# Hardscape Area & Base Calculator

> Work out surface area, sub-base and bedding sand for a patio, path or driveway in one pass.

Page: https://craftquantities.com/calculators/landscaping-outdoor/hardscape-area-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.1.0, sources checked 2026-10-31, 4 published test vectors.

Paving area: 279 sq ft for Length 19.5 ft, Width 13 ft and Bedding sand depth 1.25 in, the page's opening figures; on the metric page, 6 m, 4 m and 30 mm give 26.4 m². Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Length | `length` | 6 m | 19.5 ft | mm, cm, m, in, ft, yd; range 0.01–500 m |
| Width | `width` | 4 m | 13 ft | mm, cm, m, in, ft, yd; range 0.01–200 m |
| Traffic | `use` | Pedestrian — patio, path (100 mm sub-base) | Pedestrian — patio, path (4 in sub-base) | `pedestrian`, `light`, `vehicular` |
| Bedding sand depth | `beddingDepth` | 30 mm | 1.25 in | mm, cm, m, in, ft, yd; range 0.01–0.08 m |
| Cutting waste (%) | `wastePercent` | 10 | 10 | range 0–40 |

- **Length**: Length of the paved area.
- **Width**: Width of the paved area.
- **Traffic**: What will use the surface.
- **Bedding sand depth**: Screeded sand layer under the units.
- **Cutting waste (%)**: Allowance for cuts and breakage.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Paving area** | 26.4 m² |
| Net paved area | 24 m² |
| Sub-base depth | 100 mm |
| Sub-base to order (loose) | 3 m³ |
| Sub-base weight | 4,800 kg |
| Bedding sand | 0.72 m³ |
| Area in sq ft | 284.17 sq ft |

### US customary

| Result | Value |
|---|---|
| **Paving area** | 279 sq ft |
| Net paved area | 253.5 sq ft |
| Sub-base depth | 3.94 in |
| Sub-base to order (loose) | 3.85 yd³ |
| Sub-base weight | 10,384.18 lb |
| Bedding sand | 0.98 yd³ |
| Area in sq ft | 278.85 sq ft |

- Confidence: medium.

## How it is worked out

Sub-base includes a 25% compaction allowance. Depths follow common guidance and should give way to a specific specification where one exists.

The working the page shows, in order: Net paved area; Sub-base depth; Sub-base to order (loose); Sub-base weight; Bedding sand; Area in sq ft; then paving area.

The method, derived in full:

- [Quantity, Waste and Rounding](https://craftquantities.com/methodology/quantity-waste-and-rounding/): Why a material count is a ceiling function rather than a division, and why the waste factor — not the geometry — carries the risk.

What this calculation does not cover:

- Assumes a competent subgrade. Soft or clay ground needs excavation to a firm formation and usually a geotextile separator, neither of which is calculated here.
- No allowance for edge restraint, which paving needs on every free edge or it spreads.

## Sources

As the calculator cites them (sources checked 2026-10-31):

- Sub-base depth: 100 mm compacted for pedestrian paving, 150-200 mm for vehicular — BS 7533 and ICPI guidance
- Bedding layer 25-40 mm of sharp sand, screeded and not compacted before laying — ICPI Tech Spec 2

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**How deep should the sub-base be?**

100 mm compacted for foot traffic, 150 mm for a car driveway, 200 mm where vehicles are heavy or frequent. On soft or clay ground go deeper and add a geotextile separator — without one the stone migrates into the subgrade and the surface settles from below, which no amount of surface repair fixes.

**Should the bedding sand be compacted before laying?**

No. Screed it level and lay onto it uncompacted; the units are vibrated in afterwards, which consolidates the bedding evenly under load. Compacting first produces hard and soft patches and the paving follows them.

**Why does the sub-base quantity exceed the excavation volume?**

Because it is delivered loose and used compacted — about 25% is lost to consolidation. The figure here is what to order; the depth quoted is what you finish with after rolling.

## Related calculators

- [Paver Calculator](https://craftquantities.com/calculators/materials-quantities/paver-calculator/)
- [Paver Base & Sand Calculator](https://craftquantities.com/calculators/materials-quantities/paver-base-calculator/)
- [Gravel Calculator](https://craftquantities.com/calculators/landscaping-outdoor/gravel-calculator/)
- [Paver Polymeric Sand Calculator](https://craftquantities.com/calculators/materials-quantities/paver-polymeric-sand-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/hardscape-area-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/hardscape-area-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `hardscape-area-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/hardscape-area-calculator.json

---
Source: https://craftquantities.com/calculators/landscaping-outdoor/hardscape-area-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.