# Construction Preliminaries (General Conditions) Calculator

> Add up preliminaries (general conditions) from your own weekly and one-off figures: fixed, time-related and value-related, and what a week of delay adds.

Page: https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-02, 3 published test vectors.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Programme Duration | `programmeWeeks` | 26 | 26 | range 1–260 |
| Full-Time Site Staff | `siteStaffCount` | 2 | 2 | range 0–50 |
| Cost Per Person Per Week | `siteStaffWeeklyCost` | blank (your own rate) | blank (your own rate) | range 0–20000 |
| Accommodation and Welfare Per Week | `accommodationWeekly` | blank (your own rate) | blank (your own rate) | range 0–50000 |
| Temporary Services and Waste Per Week | `servicesWeekly` | blank (your own rate) | blank (your own rate) | range 0–50000 |
| Plant Standing Per Week | `plantStandingWeekly` | blank (your own rate) | blank (your own rate) | range 0–100000 |
| Setting Up (One-Off) | `setupCost` | 12000 | 12000 | range 0–5000000 |
| Clearing Away (One-Off) | `removalCost` | 6000 | 6000 | range 0–5000000 |
| Contract Sum | `contractSum` | 1000000 | 1000000 | range 0–500000000 |
| Insurance and Bonds | `insuranceAndBondPercent` | 1.2 | 1.2 | range 0–10 |

- **Programme Duration**: The contract period in weeks, from possession of the site to practical completion.
- **Full-Time Site Staff**: People on site full-time whose cost is not in any trade rate.
- **Cost Per Person Per Week**: All-in weekly cost of one member of site staff.
- **Accommodation and Welfare Per Week**: Weekly hire of offices, canteen, drying room, toilets and stores.
- **Temporary Services and Waste Per Week**: Power, water, lighting, telecoms and skips, per week.
- **Plant Standing Per Week**: Weekly hire of plant that stands on site rather than belonging to a trade.
- **Setting Up (One-Off)**: Mobilisation: hoarding, gates, signage, hardstanding, first connections.
- **Clearing Away (One-Off)**: Demobilisation: removing everything and making the ground good.
- **Contract Sum**: The contract value, used for the value-related items and the percentage check.
- **Insurance and Bonds**: Contract works insurance, liability cover and any bond, as a percent of the sum.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Total preliminaries** | withheld until your rate is entered |

### US customary

| Result | Value |
|---|---|
| **Total preliminaries** | withheld until your rate is entered |

- Confidence: low.
- Withheld until you enter: Cost Per Person Per Week, Accommodation and Welfare Per Week, Temporary Services and Waste Per Week, Plant Standing Per Week. The site publishes no prices.

## How it is worked out

The method, derived in full:

- [Unit-Rate Estimating, Markup and Contingency](https://craftquantities.com/methodology/unit-rate-estimating-and-markup/): Why a 20% markup is not a 20% margin, why an estimate without a range is the wrong shape of answer, and why contingency should shrink as a design develops rather than staying at ten per cent forever.

What this calculation does not cover:

- Every rate here is a quote, not a published figure — the site does not carry regional prices for site staff, accommodation hire or plant standing.
- Head office overhead and profit are NOT included. These are the cost of running the site; the mark-up that carries the business sits on top and is a separate decision.
- Assumes one continuous period of possession. A phased or sectional contract carries its setting-up more than once and needs a run for each section.
- Attendances a main contractor provides to subcontractors — scaffold use, hoist time, task lighting, cleaning up after them — are often priced within the trades instead. Wherever they are, they must appear exactly once.

## Sources

As the calculator cites them (sources checked 2026-09-02):

- Standard methods of measurement (NRM 1/2 in the UK, and the general conditions divisions of CSI MasterFormat 01 in North America) classify site-running costs as fixed charges, time-related charges and value-related charges — the split that lets a change in programme be priced separately from a change in scope
- Preliminaries on a main building contract commonly run 8-15% of the contract sum, higher on small, short or constrained sites and lower on large repetitive ones, because the fixed element is spread over more value
- The time-related total divided by the programme duration is the weekly prolongation rate — the basis on which loss and expense is evaluated when an extension of time is granted. It excludes fixed charges, which are not incurred again by a delay

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What is the difference between preliminaries and overheads?**

Preliminaries are the cost of running THIS site: the manager standing in this compound, these huts, this hoist. Head office overhead is the cost of running the business that sent them — the office, the estimators, the accounts department, the directors — and it is recovered as a percentage across every job. Mixing them is how a contractor ends up recovering the same cost twice on one job and not at all on the next. Price the site here, then add overhead and profit on top of the whole estimate.

**Why separate the weekly rate from the fixed cost?**

Because a delay repeats one and not the other. If a job overruns by six weeks you carry six more weeks of staff, huts, services and standing plant — but you do not set the site up a second time, and your insurance does not increase because the contract sum has not changed. The weekly time-related rate is therefore the number an extension of time is priced on, and a claim built on a proportion of the total would wrongly include mobilisation. It is also the number that tells you what accelerating is worth: if a week costs this much to stand still, that is your budget for avoiding it.

**Should subcontractor attendances go in here?**

Wherever you put them, exactly once. A main contractor commonly provides scaffold use, hoist time, task lighting, water, power and clearing away for its subcontractors, and there are two consistent ways to handle it: price those items here as prelims and take them out of the subcontract rates, or leave the subcontractors to price their own and keep them out of here. What loses money is doing neither — assuming the subcontractor carries it while they assume you do — and what loses just as much is doing both, and pricing yourself out.

**My percentage came out much higher than 15%. Is the estimate wrong?**

Not necessarily: on a small or short job it is usually right, and a four-week job can easily show 25% or more against the 8-15% common on a main building contract. Setting a site up costs roughly the same whether the contract is worth 40,000 or 400,000 — the same hoarding, the same welfare, the same connections — so the fixed element lands far heavier on the smaller one, and that 25% can be perfectly correct. What the high figure should prompt is a look at the programme: every week carries the full weekly rate whether or not anything is happening on site, so a duration padded for comfort is expensive in a way a padded material quantity is not.

**Does this include the contractor's profit?**

No. Everything here is cost — what leaves the bank to keep the site running. Overhead recovery and profit are applied to the estimate as a whole, after the measured work and these preliminaries are added together, and they are a commercial decision rather than a calculation. Treating prelims as a place to hide margin makes both numbers untrustworthy: the day a client asks for the prelims build-up, or a delay has to be priced from it, an inflated weekly rate is very hard to defend.

## Related calculators

- [Delay Cost and Acceleration Break-Even Calculator](https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/)
- [Interim Payment Valuation Calculator (Certificate Due)](https://craftquantities.com/calculators/financial-adjacent/interim-payment-valuation-calculator/)
- [Scaffold Face Area and Hire Quantity Calculator](https://craftquantities.com/calculators/materials-quantities/scaffold-face-area-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/preliminaries-cost-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/preliminaries-cost-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `preliminaries-cost-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/preliminaries-cost-calculator.json

---
Source: https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.