# Truck Haul Cycle Time Calculator

> Cycle time, hourly production and fleet size for an earthmoving haul, including the queueing that decides whether extra trucks help.

Page: https://craftquantities.com/calculators/heavy-civil/haul-cycle-time-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-06, 4 published test vectors.

Hourly production: 217 yd³/hr for One-way haul distance 3, Loaded speed 30 and Return speed 45, the page's opening figures; on the metric page, 3, 30 and 45 give 166 m³/hr. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| One-way haul distance (km) | `haulDistance` | 3 | 3 | range 0.05–200 |
| Loaded speed (km/h) | `loadedSpeed` | 30 | 30 | range 1–120 |
| Return speed (km/h) | `emptySpeed` | 45 | 45 | range 1–120 |
| Load time (min) | `loadTime` | 3 | 3 | range 0.1–60 |
| Dump and manoeuvre time (min) | `dumpTime` | 1.5 | 1.5 | range 0.1–30 |
| Payload per truck | `payload` | 12 m³ | 15.75 yd³ | l, gal, m3, ft3, yd3; range 0.1–500000 L |
| Number of trucks | `truckCount` | 4 | 4 | range 1–100 |
| Working minutes per hour | `efficiency` | 50 | 50 | range 20–60 |

- **One-way haul distance (km)**: Distance from load point to dump.
- **Loaded speed (km/h)**: Average speed carrying a load.
- **Return speed (km/h)**: Average speed running empty.
- **Load time (min)**: Time under the loader.
- **Dump and manoeuvre time (min)**: Spotting, tipping and turning at the dump.
- **Payload per truck**: Loose volume carried per trip.
- **Number of trucks**: Trucks in the fleet.
- **Working minutes per hour**: Real productive minutes in an hour.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Hourly production** | 166 m³/hr |
| Cycle time per truck, free-flowing | 14.5 min |
| Loaded travel | 6 min |
| Return travel | 4 min |
| Match factor | 0.83 × |
| Trips per truck per hour, free-flowing | 4.14 trips |
| Loader ceiling at 100% efficiency | 240 m³/hr |
| Trucks for a balanced fleet | 4.83 trucks |

### US customary

| Result | Value |
|---|---|
| **Hourly production** | 217 yd³/hr |
| Cycle time per truck, free-flowing | 14.5 min |
| Loaded travel | 6 min |
| Return travel | 4 min |
| Match factor | 0.83 × |
| Trips per truck per hour, free-flowing | 4.14 trips |
| Loader ceiling at 100% efficiency | 315 yd³/hr |
| Trucks for a balanced fleet | 4.83 trucks |

- Confidence: medium.

## How it is worked out

Match factor below 1 — the loader is standing idle waiting for trucks. Adding a truck will increase production.

The working the page shows, in order: Cycle time per truck, free-flowing; Loaded travel; Return travel; Match factor; Trips per truck per hour, free-flowing; Loader ceiling at 100% efficiency; Trucks for a balanced fleet; then hourly production.

The method, derived in full:

- [Temporary Works: Slings, Wind, Battering and Haul Cycles](https://craftquantities.com/methodology/temporary-works-and-site-safety/): Why a shallow sling angle doubles the tension in every leg, why a sheeted scaffold carries an order more wind than an open one, and why adding trucks to a short haul achieves nothing.

What this calculation does not cover:

- Assumes a steady haul road and constant speeds. Grades, single-lane sections and a shared road with other traffic all degrade this in practice.
- Payload is loose volume. Converting from bank measure requires the swell factor for the material, which changes the trip count.
- Does not model the dump-end constraint. A single spreader or a tight tip can throttle the fleet just as the loader can.

## Sources

As the calculator cites them (sources checked 2026-09-06):

- Cycle time = load + haul + dump + return + queue. Production = payload ÷ cycle time × efficiency
- Match factor = (number of trucks × loader cycle time) ÷ truck cycle time; a factor of 1 balances the fleet against the loader

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why does adding trucks eventually stop helping?**

Because the loader is the real constraint. Each truck must wait its turn to be filled, and once the fleet's arrival rate exceeds the loader's rate, extra trucks simply queue. The match factor tells you where you are: below 1 the loader is idle and another truck earns its keep; above 1 you are paying for a truck to sit in a line. The calculator caps production at the loader ceiling for exactly this reason.

**Why fifty working minutes rather than sixty?**

Because sixty does not happen. Breaks, refuelling, a plant move, rain, a queue at the tip and the shift change all come out of the hour. Fifty minutes is a well-run site; forty-five is common. A programme built on sixty is a programme that is already twenty percent late on day one.

**Should I use bank or loose volume?**

Loose, because that is what the truck carries. If your quantity comes from a cut-and-fill calculation it is bank measure, and material swells when excavated — commonly 10-25% for soils and more for rock. Using bank volume as payload understates the number of trips, and the error runs through the whole programme.

## Related calculators

- [Slope Cut-and-Fill Earthwork Balance Calculator](https://craftquantities.com/calculators/materials-quantities/cut-fill-earthwork-balance-calculator/)
- [Road Subgrade Excavation Truck Fleet Calculator](https://craftquantities.com/calculators/materials-quantities/subgrade-excavation-truck-calculator/)
- [Pavement Design ESAL Calculator](https://craftquantities.com/calculators/heavy-civil/asphalt-pavement-esal-calculator/)
- [Trench Sloping & Excavation Width Calculator](https://craftquantities.com/calculators/heavy-civil/trench-safety-slope-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/haul-cycle-time-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/haul-cycle-time-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `haul-cycle-time-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/haul-cycle-time-calculator.json

---