# Precast Kerb Calculator — Kerb Units, Bed and Haunch Concrete

> Count precast concrete kerb units for a run, at the unit length your merchant sells, and the concrete for the bed and haunch you specify.

Page: https://craftquantities.com/calculators/landscaping-outdoor/precast-kerb-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-10-31, 2 published test vectors.

Kerb units to order: 24 kerbs for Length of the Kerb Run 66 ft, Length of One Kerb Unit 36 in and Joint Between Units 0.2 in, the page's opening figures; on the metric page, 20 m, 915 mm and 5 mm give 24 kerbs. Source: Marshalls, half battered kerb HB2 (NBS Source).

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Length of the Kerb Run | `runLength` | 20 m | 66 ft | mm, cm, m, in, ft, yd; range 0.5–2000 m |
| Length of One Kerb Unit | `unitLength` | 915 mm | 36 in | mm, cm, m, in, ft, yd; range 0.1–2 m |
| Joint Between Units | `jointWidth` | 5 mm | 0.2 in | mm, cm, m, in, ft, yd; range 0–0.03 m |
| Waste Allowance (%) | `wastePercent` | 5 | 5 | range 0–30 |
| Concrete Bed Width | `bedWidth` | 300 mm | 11.75 in | mm, cm, m, in, ft, yd; range 0–1.5 m |
| Concrete Bed Depth | `bedDepth` | 150 mm | 6 in | mm, cm, m, in, ft, yd; range 0–0.6 m |
| Haunch Height Behind the Kerb | `haunchHeight` | 100 mm | 4 in | mm, cm, m, in, ft, yd; range 0–0.4 m |
| Haunch Width at the Bed | `haunchWidth` | 100 mm | 4 in | mm, cm, m, in, ft, yd; range 0–0.4 m |
| Concrete Allowance (%) | `concreteWaste` | 10 | 10 | range 0–50 |

- **Length of the Kerb Run**: The straight length of kerb to lay, along its face.
- **Length of One Kerb Unit**: The unit's length as sold, from your merchant's listing.
- **Joint Between Units**: The mortar joint your specification gives between units.
- **Waste Allowance (%)**: Extra units for cuts at the ends and breakages.
- **Concrete Bed Width**: The width of the concrete bed under the kerb, from your specification.
- **Concrete Bed Depth**: The depth of the concrete bed, from your specification.
- **Haunch Height Behind the Kerb**: How far up the back of the kerb the haunch rises, from your specification.
- **Haunch Width at the Bed**: How far the haunch spreads behind the kerb along the bed, from your specification.
- **Concrete Allowance (%)**: Extra concrete for an uneven dig and spillage.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Kerb units to order** | 24 kerbs |
| Kerb units laid, before the allowance | 22 kerbs |
| Kerb face laid, units and joints | 20.24 m |
| Concrete in the bed | 0.9 m³ |
| Concrete in the haunch | 0.1 m³ |
| Concrete per metre of kerb | 0.05 m³/m |
| Concrete to order, with the allowance | 1.1 m³ |

### US customary

| Result | Value |
|---|---|
| **Kerb units to order** | 24 kerbs |
| Kerb units laid, before the allowance | 22 kerbs |
| Kerb face laid, units and joints | 66.37 ft |
| Concrete in the bed | 1.2 yd³ |
| Concrete in the haunch | 0.14 yd³ |
| Concrete per metre of kerb | 0.02 yd³/ft |
| Concrete to order, with the allowance | 1.47 yd³ |

- Allowance in the figure: waste allowance (5%).

## How it is worked out

The working the page shows, in order: Kerb units laid, before the allowance; Kerb face laid, units and joints; Concrete in the bed; Concrete in the haunch; Concrete per metre of kerb; Concrete to order, with the allowance; then kerb units to order.

The method, derived in full:

- [Spacing, Pitch and the Count That Follows](https://craftquantities.com/methodology/spacing-pitch-and-count/): Why a run divided by a spacing gives the number of gaps and not the number of things, why the division rounds up rather than to nearest, and what the leftover bay at the end does to both.

What this calculation does not cover:

- Straight units only: a bend tighter than the units can follow needs radius kerbs, and a dropped crossing needs droppers and transition units, which are counted separately from the maker's list. Enter only the straight run here.
- The bed and haunch are your specification's figures, never sized here. Highway authorities publish their own kerb details, and a kerb that restrains a driveway or a road takes the detail the designer gives it.
- The haunch is taken as a triangle behind the kerb; a square-shouldered haunch holds twice that concrete. Nothing is added for a haunch on the road side or for over-digging, which the concrete waste allowance has to cover.
- Joints are counted at the width you enter between every pair of units; movement joints, where the specification calls for them, take compressible filler rather than mortar and are not counted.

## Sources

As the calculator cites them (sources checked 2026-10-31):

- Marshalls, half battered kerb HB2 (NBS Source): a straight precast unit 915 mm long, 125 mm wide and 255 mm high, hydraulically pressed, made to BS EN 1340 <https://source.thenbs.com/product/half-battered-kerb/vK64aRxVxFRU4ZSEh36WiM>
- MKM Building Supplies, concrete half battered kerb straight HB2, 915 mm × 125 × 255 mm (a UK merchant's listing, read 2026-10-31) <https://mkm.com/product/concrete-half-battered-kerb-straight-hb2-915mm-x-125-x-255mm-b009085>
- Marshalls, Demarcation Kerb Installation Guidelines: wide joints fully filled with 1:4 cement:sand mortar; units are never butt-jointed; movement joints run through the concrete race and haunching <https://media.marshalls.co.uk/image/upload/v1784898399/Demarcation_Kerb_Installation_Guidelines.pdf>
- Suffolk County Council, standard detail DM 1100 02, kerbs laid on full construction: the kerb on a concrete bed with a concrete haunch, all concrete mix ST1 (an example of a highway authority's own detail) <https://www.suffolk.gov.uk/asset-library/dm-1100-02-kerbs-laid-on-full-construction.pdf>

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**How many kerbs in a metre?**

With 915 mm units and 5 mm joints, one metre takes 1000 / 920 = 1.09 units, so about 11 units for every 10 metres before the allowance for end cuts and breakages.

**How deep should the concrete bed be?**

That is your specification's or the highway authority's figure, not this page's: it depends on what the kerb restrains and the ground. The page opens on an example and counts the concrete for the figures you enter.

## Related calculators

- [Paver Edging Calculator](https://craftquantities.com/calculators/materials-quantities/paver-edging-calculator/)
- [Concrete Curb and Gutter Volume Calculator](https://craftquantities.com/calculators/materials-quantities/curb-gutter-volume-calculator/)
- [Concrete Calculator](https://craftquantities.com/calculators/materials-quantities/concrete-calculator/)
- [Lawn Edging Calculator](https://craftquantities.com/calculators/materials-quantities/lawn-edging-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/precast-kerb-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/precast-kerb-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `precast-kerb-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/precast-kerb-calculator.json

---
Source: https://craftquantities.com/calculators/landscaping-outdoor/precast-kerb-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.