, in this hole, in this concrete, holds the specified load. Whether the specified load is the right one for the connection is a design calculation that happened long before anyone brought a pull rig to site.

## Related calculators

- [Post-Installed Concrete Anchor Drill Depth Calculator](https://craftquantities.com/calculators/materials-quantities/post-installed-anchor-drill-depth-calculator/)
- [Concrete Anchor Bolt Breakout Capacity Calculator (ACI 318)](https://craftquantities.com/calculators/materials-quantities/anchor-bolt-breakout-calculator/)
- [Helical Screw Anchor Pull-Out Capacity Calculator](https://craftquantities.com/calculators/materials-quantities/helical-anchor-pullout-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/anchor-proof-load-test-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/anchor-proof-load-test-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `anchor-proof-load-test-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/anchor-proof-load-test-calculator.json

---
Source: https://craftquantities.com/calculators/materials-quantities/anchor-proof-load-test-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.