# Interim Payment Valuation Calculator (Certificate Due)

> Net due on this month's interim valuation: gross value to date, retention against its limit, materials on site and earlier payments, in the right order.

Page: https://craftquantities.com/calculators/financial-adjacent/interim-payment-valuation-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-06, 4 published test vectors.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Contract Sum | `contractSum` | 900000 | 900000 | range 0–500000000 |
| Work Properly Executed To Date | `workCompletedGross` | 380000 | 380000 | range 0–500000000 |
| Agreed Variations To Date | `variationsAgreed` | 24000 | 24000 | range -500000000–500000000 |
| Materials On Site, Not Yet Built In | `materialsOnSite` | 18000 | 18000 | range 0–500000000 |
| Retention Rate | `retentionPercent` | 5 | 5 | range 0–20 |
| Retention Limit | `retentionCapPercent` | 3 | 3 | range 0–20 |
| Total Previously Certified | `previouslyCertified` | 300000 | 300000 | range 0–500000000 |
| Deductions and Contra Charges | `contraCharges` | 0 | 0 | range 0–500000000 |

- **Contract Sum**: The original contract sum, before variations.
- **Work Properly Executed To Date**: Cumulative value of measured work completed, not this month's slice.
- **Agreed Variations To Date**: Cumulative value of variations agreed and executed. Omissions go in negative.
- **Materials On Site, Not Yet Built In**: Unfixed materials delivered and stored on site.
- **Retention Rate**: Percent withheld from the cumulative gross valuation.
- **Retention Limit**: Maximum retention held, as a percent of the contract sum. Enter 0 for no limit.
- **Total Previously Certified**: Sum of all previous certificates, net of retention, before this one.
- **Deductions and Contra Charges**: Anything the contract lets the payer deduct from this certificate.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Net due on this certificate** | $100,900 |
| Gross valuation to date | $422,000 |
| Retention held | $21,100 |
| Valuation less retention | $400,900 |
| Less previously certified | $300,000 |
| Less deductions | $0 |
| Progress against the adjusted sum | 45.67 % |
| Net due, unrounded | $100,900 |

### US customary

| Result | Value |
|---|---|
| **Net due on this certificate** | $100,900 |
| Gross valuation to date | $422,000 |
| Retention held | $21,100 |
| Valuation less retention | $400,900 |
| Less previously certified | $300,000 |
| Less deductions | $0 |
| Progress against the adjusted sum | 45.67 % |
| Net due, unrounded | $100,900 |

## How it is worked out

Retention is still accruing at 5% and will stop at 27000, which on these figures is a cumulative gross of about 540000. Keep the materials-on-site line separate month to month: as each batch is built in it moves into the measured work, and a batch left in both places is paid for twice.

The working the page shows, in order: Gross valuation to date; Retention held; Valuation less retention; Less previously certified; Less deductions; Progress against the adjusted sum; Net due, unrounded; then net due on this certificate.

The method, derived in full:

- [Interim Valuations, Variations and the Cost of Delay](https://craftquantities.com/methodology/payment-variations-and-delay/): Why a contractor finances the retention on every project, why a change costs far more late than early, and why a skip that looks half empty can already be over its weight limit.

What this calculation does not cover:

- The contract governs, not this page: the rate, the limit, what counts as properly executed and whether a deduction has been validly notified are all things it decides.
- Sales tax is excluded on every line. It is added to the certified amount at the end, on whatever basis the contract and the jurisdiction set.
- Assumes retention at one rate. Where a contract halves the rate at practical completion, run the two periods separately.
- Off-site materials are not distinguished here; most standard forms exclude them without a vesting certificate and a bond, so they usually do not belong in the materials line at all.
- No interest, financing charge or late-payment entitlement is calculated.

A professional must decide:

- Electrics: circuit design, protection, cable sizing and the work itself are for a qualified or licensed electrician, under the rules where you build.

