# Repetition Learning Curve Calculator (Wright and Crawford)

> Total, last-unit and average time for a run of repeated units, from the first unit's time and a learning rate, under Wright's or Crawford's model.

Page: https://craftquantities.com/calculators/financial-adjacent/learning-curve-repetition-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.0, sources checked 2026-09-22, 6 published test vectors.

Total time for the run: 584 hours for Time for the First Unit 40 and Number of Units 20, the page's opening figures. Sources are cited below.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Time for the First Unit (hours) | `firstUnit` | 40 | 40 | range 0.01–100000 |
| Learning Rate (%) | `rate` | 90 | 90 | range 50–100 |
| Number of Units | `units` | 20 | 20 | range 1–10000 |
| Learning Curve Model | `model` | Crawford — each unit's own time falls | Crawford — each unit's own time falls | `crawford`, `wright` |

- **Time for the First Unit (hours)**: The hours the first repetition took, or is expected to take.
- **Learning Rate (%)**: The percentage the time falls to each time the number of units doubles.
- **Number of Units**: How many repetitions in the run.
- **Learning Curve Model**: Which quantity the learning rate applies to.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Total time for the run** | 584 hours |
| Time for unit 20, the last | 25.37 hours |
| Average time per unit | 29.22 hours |
| Time the run would take with no learning | 800 hours |
| Time the learning saves | 215.69 hours |

### US customary

| Result | Value |
|---|---|
| **Total time for the run** | 584 hours |
| Time for unit 20, the last | 25.37 hours |
| Average time per unit | 29.22 hours |
| Time the run would take with no learning | 800 hours |
| Time the learning saves | 215.69 hours |

- Confidence: medium.

## How it is worked out

Under Crawford's unit model at 90%, 20 units take 584.3 hours against 800.0 with no learning, and the last takes 25.4. The answer is only as good as the rate, which belongs to a crew and a task and is best measured from the first few units.

The working the page shows, in order: Time for unit 20, the last; Average time per unit; Time the run would take with no learning; Time the learning saves; then total time for the run.

The method, derived in full:

- [Programme Arithmetic: Durations, Float, Calendars and Learning](https://craftquantities.com/methodology/programme-arithmetic/): Why a duration is only as good as its output rate, why the critical path is the longest chain rather than the busiest, why twenty working days is four weeks, and why a repeated task gets faster by doublings.

What this calculation does not cover:

- It assumes the same crew repeats the same task without a break. A new crew, a long gap or a design change resets some of the learning, which the curve does not know.
- Learning does not continue for ever: crews reach a floor set by the work itself. Over a long run the curve understates the time for the later units.
- The two models give different answers at the same rate. A rate measured under one model should not be used in the other.

## Sources

As the calculator cites them (sources checked 2026-09-22):

- Crawford's unit learning curve: the time for the nth unit is T1 × n^b, where b = log(learning rate) ÷ log 2, so each doubling of the quantity multiplies the unit time by the learning rate; the run's total is the sum of the unit times
- Wright's cumulative average learning curve (T. P. Wright, 1936, Factors Affecting the Cost of Airplanes): the average time over the first n units is T1 × n^b, so the run's total is n times that average and the nth unit takes the difference between successive totals; the same rate gives a different answer under the two models

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What does a 90% learning rate mean?**

That each time the number of units doubles, the time falls to 90% of what it was. Under Crawford's model it is the unit's own time — the 2nd unit takes 90% of the 1st, the 4th 90% of the 2nd, the 8th 90% of the 4th. Under Wright's model it is the average — the average of the first two units is 90% of the first, the average of the first four 90% of that. 100% means no learning at all.

**Which model should I use?**

The one your rate was measured under. A rate worked out from the times of individual units is a Crawford rate; one worked out from running averages is a Wright rate. The same data gives two different rates under the two models, and using a rate in the wrong one gives the wrong total — Wright's model with a given rate always finishes sooner than Crawford's.

**What learning rate is realistic for construction?**

Measure it rather than borrow one. Repetitive site work does show learning — typical floors of a frame, identical houses, repeated precast lifts — but how much depends on the crew, the complexity of the task and how continuous the work is, and a rate from someone else's job describes their crew. Time the first few units and fit the rate to them.

**Why does the saving slow down?**

Because it is set by doublings. Going from 1 unit to 2 is a doubling, and so is going from 50 to 100, so the later units learn as much per doubling but need far more units to get there. On a long run the curve flattens, and in practice a crew reaches a floor the work itself sets.

## Related calculators

- [Activity Duration and Crew Size Calculator](https://craftquantities.com/calculators/financial-adjacent/activity-duration-crew-size-calculator/)
- [Labor Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/labor-cost-calculator/)
- [Critical Path and Float Calculator (CPM)](https://craftquantities.com/calculators/financial-adjacent/critical-path-float-calculator/)
- [Working Days to Finish Calculator](https://craftquantities.com/calculators/financial-adjacent/working-days-finish-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/learning-curve-repetition-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/learning-curve-repetition-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `learning-curve-repetition-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/learning-curve-repetition-calculator.json

---