# Earned Value Management (EVM) Calculator

> CPI, SPI, variances and a forecast at completion from planned value, earned value and actual cost.

Page: https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/ (calculator). This is the page's Markdown copy; the HTML page is the canonical version.

Version 1.0.1, sources checked 2026-09-06, 4 published test vectors.

## Inputs

A length, area or volume is entered with its unit. The page opens on the values below: a metric reader sees the metric column, a US customary reader the other.

| Input | id | Opens at (metric) | Opens at (US customary) | Accepts |
|---|---|---|---|---|
| Budget at completion (BAC) | `bac` | 1000000 | 1000000 | range 1–10000000000 |
| Planned value (PV) | `pv` | 400000 | 400000 | range 0–10000000000 |
| Earned value (EV) | `ev` | 360000 | 360000 | range 0–10000000000 |
| Actual cost (AC) | `ac` | 420000 | 420000 | range 0–10000000000 |

- **Budget at completion (BAC)**: Total authorised budget for the work.
- **Planned value (PV)**: Budgeted cost of work scheduled to date.
- **Earned value (EV)**: Budgeted cost of work actually completed.
- **Actual cost (AC)**: What has actually been spent on that work.

## The answer on the opening values

Worked exactly as the page works it, on the values each system opens on.

### Metric

| Result | Value |
|---|---|
| **Estimate at completion** | $1,166,667 |
| Cost performance index (CPI) | 0.86 |
| Schedule performance index (SPI) | 0.9 |
| Cost variance (CV) | $-60,000 |
| Schedule variance (SV) | $-40,000 |
| Variance at completion (VAC) | $-166,667 |
| Estimate to complete (ETC) | $746,667 |
| To-complete performance index (TCPI) | 1.1 |
| Percent complete | 36 % |
| Percent spent | 42 % |

### US customary

| Result | Value |
|---|---|
| **Estimate at completion** | $1,166,667 |
| Cost performance index (CPI) | 0.86 |
| Schedule performance index (SPI) | 0.9 |
| Cost variance (CV) | $-60,000 |
| Schedule variance (SV) | $-40,000 |
| Variance at completion (VAC) | $-166,667 |
| Estimate to complete (ETC) | $746,667 |
| To-complete performance index (TCPI) | 1.1 |
| Percent complete | 36 % |
| Percent spent | 42 % |

## How it is worked out

Over budget and behind schedule on the figures given. TCPI shows the efficiency the remaining work would need to still land on budget.

The working the page shows, in order: Cost performance index (CPI); Schedule performance index (SPI); Cost variance (CV); Schedule variance (SV); Variance at completion (VAC); Estimate to complete (ETC); To-complete performance index (TCPI); Percent complete; Percent spent; then estimate at completion.

The method, derived in full:

- [Earned Value Indices](https://craftquantities.com/methodology/earned-value-indices/): How three numbers become a forecast, why the schedule index lies at the end of a project, and what TCPI is really asking.

What this calculation does not cover:

- Every figure is only as good as the earned value input. Optimistic percent-complete reporting produces a healthy CPI on a failing project, and it is the standard failure mode of EVM in practice.
- SPI is measured in currency, not time, and it converges to 1.0 as a project finishes regardless of how late it is — a project delivered a year late still ends with SPI = 1. Use the schedule network for time performance, not this index.
- EAC here assumes current cost performance continues. Other sanctioned formulas assume the remainder runs to plan, or weight cost and schedule together; they give materially different answers on a troubled project.

## Sources

As the calculator cites them (sources checked 2026-09-06):

- PMBOK earned value definitions: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV
- EAC = BAC ÷ CPI where current cost performance is expected to continue; the most commonly used of several sanctioned formulas

A code or standard has force only where a jurisdiction has adopted it, usually with local amendments; check what is in force with the authority where you build.

## Questions answered on the page

**What does CPI actually tell me?**

How much value you are getting per unit of money spent. A CPI of 0.857 means that for every pound spent you have earned 85.7 pence of budgeted work — you are getting about six pounds of progress for every seven you spend. Projected across the whole budget, that is where the estimate at completion comes from, and it is why a small CPI shortfall early is a large number at the end.

**Why is SPI misleading late in a project?**

Because it is measured in currency rather than time, and it mathematically converges to 1.0 as the work finishes. At completion, earned value equals planned value by definition — so a project delivered a year late still ends with a perfect schedule index. SPI is useful in the middle of a project and worthless at the end; time performance belongs to the schedule network.

**What is TCPI for?**

It is the reality check. TCPI is the cost efficiency the remaining work would have to achieve to still finish on the original budget. If your CPI is 0.86 and your TCPI is 1.12, you are being asked to believe the team will suddenly become thirty percent more efficient than it has been all project. Quantifying that gap is usually the most useful thing EVM does.

**Can EVM be gamed?**

Easily, and it usually is. Every index depends on earned value, and earned value depends on someone's assessment of what is complete. Optimistic percent-complete reporting produces a healthy CPI on a failing project right up until the last month. The defence is objective measures — units installed, milestones passed, tests witnessed — rather than a judgement of how far along something feels.

## Related calculators

- [Change Order Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/change-order-cost-calculator/)
- [Renovation Budget Calculator](https://craftquantities.com/calculators/financial-adjacent/renovation-budget-calculator/)
- [Cost to Build a House Calculator](https://craftquantities.com/calculators/financial-adjacent/cost-to-build-house-calculator/)
- [Change Order Cost Calculator](https://craftquantities.com/calculators/financial-adjacent/change-order-cost-calculator/)

## Run it from a program

- REST: `GET https://api.craftquantities.com/v1/calculate/earned-value-management-calculator` with each input as a query parameter, a length, area or volume with its unit; `https://api.craftquantities.com/v1/describe/earned-value-management-calculator` lists the inputs.
- MCP: the `calculate` tool at https://api.craftquantities.com/mcp with `slug` `earned-value-management-calculator`.
- Definition and test vectors: https://craftquantities.com/api/v1/calculators/earned-value-management-calculator.json

---
Source: https://craftquantities.com/calculators/financial-adjacent/earned-value-management-calculator/
Craft Quantities: free to read, cite and link to; the pages are not licensed for republication. Quantities only: no prices, no design and no certification.