## Sources

As the calculator cites them (sources checked 2026-09-06):

- Standard forms of building contract (JCT, NEC, FIDIC and the AIA payment application) all value interim payments on the CUMULATIVE value of work properly executed to the valuation date, deduct retention from that cumulative figure, and then deduct the total previously certified — so an over- or under-measure in an earlier month self-corrects rather than compounding
- Retention is commonly deducted at 5% of the cumulative gross valuation, LIMITED to a total of 3% of the contract sum; once that limit is reached no further retention is withheld, however much work follows
- Materials and goods on site but not yet incorporated are payable in most standard forms where they are on site at the right time, adequately protected and reasonably brought there; title then passes TO the employer once the amount has been included in a certificate and paid. Materials stored OFF site are treated far more strictly and are commonly excluded entirely without a vesting agreement and a bond

The site's pages for the documents these name:

- [National Electrical Code (NFPA 70)](https://craftquantities.com/standards/nfpa/nec/)

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**Why value the whole job again every month instead of just this month's work?**

Because measurement is never final until it is. Valuing cumulatively and deducting everything previously certified means an error in any earlier month corrects itself the moment it is spotted — the certificate simply comes out smaller, with no credit note, no adjustment line and no argument about which month it belonged to. Valuing month by month locks every mistake in place and forces a separate correction that somebody has to agree to, which on a difficult job is exactly the conversation nobody has.

**What is the difference between the retention rate and the retention limit?**

The rate is how fast retention accrues; the limit is where it stops. A common pairing is 5% withheld up to a maximum of 3% of the contract sum, which means retention accumulates for the first 60% of the job and then stops entirely. Applying the rate without the limit under-values every certificate for the back half of the contract — a 900,000 job at that pairing leaves about 9,200 uncollected on a single certificate near the end — and that is money owed, not money at risk.

**Should materials on site be in the valuation at all?**

In most standard forms yes, but conditionally: they must be on site, delivered at the right time rather than prematurely, adequately protected and insured. Note the direction of the ownership test, which is the opposite of the way it is often stated: employer ownership is a CONSEQUENCE of certification and payment, not a precondition of valuing the materials — title passes once the amount has been certified and paid. What does defeat a claim is the contractor not having good title to pass on, typically because a supplier's retention-of-title clause is still live, and ownership must have passed to the employer. Materials stored OFF site are usually excluded entirely unless the contract specifically allows them, and then only with a vesting certificate and often a bond. Keep the line separate and reduce it as each batch is built in — the value moves into the measured work at that point, and a batch left in both places is paid for twice, which is the sort of thing that gets found in a final account when there is no goodwill left to spend on it.

**Can a certificate be negative?**

Arithmetically yes, and it means more has been certified than the work now supports — usually because an earlier valuation over-measured, or because a deduction has landed that exceeds the month's progress. What happens next is a contract question rather than an arithmetic one: several standard forms carry a negative forward against the next certificate rather than creating a debt payable immediately. Check the payment provisions before issuing one, because getting that wrong turns a bookkeeping correction into a dispute.

**Does this tell me when I will be paid?**

No — it tells you what the certificate should come to. When the money arrives depends on the payment terms: the date the application is due, the date the certificate must be issued, and the final date for payment, all of which the contract sets and all of which are separate from the amount. The working capital panel inside My Project on this site takes those terms alongside a programme and shows what the lag costs while it runs — the peak of your own money in the job, and when the retention comes back — which is the other half of the same question.

## Related calculators

- [Construction Preliminaries (General Conditions) Calculator](https://craftquantities.com/calculators/financial-adjacent/preliminaries-cost-calculator/)
- [Delay Cost and Acceleration Break-Even Calculator](https://craftquantities.com/calculators/financial-adjacent/delay-cost-acceleration-calculator/)
- [Change Order Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/change-order-cost-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/interim-payment-valuation-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/interim-payment-valuation-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `interim-payment-valuation-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/interim-payment-valuation-calculator.json

---
Source: https://craftquantities.com/calculators/financial-adjacent/interim-payment-valuation-calculator/